Site Organization and services for machine installation/commissioning Peter Rådahl www.europeanspallationsource.se June 2016.

Similar presentations


Presentation on theme: "Site Organization and services for machine installation/commissioning Peter Rådahl www.europeanspallationsource.se June 2016."— Presentation transcript:

1 Site Organization and services for machine installation/commissioning Peter Rådahl www.europeanspallationsource.se June 2016

2 Summary This presentation is a follow up on the MMT meeting that took place in May and a request from Roland to EIS to propose a coordinated installation/ commissioning for the machine. The slides provide ideas on organization and service needs. A supportive document provides more detail related to the service (responsibilities, requirements, strategies and time plan). 2

3 Recommendation Establish an overall site organization with a Site Manager representing ESS. – Coordinates the site activities – This person should not come from CF to manage prioritizations etc. – This person is not part of a cervice but the responsible site manager at Site. Agree and implement an ”aligned” site organization on project level Establish central services related to installation/commissioning – Quality control (Q division) – Skanska Maskin (offer from CF) – Machine Installation/Commissioning (a combination of services from ESS of areas not ´provided by Skanska Maskin/CF) Establish an installation service supporting the machine – One of the services under Machine Installation/Commissioning 3

4 Proposal-overall site organization Overall Site Manager Deputy Site Manager Overall Site Manager Deputy Site Manager Overall QC and QC service Installation Inspection Receival inspection NDT (X-ray, PT, UT etc.) Accredited Inspection Body AIB Accredited Body AB Final quality documentation Overall QC and QC service Installation Inspection Receival inspection NDT (X-ray, PT, UT etc.) Accredited Inspection Body AIB Accredited Body AB Final quality documentation Site Admin Time Schedule Financial control Procurement inst. hardware/manpower Site Admin Time Schedule Financial control Procurement inst. hardware/manpower Temporary Services, Skanska maskin Scaffolding Laydown Areas Crane Drivers Logistics/Transport Warehouse Heavy lifting Temporary Power & Fluids Concrete Boring/Drilling Survey/Alignment Waste Temporary Services, Skanska maskin Scaffolding Laydown Areas Crane Drivers Logistics/Transport Warehouse Heavy lifting Temporary Power & Fluids Concrete Boring/Drilling Survey/Alignment Waste TD Site Manager TD Site Manager ACC Site Manager ACC Site Manager NSS Site Manager NSS Site Manager ICS Site Manager ICS Site Manager CF Site Manager CF Site Manager Machine Installation/Commission ing services Installation service Survey, Alignment and Metrology Laser scanning Vacuum Specialised handling Fabrication/adjustments Installation material Others Machine Installation/Commission ing services Installation service Survey, Alignment and Metrology Laser scanning Vacuum Specialised handling Fabrication/adjustments Installation material Others Service from outside the project organization

5 Proposal-template project site organization Project Site Manager Deputy Site Manager Project Site Manager Deputy Site Manager Machine Installation/Commissioning services QC Installation Inspection Receival inspection NDT (X-ray, PT, UT etc.) Accredited Inspection Body AIB Accredited Body AB Final quality documentation QC Installation Inspection Receival inspection NDT (X-ray, PT, UT etc.) Accredited Inspection Body AIB Accredited Body AB Final quality documentation Site Admin Document control Time Schedule Work Permit Accommodation (Site & Hotel) Financial control Procurement inst. hardware/manpower NCR (Non Conformity Report) Site Admin Document control Time Schedule Work Permit Accommodation (Site & Hotel) Financial control Procurement inst. hardware/manpower NCR (Non Conformity Report) Temporary Services, Skanska maskin Installation Package

6 Technology and Installation services Installation planning on machine level Machine installation services – Framework Competences, equipment, tools not provided by Skanska maskin Establish processes, procedures, guidelines and templates (copy routines from Skanska and adopt to ESS) Specialized handling and movement 6 Framework Agreements Welders Fitters Electrical I&C Technicians Equipment's Tools Etc. Framework Agreements Welders Fitters Electrical I&C Technicians Equipment's Tools Etc. Time to establish the framework: 7-13 months 1-3(?) months to collect needs, volumes, competences 1-2 months to set FA strategies 2 months for tendering 1-2 months for review of tenders 1-2 months for signing FA contract 1-2 months to establish the work


Download ppt "Site Organization and services for machine installation/commissioning Peter Rådahl www.europeanspallationsource.se June 2016."