Presentation is loading. Please wait.

Presentation is loading. Please wait.

HIGH TENSION CABLE BARRIER IN THE MEDIAN OF A FREEWAY IN ALBERTA, CANADA: A CASE STUDY OF TWO SUCCESSFUL PROJECTS TRB First International Roadside Safety.

Similar presentations


Presentation on theme: "HIGH TENSION CABLE BARRIER IN THE MEDIAN OF A FREEWAY IN ALBERTA, CANADA: A CASE STUDY OF TWO SUCCESSFUL PROJECTS TRB First International Roadside Safety."— Presentation transcript:

1 HIGH TENSION CABLE BARRIER IN THE MEDIAN OF A FREEWAY IN ALBERTA, CANADA: A CASE STUDY OF TWO SUCCESSFUL PROJECTS TRB First International Roadside Safety Conference, June 2017, San Francisco, California Paul Steel, Masood Hassan & Gerard Kennedy - Tetra Tech Canada Bill Kenny - Alberta Transportation

2 PURPOSE & OUTLINE OF PRESENTATION
The purpose is to highlight interesting features of, and experience with, two successful high tension cable barrier (HTCB) projects in Alberta, Canada, that would be of interest to road safety professionals around the world. Outline of presentation Description of the two projects Important design considerations Safety effectiveness Benefit-Cost analysis Innovative construction techniques Operation and maintenance experience Concluding comments

3 HIGH TENSION CABLE BARRIERS
Pre-stretched, post-tensioned; 3- or 4-cable galvanized steel cables; 1,000ft lengths joined by turnbuckles Proprietary systems (posts, terminals, foundations, post spacing, test deflection, etc.) Acceptance by US Federal Highway Administration (FHWA) based on independent tests at various Test Levels. Guidelines by FHWA and American Association of State Highway & Transportation Officials (AASHTO)

4 LOCATION OF THE TWO HTCB PROJECTS IN ALBERTA, CANADA

5 SUMMARY CHARACTERISTICS OF THE TWO ALBERTA HTCB PROECTS
ITEM DEERFOOT TRAIL, WITHIN CITY OF CALGARY HIGHWAY 2, CALGARY NORTHWARD Cross section 6-lane divided 4- to 6-lane divided Median type Depressed median Median width 16m to 31m 9m to 18m Median side slopes 6:1 4:1 to 6:1 Cable barrier project length 11 highway-km 11 HTCB-km 122 highway-km 133 HTCB-km (11km on both sides) Traffic volume (AADT) 154,000 29,000 to 34,000 Speed limit 100 – 110 km/hr 110 km/hr Year of HTCB constr’n 2007 2010 No. of cables 3 cables 4 cables

6 SALIENT DESIGN ELEMENTS OF THE TWO ALBERTA HTCB PROJECTS
DOT’s Design Bulletin for HTCB did not exist at the time Consulted FHWA and AASHTO and US State-DOT officials At least two FHWA-accepted HTCB systems must be eligible Max. test deflection = 2.4m (8ft); Max. post spacing = 6.1m (20ft) Cast-in-place concrete or driven steel foundations for posts and terminals acceptable (For Highway 2, precast concrete terminal foundations were allowed, with consequent movement problems) Supplier’s design for terminal foundations to be confirmed or modified by an Alberta-certified geotechnical engineer on the basis of subsoil data

7 SALIENT DESIGN ELEMENTS OF THE TWO ALBERTA HTCB PROECTS (Cont’d)
Placement in the Median FHWA guidelines applied Placing near the shoulder preferred, provided the distance to the painted shoulder line, and to un- protected hazards in the median, exceeds the maximum specified (test) deflection. If this condition cannot be met, the HTCB should be installed in the ditch or on both sides of the median. Deerfoot Trail: all 11km placed near the shoulder Highway 2: 55km near the shoulder; 56km in ditch centre; 11km on both sides.

8 SAFETY EFFECTIVENESS: DEERFOOT TRAIL
Median-related collision statistics for the before-HTCB period to 2006 (five years) were compared to the 32-month (May 2007 to December 2009) after-HTCB period. The proportion of median related fatal collisions dropped from 4.4% to 0% (From 2007 to May 2017 there has been no median related fatal collision on Deerfoot Trail). The proportion of median related injury collisions dropped from 21.1% to 11.8%.

9 SAFETY EFFECTIVENESS: HIGHWAY 2
Median related collision statistics for 63 months before-HTCB were compared to the 18-month after-HTCB period. The proportion of median related fatal collisions dropped from 2.1% to 0.5%. The proportion of median related injury collisions dropped from 34.5% to 10.0%

10 BENEFIT-COST ANALYSIS
ITEM DEERFOOT TRAIL HiIGHWAY 2 Highway & HTCB length 11 highway-km (11 HTCB-km) 122 highway-km (133 HTCB-km) Traffic volume (AADT) 154,000 29,000 to 34,000 Year of HTCB Construction 2007 2010 No. of cables 3 cables 4 cables Total Capital cost $946,000 $7,500,000 Capital cost/HTCB-km $92,000 $56,000 Maintenance cost/HTCB-km/year $6,050 $3,790 20-year Net Present Value $18,500,000 $53,100,000 Benefit-Cost Ratio 11.1 4.6 Payback period <1 year 2 years Note: amounts shown are in CDN $

11 INNOVATIVE CONSTRUCTION TECHNIQUES ON THE HIGHWAY 2 PROJECT
Vibratory Post Driver mounted on a mini- excavator to install the driven steel post sockets (Instead of the usual drop hammer technique) Customized spool delivery truck to expedite production

12 INNOVATIVE CONSTRUCTION TECHNIQUES ON THE HIGHWAY 2 PROJECT (Cont’d.)
Special guide-post attachment to aid cable installation Electric winch to tension the cable (Instead of the usual block and tackle arrangement)

13 INNOVATIVE CONSTRUCTION TECHNIQUE ON THE HIGHWAY 2 PROJECT (that didn’t quite work!)
Precast concrete foundations for end terminal anchors were allowed, resulting in terminal foundation movement problems

14 INNOVATIVE CONSTRUCTION TECHNIQUE ON THE HIGHWAY 2 PROJECT (Cont’d)
The innovations enabled the installation of 135km of HTCB in 45 days compared to an estimated 150 days with conventional installation methods, and more cheaply. Of the 106 terminal foundations, 60% were driven steel, 35% precast concrete, and 5% cast-in-place concrete. Majority of the precast concrete and driven steel terminal foundations exhibited some movement. Inspection indicated that this movement did not compromise the functionality of the HTCB. A few foundations required remedial action. DOT now requires that terminal foundations must be cast-in- place concrete or driven steel; in the latter case they should be specified at a greater depth than the suppliers’ standard details.

15 OPERATION & MAINTENANCE EXPERIENCE
Deerfoot Trail 11km HTCB: 9-year ( ) Hit and Repair Record Average no. of hits requiring replacement of parts = 0.3 hits per km per month Average no. of parts replaced per hit 3.8 Posts (range 0–31) 4.8 hairpins (range 0–31) 5.1 lock plates (range 0–31)

16 Maintenance and Operational Benefits of HTCB
Repair requires smaller crews; and is easier, quicker and cheaper (and with fewer snow problems) than more rigid barriers Post replacement, cable splicing, re-tensioning are relatively simple HTCB is functional in most cases following a hit, and can retain subsequent hits (except when terminal is down); no cable break experienced

17 Maintenance and Operational Issues and Challenges of HTCB
Greater need for maintenance-worker safety High traffic roads require full traffic accommodation (Deerfoot Trail HTCB repairs are mostly done at night) Some problems with mowing in the median, e.g. when trimming under the barrier in a narrow median, or when HTCB transitions from shoulder to ditch bottom requires mowing

18 Maintenance and Operational Issues and Challenges of HTCB (Cont’d)
Snow removal can be difficult in some snow-accumulation-prone areas where HTCB is near the shoulder (no longer possible to wing snow to ditch) leading to accumulation at the barrier which can accelerate snow drifting Some activities (e.g. sign washing) now completed at night to limit exposure of workers and to reduce road user delays

19 CONCLUDING COMMENTS Median HTCBs drastically reduce crossover fatalities and collision severity. And they are more cost-effective than conventional barriers. HTCBs are easier and cheaper to maintain than conventional barriers. The reaction of the public and emergency responders to the HTCB installations has been consistently positive. Alberta experience indicates that, when planning and designing median HTCB installations, special attention to specific site conditions may be required, e.g. existing structures and conventional barriers in the median, or other local characteristics.

20 THE NEXT SLIDE WILL BE USED ONLY IF THERE IS A RELATED QUESTION FROM THE AUDIENCE.

21 SAFETY EFFECTIVENESS: HIGHWAY 2 Effect of HTCB placement, median width & median side slope during 18 months after HTCB installation Factor Collision Counts Segment Properties Median-Related Collision Rates (Collisions/100 Million veh-km) All Collisions Injury Fatal Highway Length (km) Daily Traffic (Weighted AADT) Barrier Location Both Shoulders 94 8 12.87 33,500 42.09 3.58 0.00 Ditch 267 29 1 55.92 29,950 30.78 3.34 0.12 Shoulder 238 23 2 53.17 29,510 29.28 2.83 0.25 Total 599* 50* 3 121.96 Median Width <= 9.0 m 80 10 17.43 28,620 30.96 3.87 > 9.0 m 478 47 104.53 29,980 29.45 2.90 0.18 558* 57* Median Sideslope 4:1 136 13 15.21 33,260 52.28 4.96 0.38 5:1 313 30 73.16 27.66 2.64 0.09 6:1 150 16 33.59 30,060 28.87 3.06 0.19 59*


Download ppt "HIGH TENSION CABLE BARRIER IN THE MEDIAN OF A FREEWAY IN ALBERTA, CANADA: A CASE STUDY OF TWO SUCCESSFUL PROJECTS TRB First International Roadside Safety."

Similar presentations


Ads by Google