2 LIU / HL-LHC Cost and Schedule Review
17-19 October 2016 17-19 October 2016

3 LIU-Safety aspects and documentation
Anne Funken BE-ASR, Project Safety Officer Joachim Vollaire, Helmut Vincke, Robert Froeschl, Luisa Ulrici, Doris Forkel-Wirth, Stefan Roesler HSE-RP Table of contents: General safety Safety organisation Status of the documentation Conventional Waste handling Next steps towards equipment installation and beam permit Radiation protection RP documentation and studies Radiological impact of operation with LIU parameters New RP instrumentation Radioactive Waste Budget and operational RP 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review

4 Safety organisation of the LIU project
In accordance with the Safety Regulation SR- SO, the Project Leader (PL) is responsible for Safety in the Project The PL is assisted by a Project Safety Officer (PSO) who oversees and coordinates Safety aspects of the Project: The PSO verifies that Safety aspects have been correctly considered within the different work packages, that the proposed Safety measures are consistent with the general Safety policy of the Project and that they are correctly applied by the different work packages, The PSO identifies the Safety issues arising at the interface between work packages and whenever required, asks the relevant work packages to apply the appropriate measures, The PSO coordinates the editorial work for the Safety documentation of the Project. The work package Holders are responsible for proposing and applying the correct Safety measures for the work and equipment included in their work package HSE produces the Launch Safety Agreements (LSA) for non radiological aspects that details the Safety requirements and delivers the safety clearances when applicable. The Radiation Protection Group takes responsibility for all radiation protection aspects. 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review Safety : A. Funken, J. Vollaire, R. Froeschl, H. Vincke, L. Ulrici

5 Safety documentation of the LIU project
As for all projects, a safety documentation (Safety File) is required to demonstrate that the new systems or facilities: Are being designed respecting safety principles and Can be constructed, commissioned, operated and dismantled safely It covers occupational health and safety, the protection of the environment and the safe operation of CERN’s Installations The LIU project is divided in Work Packages (WP), i.e equipment or services delivered by the different groups. Each WP has one WP Holder Due to the extend of the project that covers the upgrade of five different accelerators, the concept of Safety Package (SP) was introduced 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review Safety : A. Funken, J. Vollaire, R. Froeschl, H. Vincke, L. Ulrici

6 Concept of Safety Package: LIU-PSB example
PSB Rings Injection Extraction (BTY excluded) 4. New bldg.245 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review Safety : A. Funken, J. Vollaire, R. Froeschl, H. Vincke, L. Ulrici

7 Safety documentation of the LIU project: LIU-PSB example
PSB Safety File Part 1 Descriptive Part 2 Demonstrative Part 3 Operational Part 4 REM Once the system/facility of a SP is in operation, the corresponding parts of the Safety File will be attached to the Safety File of the PSB Goal, motivation, brief description of the systems/facility focusing on the safety aspects Part 1 Descriptive List of hazards, risks assessment, mitigation measures Part 2 Demonstrative List of procedures required to operate and maintain the systems/facility safely, to dismantle it and dispose of its components safely Part 3 Operational Safety documents which demonstrate the compliance: test reports, certificates of conformity Inspections, safety reports, non-conformities, near-misses, incidents/accidents, experience gained Part 4 Records, Experience, Monitoring (REM) LIU-PSB Safety Files PSB-Rings PSB-Bldg.245 PSB-Extraction PSB-Injection Documents are stored in EDMS 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review Safety : A. Funken, J. Vollaire, R. Froeschl, H. Vincke, L. Ulrici

8 Status of the safety documentation
(*) (*) I. Kobzeva replaced by D. Carloni as from Conventional hazards identified at this stage 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review Safety : A. Funken, J. Vollaire, R. Froeschl, H. Vincke, L. Ulrici

9 Status of the safety documentation
(*) (*) I. Kobzeva replaced by D. Carloni as from 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review Safety : A. Funken, J. Vollaire, R. Froeschl, H. Vincke, L. Ulrici

10 Conventional Waste handling
Waste inventory required according to the LSA HSE template recently proposed for the non-radioactive waste inventory/forecast, considering the waste categories that are already declared through the CERN-wide annual waste inventory Inventory to be filled in during the project phase, focussing on operation, shall inform about the annual waste production Courtesy: Sonja Kleiner, Beatriz Leon HSE-SEE Environment 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review Safety : A. Funken, J. Vollaire, R. Froeschl, H. Vincke, L. Ulrici

11 Next steps towards equipment installation and beam permit
Safety milestones: Approval and release of the Safety files of the LIU Safety Packages HSE-SEE regulatory controls Resources on overall CERN HSE-SEE budget Safety file compliance Verification that the prevention and controls measures defined in the Safety Files are implemented and functional Hardware permits and Beam permits Check-list of controls signed off by the corresponding responsible persons (installation completeness, access safety system, safety file compliance, DSO tests, patrol, RP) 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review Safety : A. Funken, J. Vollaire, R. Froeschl, H. Vincke, L. Ulrici

12 RP documentation and RP studies
RP work-packages within LIU (PSB, PS, SPS and LIU ions) RP performs studies and advises for upgrades with radiological implications (beam dumps, collimators, scrapers, energy increase, beam losses…) Studies documented in Technical Notes and are being summarized in RP Safety Files (stray radiation and shielding, residual dose rate, induced activity, air and cooling water activation, RP monitoring…) mSv/h Examples of studies (FLUKA code): SPS beam dump – Residual dose rate 1 week cooling time PS internal beam dump study (stray radiation with dump in SS75) PSB injection – Residual dose rate 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review Safety : A. Funken, J. Vollaire, R. Froeschl, H. Vincke, L. Ulrici

13 Radiological impact of operation with LIU parameters
Effects (from a RP standpoint) of beam energy and beam intensity increase have been assessed and mitigated when needed: New charge-exchange injection at 160 MeV in the PSB PSB extraction and PS injection at 2 GeV (instead of 1.4 GeV) Shielding re-enforced in LS1 above the injection and extraction areas of the PS (mandatory for long term PS operation) Detailed RP studies for new intercepting devices (design optimization: shielding and intervention scenario) PSB: Beam dump (installed in LS1), new PSB scrappers PS: Replacement of internal beam dumps in SS47/SS48 SPS: Unshielded beam dump (in LSS1) replaced by new one in LSS5 with appropriate shielding. Scrappers, TCDI collimators in transfer lines are also being studied. LIU ions: no impact on the radiological situation (Linac3, LEIR, PS and SPS) 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review Safety : A. Funken, J. Vollaire, R. Froeschl, H. Vincke, L. Ulrici

14 New RP instrumentation
Defined as part of RP studies: Stray radiation monitors (example: above the new PS internal dumps…) Induced activity monitors (inside the machine) close to beam intercepting devices PS ring: four new ventilation exhaust stacks equipped with activated air monitors in LS1 (requirements for new facility) Stray radiation monitor on top of PSB dump Induced activity monitor inside the PS ring New ventilation exhaust for the PS ring Bungalow with monitors Sampling 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review Safety : A. Funken, J. Vollaire, R. Froeschl, H. Vincke, L. Ulrici

15 Radioactive waste A budget of about 5 MCHF per year is allocated to the management of CERN’s radioactive waste The forecast of all radioactive waste that will be produced until 2034 is available, based on information provided by the CERN groups and experiments (data collection as of December 2015 – Regularly updated) The elimination of radioactive waste is planned such to allow the reception and temporary storage of the forecasted waste produced until the end of LS2 (Goal: elimination of about 3700 m3) Period January - September 2016: for the first time, the amount of eliminated waste (1050 m3) exceeded the volume received (571 m3) 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review Safety : A. Funken, J. Vollaire, R. Froeschl, H. Vincke, L. Ulrici

16 Waste forecast for The current radioactive waste forecast is not listed per project but per group or experiment An update identifying the radioactive waste linked to LIU and HL-LHC projects is ongoing and will be available at the beginning of 2017 For comparison: the volume of waste received in LS1 is about 1800 m3 over 18 months 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review Safety : A. Funken, J. Vollaire, R. Froeschl, H. Vincke, L. Ulrici

17 Remaining budget and operational Radiation Protection
[kCHF] Cost to Completion Comments PSB 11 8 Half Sector Test (test of charge exchange injection in the Linac4 transfer line) in 2016 / 2017 PS 94 RP monitoring (new internal dump position for example) and RP personnel support in LS2 SPS 350 RP monitoring and mainly RP personnel support in LS2 Remaining budget for identified activities is adequate Manpower for studies and documentation tight (relying on fellows) Operational Radiation Protection: RP requirements transmitted in LS2 preparatory meetings and facility coordination meetings (training, ALARA, operational dosimetry, traceability, waste acceptance criteria….) RP cool-down requirements for access to facility integrated in overall LS2 planning 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review Safety : A. Funken, J. Vollaire, R. Froeschl, H. Vincke, L. Ulrici

18 Summary The LIU Safety structure is in place and Safety well integrated in the project Editorial work for the Safety documentation is ongoing Ionizing radiation hazards well identified and mitigated (design of new systems and operation of injectors complex with LIU parameters) Budget adequate for RP activities Manpower tight (relying on fellows for missing staff resources) 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review Safety : A. Funken, J. Vollaire, R. Froeschl, H. Vincke, L. Ulrici

19 Spare slides 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review
Safety : A. Funken, J. Vollaire, R. Froeschl, H. Vincke, L. Ulrici

20 LIU Safety Packages A SP comprises a set of systems located in a same location under the responsibility of several groups. The LIU project includes 16 SPs (and 90 WPs). A Safety Package Coordinator (SPC) is appointed for each SP. The SPC is acting as the technical link person for the corresponding SP. A SP does not change the fact that each group remains owner and responsible of their own Work Package (WP), which are covering their equipment or services. The HSE Launch Safety Agreements (LSA) covering the conventional safety aspects are produced at the level of the SPs. 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review Safety : A. Funken, J. Vollaire, R. Froeschl, H. Vincke, L. Ulrici

21 Storage of the safety documentation for the LIU project
Operation phase Project phase 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review Safety : A. Funken, J. Vollaire, R. Froeschl, H. Vincke, L. Ulrici

22 Safety during shutdown installation
Documents to be provided by the equipment groups according to the HSE LSA: design compliance, conformity of equipment, procedures (part of the Safety Files of the SPs) Standard CERN-wide procedures applicable (IMPACT, Joint Inspection Visits, TREC, ALARA). Facility coordination meetings at machine level ensure the management of the planning and the coactivity. Safety Support Officer LS2 appointed for the injectors. 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review Safety : A. Funken, J. Vollaire, R. Froeschl, H. Vincke, L. Ulrici

23 Safety permits A Safety permit will be issued for each major phase
Installation phase Hardware Commissioning Beam Commissioning Hardware (Commissioning) Permit Beam Permit Courtesy: Christelle Gaignant 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review Safety : A. Funken, J. Vollaire, R. Froeschl, H. Vincke, L. Ulrici

24