Presentation is loading. Please wait.

Presentation is loading. Please wait.

Conventional Facilities/Siting Jonathan Hunt Project X Machine Advisory Committee March 18-19, 2013.

Similar presentations


Presentation on theme: "Conventional Facilities/Siting Jonathan Hunt Project X Machine Advisory Committee March 18-19, 2013."— Presentation transcript:

1 Conventional Facilities/Siting Jonathan Hunt Project X Machine Advisory Committee March 18-19, 2013

2 Conventional Facilities/Siting Siting History –2010 version –Current version Siting Considerations –Environmental Issues –Master Plan Conventional Facilities –Site Work –Utilities 2013 XMAC Meeting, Jonathan Hunt2

3 Siting History - 2010 2013 XMAC Meeting, Jonathan Hunt3

4 Siting History - 2010 2013 XMAC Meeting, Jonathan Hunt4

5 Siting History - Current 2013 XMAC Meeting, Jonathan Hunt5 ~750’ ~950’ ~1230’

6 Siting Considerations 2013 XMAC Meeting, Jonathan Hunt6

7 Siting Considerations 2013 XMAC Meeting, Jonathan Hunt7

8 Siting Considerations Environmental Issues –Wetland Mitigation Likely area of wetland disturbance = 65 acres Mitigation ratios between 1.5:1 and 5:1 depending on the quality of the wetlands as determined by the Army Corps of Eng. Various methods to mitigating wetland disturbance –Purchased wetland bank credits –Enhance existing wetlands on-site –Creation of new wetlands on-site Purchased wetland bank credits –Costs vary. Estimate $65K per mitigated acre. –@ 1.5:1 = 65 acres x 1.5 x $65K = $6.3M –@ 5:1 = 65 acres x 5 x $65K = $21M 2013 XMAC Meeting, Jonathan Hunt8 Use Avg. ~$14M

9 Siting Considerations Environmental Issues –Wetland Mitigation (cont’d) Army Corps of Engineers will require: –Avoid –Minimize –Mitigate –Environmental Assessment U.S. Fish and Wildlife Consultation May have to do an Environmental Impact Study 2013 XMAC Meeting, Jonathan Hunt9

10 Siting Considerations 2013 XMAC Meeting, Jonathan Hunt10

11 Siting Considerations 2013 XMAC Meeting, Jonathan Hunt11

12 Conventional Facilities Above-grade buildings, roads, parking lots Below-grade beam enclosures and utilities Site Work –Grading and Drainage –Road Construction –Landscaping –Wetland Mitigation Utilities –Electrical –Communications –CHW, LCW, ICW, DWS –Sanitary –Natural Gas 2013 XMAC Meeting, Jonathan Hunt12

13 Utilities Electrical –New duct banks –Utilize existing duct banks –Tieback to both Kautz Road and Master Substations –Separate HV feeders with backup for conventional, machine, and cryogenic 2013 XMAC Meeting, Jonathan Hunt13

14 Utilities Site Power Requirements –Supports operations with: 1 MW of beam power at 1 GeV 3 MW of beam power at 3 GeV 350 kW of beam power at 8 GeV –Total system efficiency ~ 12% 2013 XMAC Meeting, Jonathan Hunt14

15 Utilities 2013 XMAC Meeting, Jonathan Hunt15 Master Substation Kautz Road Substation Kautz Road CUB

16 Utilities Communications –New duct banks –Tie into existing network along Kautz Road Chilled Water (CHWS & CHWR) –Machine and building cooling –New supply and return lines –Tie into existing lines at CUB Low Conductivity Water (LCW) –Machine cooling –New supply and make-up water –Tie into existing Main Injector ring LCW system 2013 XMAC Meeting, Jonathan Hunt16

17 Utilities Industrial Cooling Water (ICW) –Fire protection –New supply and return lines –Tie into existing site-wide system Domestic Water Supply (DWS) –Potable water –New supply lines –Tie into existing site-wide system 2013 XMAC Meeting, Jonathan Hunt17

18 Utilities Sanitary Sewer –New main and lift station –Tie into existing site-wide system Natural Gas –Building heat –New supply lines –Tie into existing site-wide system 2013 XMAC Meeting, Jonathan Hunt18


Download ppt "Conventional Facilities/Siting Jonathan Hunt Project X Machine Advisory Committee March 18-19, 2013."

Similar presentations


Ads by Google