Presentation is loading. Please wait.

Presentation is loading. Please wait.

HMA AWG, 6 November 2013 Slide 1 HMA for Science - Status HMA AWG Meeting 6 November 2013, ESRIN Frascati Yves Coene, Spacebel s.a. Claudio Gizzi, Astrium.

Similar presentations


Presentation on theme: "HMA AWG, 6 November 2013 Slide 1 HMA for Science - Status HMA AWG Meeting 6 November 2013, ESRIN Frascati Yves Coene, Spacebel s.a. Claudio Gizzi, Astrium."— Presentation transcript:

1 HMA AWG, 6 November 2013 Slide 1 HMA for Science - Status HMA AWG Meeting 6 November 2013, ESRIN Frascati Yves Coene, Spacebel s.a. Claudio Gizzi, Astrium Ltd.

2 HMA AWG, 6 November 2013 Slide 2 Overview  Task 1 - Project Management: Schedule Standardisation status RID status  Task 2/3/5 Demonstrator Status  Dedicated presentations Task 2 – Identity Mgt Task 4 – OpenSearch Task 6 – Web Processing Service Task 7 – Feasibility Analysis

3 HMA AWG, 6 November 2013 Slide 3 EventDateLocationName MTR (PR4)25/09/2013ESRIN (Frascati) Mid-Term Review PR506/11/2013 Demonstrator FAT PART 1 19/12/2013Webex Objective: Acceptance of Task Technical Notes and associated Demonstrator Software. Task 2, 3, 5, 7. Task 4: limited to Search. Demonstrator FAT PART 2 TBDWebex Objective: Acceptance of Task Technical Notes and associated Demonstrator Software. Task 6 and Task 4: limited to Order and Download. PR61/02/2013 Testbed FATIntended to be incremental. Latest: 1/02/2014. Webex Note: TestBed is full set of Demonstrator VMs at ESA including TEAM engine loaded with ETS scripts. To be discussed. Objective: acceptance of ETS, ETS Test Reports, TestBed and TestBed Technical Note. OGC TC (TBC) AR March 2014 Virginia (U.S.) ESRIN Participation of selected tasks to OGC TC TBC depending on availability of funds. FPJune 2014Collocated with OGC TC Schedule

4 HMA AWG, 6 November 2013 Slide 4 Task 1 – Project Mgt  Document deliveries since OGC TC Meeting Project Management Plan (PMP)HMA-S.ASU.D1000.1, Issue 1, Revision 2 DRAFT, 1/11/2013. OGC 10-032r7 OpenSearch Geo-temporal OGC 13-026r3 (30/10/2013) OpenSearch Extension for EO Products OGC 13-039 (04/11/2013) OpenSearch Extension for EO Satellite Tasking

5 HMA AWG, 6 November 2013 Slide 5 Task 1 – Project Mgt  Issues Standardisation Task 6: WPS  Impact on ETS and Demonstrator development Demonstrator Task 4 « EO Data Access Protocol» OGC 13- 043:  Needed for ETS development  Solution: ASU will provide additional demonstrator. OGC slow to implement Frascati OGC decisions  Carl Reed provided status: next slide. RID closure process not completed. Process should be accelerated.

6 HMA AWG, 6 November 2013 Slide 6  Email Carl Reed 31/10/2013:

7 HMA AWG, 6 November 2013 Slide 7 Task 1 – Project Mgt  Standardisation Plan Task 7: Feasibility Analysis (OGC 13-039) uploaded on 4/11/2013 for vote in Mumbai.

8 HMA AWG, 6 November 2013 Slide 8 Task 1 – Project Mgt  Actions MTR: Total 53, Open 10 (19%). Now: Total: 83, Open 20 (24%).  RIDs MTR: Total 257 Now: Total 309 – Closed: more than 267. Open: less than 32. Recent document updates to be checked.

9 HMA AWG, 6 November 2013 Slide 9 Task 2 – Identity Mgt  Status: Demonstrator TN: completed. Being reviewed internally. Demonstrator: completed @Spacebel.  CIM EP backend to be replaced by I15 EP backend when available.  CIM EP client to be updated to I15 EP in Task 5.  Issues: OGC 07-118 DelegateTo specification alternatives. See separate slides.

10 HMA AWG, 6 November 2013 Slide 10 Task 3 – EOP O&M Metadata  Status: Demonstrator TN: draft. Demonstrator  Client: 50% completed @Spacebel. –FEDEO endpoint used for early testing.  OpenSearch server @Intecs not yet available.  Issues: None.

11 HMA AWG, 6 November 2013 Slide 11 Task 5 – I15 EP  Status: Demonstrator TN: draft. Demonstrator  Client: to be completed @Spacebel.  CIM EP bridge endpoint available @con terra  CIM EP server @Intecs not yet available.  Issues: None.

12 HMA AWG, 6 November 2013 Slide 12 Task 8 – TestBed  Status: Machine for Demonstrators prepared @Spacebel.  Task 3 Demonstrator installed (with CIM EP instead of I15 EP).  Task 4 & 7 Demonstrator (VM) shipped by ASU to Spacebel. Machine for TEAM engine available @Intecs. Draft HMA-S.SPB.D8000.2 (TestBed Technical Note) prepared  Information from Final Demonstrator TN to be integrated when they become available.  Issues: None.


Download ppt "HMA AWG, 6 November 2013 Slide 1 HMA for Science - Status HMA AWG Meeting 6 November 2013, ESRIN Frascati Yves Coene, Spacebel s.a. Claudio Gizzi, Astrium."

Similar presentations


Ads by Google