Download presentation
Presentation is loading. Please wait.
Published byElwin Leonard Modified over 8 years ago
1
Conventional Facilities/Siting Jonathan Hunt Project X Machine Advisory Committee March 18-19, 2013
2
Conventional Facilities/Siting Siting History –2010 version –Current version Siting Considerations –Environmental Issues –Master Plan Conventional Facilities –Site Work –Utilities 2013 XMAC Meeting, Jonathan Hunt2
3
Siting History - 2010 2013 XMAC Meeting, Jonathan Hunt3
4
Siting History - 2010 2013 XMAC Meeting, Jonathan Hunt4
5
Siting History - Current 2013 XMAC Meeting, Jonathan Hunt5 ~750’ ~950’ ~1230’
6
Siting Considerations 2013 XMAC Meeting, Jonathan Hunt6
7
Siting Considerations 2013 XMAC Meeting, Jonathan Hunt7
8
Siting Considerations Environmental Issues –Wetland Mitigation Likely area of wetland disturbance = 65 acres Mitigation ratios between 1.5:1 and 5:1 depending on the quality of the wetlands as determined by the Army Corps of Eng. Various methods to mitigating wetland disturbance –Purchased wetland bank credits –Enhance existing wetlands on-site –Creation of new wetlands on-site Purchased wetland bank credits –Costs vary. Estimate $65K per mitigated acre. –@ 1.5:1 = 65 acres x 1.5 x $65K = $6.3M –@ 5:1 = 65 acres x 5 x $65K = $21M 2013 XMAC Meeting, Jonathan Hunt8 Use Avg. ~$14M
9
Siting Considerations Environmental Issues –Wetland Mitigation (cont’d) Army Corps of Engineers will require: –Avoid –Minimize –Mitigate –Environmental Assessment U.S. Fish and Wildlife Consultation May have to do an Environmental Impact Study 2013 XMAC Meeting, Jonathan Hunt9
10
Siting Considerations 2013 XMAC Meeting, Jonathan Hunt10
11
Siting Considerations 2013 XMAC Meeting, Jonathan Hunt11
12
Conventional Facilities Above-grade buildings, roads, parking lots Below-grade beam enclosures and utilities Site Work –Grading and Drainage –Road Construction –Landscaping –Wetland Mitigation Utilities –Electrical –Communications –CHW, LCW, ICW, DWS –Sanitary –Natural Gas 2013 XMAC Meeting, Jonathan Hunt12
13
Utilities Electrical –New duct banks –Utilize existing duct banks –Tieback to both Kautz Road and Master Substations –Separate HV feeders with backup for conventional, machine, and cryogenic 2013 XMAC Meeting, Jonathan Hunt13
14
Utilities Site Power Requirements –Supports operations with: 1 MW of beam power at 1 GeV 3 MW of beam power at 3 GeV 350 kW of beam power at 8 GeV –Total system efficiency ~ 12% 2013 XMAC Meeting, Jonathan Hunt14
15
Utilities 2013 XMAC Meeting, Jonathan Hunt15 Master Substation Kautz Road Substation Kautz Road CUB
16
Utilities Communications –New duct banks –Tie into existing network along Kautz Road Chilled Water (CHWS & CHWR) –Machine and building cooling –New supply and return lines –Tie into existing lines at CUB Low Conductivity Water (LCW) –Machine cooling –New supply and make-up water –Tie into existing Main Injector ring LCW system 2013 XMAC Meeting, Jonathan Hunt16
17
Utilities Industrial Cooling Water (ICW) –Fire protection –New supply and return lines –Tie into existing site-wide system Domestic Water Supply (DWS) –Potable water –New supply lines –Tie into existing site-wide system 2013 XMAC Meeting, Jonathan Hunt17
18
Utilities Sanitary Sewer –New main and lift station –Tie into existing site-wide system Natural Gas –Building heat –New supply lines –Tie into existing site-wide system 2013 XMAC Meeting, Jonathan Hunt18
Similar presentations
© 2024 SlidePlayer.com Inc.
All rights reserved.