1 GAUTENG DEPARTMENT OF HUMAN SETTLEMENTS PORTFOLIO COMMITTEE PRESENTATION

2 I INTRODUCTION AND PROVINCIAL CONTEXT
The business plan is based on the allocation letter Planned delivery is stands and units (including social housing) social housing programmes for the delivery of 1850 units at R and The are 912 CRU converted and upgraded in the business plan The confirmation of the R5,528,050,000 budget allocation

3 2017 MTEF Final BP – Programme Summary R5,5Bil
Sub-Programme Planned Sites Planned Units Total Annual Budget % 1. Financial Intervention 1.1b Individual housing subsidies (R0 - R3 500) Non - Credit Linked 100 R 16,057,300 1.2 Housing finance linked Individual subsidies (FLISP)-(R R15 000) 4,135 R 222,326,916 1.3 Enhanced Extended Discount Benefit Scheme (EEDBS) R 100,000,000 1.4 State Asset Maintenance Programme R 64,880,380 1.8 Operational Capital Budget R 210,907,400 1.10 NHBRC enrolment (related to grant) R 40,000,000 1.11a Land parcels procured(IHAHSD) R 105,818,189 Sub-total: Financial Intervention 4,235 R 759,990,185 13.75% 2. Incremental Housing Programmes 2.2a IRDP :Phase 1:Planning and Services 11,934 R 607,328,352 2.2b IRDP :Phase 1:Planning and Services INFORMAL SETTLEMENTS 6,815 R 426,722,652 2.2c IRDP : Phase 2:Top Structure Construction 250 7,483 R 878,141,164 2.2d IRDP :Phase 2:Top Structure Construction INFORMAL SETTLEMENTS 16,687 R 1,789,801,672 2.4 Informal Settlement Upgrading 167 R 20,703,178 Sub-total: Incremental Housing Programmes 18,999 24,337 R 3,725,136,817 67.39% 3. Social & Rental Housing 3.2b Social Housing: Capital Grants for rental housing (Funded by NDoH) 1,850 R 185,746,093 3.3a Community residential units (CRU) Converted/Upgraded 912 R 235,113,550 3.3b Community residential units (CRU) Constructed 40 R 14,760,336 Sub-total: Social & Rental Housing 2,802 R 435,619,980 7.88% 4. Rural Housing 4.1 Farm Worker Housing Assistance 200 565 R 74,943,840 4.2 Rural Housing: Communal land rights R 22,189,400 Sub-total: Rural Housing 765 R 97,133,240 1.76% 5. PRIORITY PROJECTS 600 2,148 R 306,513,365 5.54% 6. PROVINCIAL SPECIFIC PROGRAMMES 825 R 203,656,414 3.68% Gauteng Human Settlements Total 19,799 35,112 R 5,528,050,000 100.00%

4 MINING TOWNS Sub-Programme Project Name Project Number (HSS)
Planned Number of Sites (Current year) Planned Number of Houses (Current Year) Total Annual Budget PRIORITY PROJECTS Khutsong South Ext 5 & 6(Mining Town) G 300 500 R 68,561,300 Kokosi Ext 6 (Mining Town) G /1 R 51,477,000 Kokosi Ext 6 (prof fees)(Mining Town) R 5,147,700 Simunye Ext 2(Mining Town) G /1 152 R 16,863,944 PROVINCIAL SPECIFIC PROGRAMMES Bekkersdal Afganistan ,X and Z Section(Mining Towns) G /1 115 R 11,839,710 Bekkersdal Afganistan ,X and Z Sections Prof fees (Mining Town) R 1,183,971 Westonaria Borwa (MV) (Mining Town) G /1 120 R 12,354,480 Militery Veterans Housing (Prof Fees) (Mining Town) R 1,235,448 Munsiville Ext 9- Construction of Roads and Storm water(Mining Town) R 5,738,770 Sewer Rehabilitation Project - Bekkersdal (Mining Town) G /1 R 78,770,497 Bekkersdal link road and bridge(Mining Town) R 9,428,850 Construction of Roads Mohlakeng Ext 11 (Mining Town) G /1 R 561,971 Construction of Roads Mohlakeng Ext 11 (Proff Fees) (Mining Town) R 1,000,000 Total 1,387 R 264,163,641

5 SUMMARY OF PLANNED TARGETS: 2017/18
PROGRAMME Total Sites Budget for Sites Total Units Budget for Units Budget for Other Programmes Total Allocation per programme UISP 6815 R429,162,452 167 R20,703,178 NEW INDIVIDUAL UNITS (EXL. RURAL) 12434 R635,309,773 11514 R1,215,800,242 CRU (CONSTRUCTED) R0 40 R14,760,336 SOCIAL AND RENTAL HOUSING R1,000,000 1850 R184,746,093 From HSDG grant FLISP 4135 R222,326,916 RURAL HOUSING 200 R13,030,330 765 R84,102,910 TOTAL 12634 R648,340,103 16621 R1,557,693,582 MILITARY VETERANS   675 R74,889,225 TITLE DEEDS BACKLOG ERADICATION (pre-1994)  4 629 8,332,200.00  Tittle deeds are determined at stand level  99,968,400.00 TITLE DEEDS BACKLOG ERADICATION (post 1994 – 2014/15) 50 909 91,636,200.00 TITLE DEEDS (NEW DEVELOPMENTS) 15 240 27,432,000.00 LAND ACQUISITION Acquisiton of various portions Golf Park Extension 3 & 4 , Farm Leeuwspruit No.200; Fochville, Frankenworld R35,089,812

6 REGIONAL BREAKDOWN OF PLANNED TARGETS
REGION/ DISTRICT MUNICIPALITY Total Sites Budget for Sites Total Units Budget for Units Budget for Other Programmes Total Allocation per programme Ekurhuleni Region 3,192 R 166,382,495 7,705 R 735,469,132 R 901,851,627 Joburg Region 3,178 R 266,995,124 4,655 R 668,785,375 R 935,780,500 Tshwane Region 4,330 R 191,444,803 7,884 R 764,981,012 R 956,425,815 West Rand District Municipality 5,150 R 346,820,320 5,535 R 668,473,264 R 1,015,293,584 Sedibeng District Municipality 3,949 R 290,049,473 5,901 R 653,725,510 R 943,774,983 Social Housing (across regions) 1,850 R Head Office FLISP 1,582 R 71,180,900  R 71,180,900 Title Deeds Restoration R 100,000,000 Assest Maintenance R 64,880,380 Operational Capital 4% R 210,907,400 NHBRC Home Enrolement R 40,000,000 Various Land Purchases In Non Metro's (Frankenworld/Leeuspruit/Golf Park/Evaton West and Impumelelo) R 32,589,812 TOTAL 19,799 R 1,261,692,215 35 ,112 R 3,562,615,193 R 448,377,592 R 5,

7 MILITARY VETERANS: PLANNED TARGETS FOR 2017/18 F/Y
REGION PROJECT UNITS TOTAL Ekurhuleni Tsakane ext 22 15 25 Tshwane Nellmapius x22 50 150 Clayville ext 45 10 Soshanguve 19 Sedibeng Evaton Show Village 5 225 Oliventhoutbosch Ext 27 Sebokeng x28 20 Westrand Westonaria Borwa 120 205 Savannah City 200 Chief Mogale Joburg Elias Motsoaledi 70 Kagiso x13 Lufhereng 30 Khutsong South x 5 & 6 Lehae Phase 1 Grand total – 675 units

8 PLANNED TARGETS PER PROGRAMME
MTSF PICTURE PER PROGRAMME Total Sites Budget for Sites Total Units Budget for Units Total Allocation per programme UISP TOTAL 6 815 R 167 R R   2.2b IRDP: Phase 1:Planning and Services INFORMAL SETTLEMENTS R R0  R 2.2d IRDP: Phase 2:Top Structure Construction INFORMAL SETTLEMENTS 16 687 R    R 2.2e IRDP: Phase 4:Top Structure Construction (INFORMAL SETTLEMENTS) R0  2.3b People's Housing Process INFORMAL SETTLEMENTS R 2.4 Informal Settlement Upgrading NEW INDIVIDUAL SUBSIDIES TOTAL (EXCL. RURAL) 12 184 R 7 583 R R   1.1a Individual housing subsidies (R0 - R3 500) credit linked  0 1.1b Individual housing subsidies (R0 - R3 500) Non - Credit Linked 100 R 2.2a IRDP: Phase 1:Planning and Services 11 934 R 2.2c IRDP: Phase 2:Top Structure Construction  250 R   7 483 R R

9 PLANNED TARGETS PER PROGRAMME
MTSF PICTURE PER PROGRAMME Total Sites Budget for Sites Total Units Budget for Units Total Allocation per programme 2.3a People's Housing process R0 2.5a Consolidation Subsidies (Excluding Blocked Projects) SOCIAL AND RENTAL HOUSING INCLUDING CRU TOTAL  0 R0  1890 R 3.1 Institutional Subsidies 3.2b Social Housing: Capital Grants for rental housing (Funded by NDoH) 1850 R 3.3b Community residential units (CRU) Constructed 40 R RURAL HOUSING TOTAL 200 R 765 R R 4.1 Farm Worker Housing Assistance  200 R    565 R    R 4.2 Rural Housing: Communal land rights 200  R   FLISP 4 135 R

10 PLANNED TARGETS PER PROGRAMME
MTSF PICTURE PER PROGRAMME Total Sites Budget for Sites Total Units Budget for Units Total Allocation per programme 5. PRIORITY PROJECTS (New opportunities: sites & units) 600  R   2 148  R   R   6. PROVINCIAL SPECIFIC PROGRAMMES (New opportunities: sites & units) R0  825  R   SUB-TOTAL NATIONAL MTSF TARGET 2 973   R R   Emergency Housing Programme (new units) GRAND TOTAL 600 R 2 973 R

11 PROVINCIAL SUMMARY OF PROJECT READINESS
LEGEND Project Ready for construction /Contractor & PRT on Site Projects require SCM, Process dealing with contracts and IPW’s Projects under Planning Provincial (All Projects) Sites Units Budget % of Total HSDG budget allocation 7585 25461 R 3,767,048,521 71% 12214 7801 R 1,402,582,119 27% R 101,386,296 2% Total 19799 33262 R 5,272,685,000 100% Projects Revitalisation of Distressed Communities Sites Units Budget % of Total budget allocation 300 1120 R 234,276,016 4% 267 R 29,887,625 1% 0% Total 1387 R 264,163,641 5%

12 MTEF Business Plan Corridor 2017/18 2018/19 2019/20 Sites
Sites Houses /Units Eastern Mega 2915 2278 1900 3871 2352 5070 Eastern Legacy 277 5627 400 3300 2424 Eastern Total 3192 7905 2300 7171 2752 7494 Central Mega 2228 1881 1150 3373 1200 2480 Central Legacy 950 3684 4183 3490 Central Total 3178 5565 7556 5970 Northern Mega 3463 4349 8445 1624 8440 Northern Legacy 867 4175 1500 4147 706 3928 Northern Total 4330 8524 2700 12592 2330 12368 Southern Mega 3949 4884 8463 4495 8228 3063 Southern Legacy 1017 707 3000 100 Southern Total 5901 8863 5202 11228 3163 Western Mega 6450 4423 3101 9477 2500 13214 Western Legacy 500 1212 250 750 1000 1250 Western Total 5150 5635 3351 10277 3500 14464 Total Mega 17205 17815 15814 29661 15904 32267 Total Legacy 2594 17297 2550 14820 5106 13082 TOTAL MTEF 19 799 35 112 18364 42748 21010 43459 Open Market FLISP 1582 1733 1890

13

14 REGIONAL BREAKDOWN OF PLANNED TARGETS (TITLE DEEDS) – PRE 1994
REGION/ DISTRICT MUNICIPALITY Total Sites Budget for Sites Johannesburg  1 765 R3,177,000.00  Tshwane  384 R691,200.00  Ekurhuleni  1 383 R2,489,400.00  West Rand  578 R1,040,400.00  Sedibeng  519 R934,200.00  Total  4 629 R8,332,200.00

15 REGIONAL BREAKDOWN OF PLANNED TARGETS (TITLE DEEDS) POST 1994
REGION/ DISTRICT MUNICIPALITY Total Sites Budget for Sites Johannesburg 5 508 R9,914,400.00 Tshwane 14 655 R26,379,000.00 Ekurhuleni 21 947 R39,504,600.00 West Rand 3 327 R5,988,600.00 Sedibeng 5 472 R9,849,600.00 Total 50 909 R91,636,200.00

16 REGIONAL BREAKDOWN OF PLANNED TARGETS (TITLE DEEDS) CURRENT PROJECTS
REGION/ DISTRICT MUNICIPALITY Total Sites Budget for Sites Johannesburg 1 633 R2,939,400.00 Tshwane 5 805 R10,449,000.00 Ekurhuleni 2 229 R4,012,200.00 West Rand 2 299 R4,138,200.00 Sedibeng 3 274 R5,893,200.00 Total 15 240 R27,432,000.00

17 PROVINCIAL SUMMARY OF TITLE DEEDS TO BE ERADICATED AND READINESS
Pre 1994 Post 1994 Cost implications Source of funding Total Provincial Backlog to be eradicated Deeds Ready for conveyancing IN 2017/18 F/Y 4 629 50 909 R99,968,400.00 HSDG Allocation Beneficiaries to be confirmed 70 000 R17,500,000.00 No of Title Deeds in Township Establishment Processes 133,819

18 MEGA AND CATALYTIC PRIORITY PROJECTS IN IMPLEMENTATION
Municipality Mega & Catalytic Projects 1. COJ South Hills 2. Riverside 3. Goudrand 4. Lufhereng 5. Malibongwe Ridge 6. Fleurhof 7. EMM Chief Albert Luthuli Ext 6 8. Tsakane Ext 22 9. Clayville Ext 45 10. Leeuwpoort

19 MEGA AND CATALYTIC PRIORITY PROJECTS IN IMPLEMENTATION
Municipality Mega & Catalytic Projects 11. EMM Germiston 12. CoT Fort West 13. Nelmapius Ext 22 14. Midvaal Savanna City 15. Sedibeng Golden Highway Mega 16. Boiketlong 17. Obed Nkosi 18. West Rand Chief Mogale Kokosi Ext 6 & 7 20. Westonaria Borwa

20 MEGA AND CATALYTIC PROJECTS
MUNICIPALITY PROJECT PLANNED SITES BUDGET PLANNED UNITS COJ South Hills 550 R 100 R Riverside 226 R 200 (F) 410(h) 140 R R Goudrand 300 R 300 (h) 200(f) R R Lufhereng 30 R Malibongwe Ridge R 250 R Fleurhof R R Leratong/Witpoortjie 828 R 365 R Ekurhuleni Chief Albert Luthuli 6 900 R 450 R Tsakane 22 1165 R 350 R Clayville 45 402 (f) 500(h) R Helderwyk R Daggafontein 500 R 376 R

21 MEGA AND CATALYTIC PROJECTS
MUNICIPALITY PROJECT PLANNED SITES BUDGET PLANNED UNITS Tshwane Nelmapius Ext 22 650 R Nellmapius Willows Ext 4 213 R Cullinan Ext 2 1500 R 55(f) 392 R R Park City 500 R 250 R Tswaing ( New Eeersterus) 350 R Sedibeng Boiketlong Mega 662 R 562 Obed Mthombeni 335 R 300 R Savannah City 1000 R 500 (f) 1000(h) R R Golden Gardens 189 R Kwa Zenzele Phase 2 1242 R 653 R Johandeo (Golden Highway Mega) R

22 MEGA AND CATALYTIC PROJECTS
MUNICIPALITY PROJECT PLANNED SITES BUDGET PLANNED UNITS West Rand Chief Mogale 568 R 600 R Kokosi Ext 6 & 7 500 R Westonaria Borwa (includes Wagterskop) 569 230 (F) 1000(H) R Vaarkenslaagte 800 R 250 R Western Mega 1214 R 450 R Montrose 1000 402 R Affri Village(Green Hills Extention 2 R

23 SUMMARY & CONCLUSION A draft trilateral agreements has been developed between the Province ,GPF and HDA in the implementation of mega and catalytic projects To strengthen intergovernmental relations and integrated planning with municipalities, engagements are held towards the establishment of a Provincial planning structure (to align USDG and HSDG) Bulk infrastructure investment remains critical in the successful investment of mega and catalytic projects Depicted below are bulk cost estimates identified to support the mega projects in the second phases of implementation

24 BULK INFRASTRUCTURE REQUIREMENTS FOR PHASE 1
* NOTE; THESE ARE COST ESTIMATES. FINAL COSTS TO BE CONFIRMED BY THE MUNICIPALITIES BULK INFRASTRUCTURE REQUIREMENTS FOR PHASE 1