Presentation is loading. Please wait.

Presentation is loading. Please wait.

Chapter 13 MRP and ERP.

Similar presentations


Presentation on theme: "Chapter 13 MRP and ERP."— Presentation transcript:

1 Chapter 13 MRP and ERP

2 Material requirements planning (MRP)
Material requirements planning (MRP) Computer-based information system that translates master schedule requirements for end items into time-phased requirements for subassemblies, components, and raw materials. BOM MRP MPS Current Availabilities Planned Order Releases Priority Planning Lead Times Lot Sizing Policies

3 Independent and Dependent Demand
Independent Demand A Dependent Demand B(4) C(2) D(2) E(1) D(3) F(2) Independent demand is uncertain. Dependent demand is certain.

4 Dependant Demand Dependent demand: Demand for items that are subassemblies or component parts to be used in production of finished goods. Once the independent demand is known, the dependent demand can be determined.

5 Dependent vs Independent Demand
“Lumpy” demand Demand Stable demand Demand Time Time Amount on hand Amount on hand Safety stock Time Time Figure 14.1

6 Overview of MRP Figure 14.2 MRP Inputs MRP Processing MRP Outputs
Master schedule Bill of materials Inventory records MRP computer programs Changes Order releases Planned-order schedules Exception reports Planning reports Performance- control reports transaction Primary Secondary Figure 14.2

7 MRP Inputs Product Structure Tree Lead Times
Master Production Schedule Time-phased plan specifying timing and quantity of production for each end item. Material Requirement Planning Process Product Structure Tree Lead Times

8 Master Schedule Master schedule Cumulative lead time
One of three primary inputs in MRP; states which end items are to be produced, when these are needed, and in what quantities. Cumulative lead time The sum of the lead times that sequential phases of a process require, from ordering of parts or raw materials to completion of final assembly.

9 Planning Horizon Figure 14.4 1 2 3 4 5 6 7 8 9 10 Time Period (weeks)
Procurement Fabrication Subassembly Assembly Time Period (weeks) Figure 14.4

10 Bill-of-Materials Bill of materials (BOM): One of the three primary inputs of MRP; a listing of all of the raw materials, parts, subassemblies, and assemblies needed to produce one unit of a product. Product structure tree: Visual depiction of the requirements in a bill of materials, where all components are listed by levels. Low-level coding: Restructuring the bill of materials so that multiple occurrences of a component all coincide with the lowest level the component occurs

11 Bill of Materials Bill of Materials – Parent-child diagram that shows what goes into what. Used to make sure enough parts for production plan Each part has LT, ordering policy One BOM for every end product Bike Frame Assy Wheel Assy Components Wheel Tires Hubs & Rims Spokes

12 Product Structure Tree
Chair Seat Legs (2) Cross bar Side Rails (2) Back Supports (3) Leg Assembly Level 1 2 3 Figure 14.5

13 Inventory Records One of the three primary inputs in MRP
Includes information on the status of each item by time period Gross requirements Scheduled receipts Amount on hand Lead times Lot sizes And more …

14 Inventory Requirements
Net requirements: Net Requirements = Gross Requirements – Available Inventory Available Inventory: Available Inventory = Projected on hand – Safety stock – Inventory allocated to other items

15 Assembly Time Chart Figure 14.7 1 2 3 4 5 6 7 8 9 10 11 Procurement of
raw material D raw material F part C part H raw material I Fabrication of part G of part E Subassembly A Subassembly B Final assembly and inspection 1 2 3 4 5 6 7 8 9 10 11

16 MRP Processing- Outputs
Gross requirements Total expected demand Scheduled receipts Open orders scheduled to arrive Planned on hand Expected inventory on hand at the beginning of each time period

17 MRP Processing- Outputs …
Net requirements Actual amount needed in each time period Planned-order receipts Quantity expected to received at the beginning of the period Offset by lead time Planned-order releases Planned amount to order in each time period

18 Updating the System Regenerative system Net-change system
Updates MRP records periodically Net-change system Updates MPR records continuously

19 MRP Primary Reports Planned orders - schedule indicating the amount and timing of future orders. Order releases - Authorization for the execution of planned orders. Changes - revisions of due dates or order quantities, or cancellations of orders.

20 MRP Secondary Reports Performance-control reports Planning reports
Exception reports

21 Other Considerations Safety Stock Lot sizing Lot-for-lot ordering
Economic order quantity Fixed-period ordering

22 MRP in Services Food catering service Hotel renovation
End item => catered food Dependent demand => ingredients for each recipe, i.e. bill of materials Hotel renovation Activities and materials “exploded” into component parts for cost estimation and scheduling

23 Benefits of MRP Low levels of in-process inventories
Ability to track material requirements Ability to evaluate capacity requirements Means of allocating production time Ability to easily determine inventory usage by backflushing Backflushing: Exploding an end item’s bill of materials to determine the quantities of the components that were used to make the item. And issue the materials after production.

24 Requirements of MRP Computer and necessary software
Accurate and up-to-date Master schedules Bills of materials Inventory records Integrity of data

25 Example 2 Plant produces Wood Shutter Book Cases 1 2 3 4 5 6 7 8 100
Quantity 100 150 Shutter Assembly LT = 1 Frames (2) Order LT =2 Wood Section (4) Fabrication LT = 1 Schedule Re. W 1 = 70

26 Shutter 1 2 3 4 5 6 7 8 Quantity 100 150 Shutter 1 2 3 4 5 6 7 8 Gross Req. 100 150 Scheduled Receipts Projected on hand Net requirement Planned order receipts Planned order release

27 Shutter 1 2 3 4 5 6 7 8 Planned order release 100 150 Frames 1 2 3 4 5 6 7 8 Gross Req. 200 300 Scheduled Receipts Projected on hand Net requirement Planned order receipts Planned order release

28 SAMPLE MRP Report

29 Computing the item Scheduled Releases
Safety Stock Requirements Lot Sizing Policy Lead Time Parent Sched. Rel. Gross Reqs Planned Order Releases Planned Order Receipts Synthesizing item demand series Projecting Inv. Positions and Net Reqs. Lot Sizing Time- Phasing Net Reqs Item External Demand Scheduled Receipts Initial Inventory

30 Lot Sizing If affordable, a lot-for-lot (L4L) policy will incur the lowest inventory holding costs and it will maintain a smoother production flow. Possible reasons for departure from a L4L policy: High set up times and costs => need for serial process batching to control the capacity losses Processes that require a large production volume in order to maintain a high utilization (e.g., fermentors, furnaces, etc.) => need for parallel process batching Selection of a pertinent process batch size It must be large enough to maintain feasibility of the production requirements It must control the incurred inventory holding costs, and/or part delays (this is a measure of disruption to the production flow caused by batching) Move or transfer batches: The quantities in which parts are moved between the successive processing stations. They should be as small as possible to maintain a smooth process flow

31 Some Lot Sizing Methods employed in the traditional MRP framework
Main focus: Balance set-up and holding costs Wagner-Whitin Algorithm for dynamic Lot Sizing Economic Order Quantity (EOQ): Compute a lot size using the EOQ formula with the demand rate D set equal to the average of the net requirements observed over the considered planning horizon. Periodic Order Quantity (POQ): Compute T = round(EOQ/D), and every time you schedule a new lot, size it to cover the net requirements for the subsequent T periods.

32 Some Lot Sizing Methods employed in the traditional MRP framework …
Silver-Meal (SM): Every time you start a new lot, keep adding the net requirements of the subsequent periods, as long as the average (setup plus holding) cost per period decreases. Least Unit Cost (LUC): Every time you start a new lot, keep adding the net requirements of the subsequent periods, as long as the average (setup plus holding) cost per unit decreases. Part Period Balancing (PPB): Every time you start a new lot, add a number of subsequent periods such that the total holding cost matches the lot set up cost as much as possible.

33 MRP II Expanded MRP with emphasis placed on integration
Financial planning Marketing Engineering Purchasing Manufacturing

34 MRP II Figure 14.14 Market Demand Production plan Problems? Rough-cut
capacity planning Yes No Finance Marketing Manufacturing Adjust production plan Master production schedule MRP Capacity planning Requirements schedules Adjust master schedule

35 Capacity Planning Capacity requirements planning: The process of determining short-range capacity requirements. Load reports: Department or work center reports that compare known and expected future capacity requirements with projected capacity availability. Time fences: Series of time intervals during which order changes are allowed or restricted.

36 Capacity Planning Figure 14.15 Develop a tentative master production
schedule Use MRP to simulate material requirements Rough-cut capacity planning Firm up a portion of the MPS Is shop capacity adequate? Can capacity be changed to meet Revise tentative Change Yes No

37 Solved Problem 3 Std. Times Prod. Schedule Labor 0.5 hrs/unit Week 1 2
4 Machines Quantity 200 300 100 150 Labor hr 50 75 Av. Capacity Machine hrs hrs Labor Util. 50.00% 75.00% 25.00% 37.50% 250 Machine Util. 80.00% 120.00% 40.00% 60.00%

38 MRP in Services Service applications such as: Professional services
Postal services Retail Banking Healthcare Higher education Engineering Logistical services Real estate

39 Enterprise resource planning (ERP)
MRP >> MRPII >> ERP Integration of financial, manufacturing, and human resources on a single computer system.

40 ERP Software ERP software provides a system to capture and make data available in real time to decision makers and other users in the organization Provides tools for planning and monitoring various business processes Includes Production planning and scheduling Inventory management Product costing Distribution

41 ERP Strategy Considerations
High initial cost High cost to maintain Future upgrades Training

42

43 Learning Objectives Describe the conditions under which MRP is most appropriate. Describe the inputs, outputs, and nature of MRP processing. Explain how requirements in a master production schedule are translated into material requirements for lower-level items. Discuss the benefits and requirements of MRP.

44 Learning Objectives Explain how an MRP system is useful in capacity requirements planning. Outline the potential benefits and some of the difficulties users have encountered with MRP. Describe MRP II and its benefits. Describe ERP, what it provides, and its hidden costs.


Download ppt "Chapter 13 MRP and ERP."

Similar presentations


Ads by Google