Presentation is loading. Please wait.

Presentation is loading. Please wait.

Pieter Mattelaer (SMB-DI)

Similar presentations


Presentation on theme: "Pieter Mattelaer (SMB-DI)"— Presentation transcript:

1 Pieter Mattelaer (SMB-DI)
WP 17.1 Civil Engineering Pieter Mattelaer (SMB-DI) Consultant Kick-off Meeting – CERN – 31/05/2016

2 Detailed Scope (per WBS); Schedule; Risks; SMB Team; Questions.
WP17.1 Agenda HiLumi WPs → WP17 → WP17.1; Contract Strategy; Scope (per WBS); Detailed Scope (per WBS); Schedule; Risks; SMB Team; Questions. Consultant Kick-off Meeting

3 Consultant Kick-off Meeting - 31.05.2016

4 Consultant Kick-off Meeting - 31.05.2016

5 WP17 – Infrastructure, Logistics & Civil Engineering
WP17.1 Civil Engineering; WP17.2 Electrical distribution; WP17.3 Cooling and ventilation; WP17.4 Access & Alarms; WP17.5 Technical monitoring; WP17.6 Survey & Alignment; WP17.7 Transport; WP17.8 Upgrad. & Cons. of Test/Assembly Facilities for HL-LHC; WP17.9 Logistics & storage; WP17.10 Operational Safety. Consultant Kick-off Meeting

6 WP17.1 Contract Strategy Consultant Kick-off Meeting - 31.05.2016
Point 5 - CMS: 5a : Architect for building permit submission (FR) 5b : Consultant for design of underground and surface works 5c : Contractor for underground and surface works Point 1 - ATLAS: 1a : Architect for building permit submission (CH) 1b : Consultant for design of underground and surface 1c : Contractor for underground and surface works Consultant Kick-off Meeting

7 HL-LHC Works @ Point 1 (ATLAS)
Consultant Kick-off Meeting

8 HL-LHC Works @ Point 5 (CMS)
Consultant Kick-off Meeting

9 Scope (per WBS) WBS Description 17.1.1 SWP17.1 Management 17.1.2
Geotechnical Investigation (P1/5) 17.1.3 Building Permit (P1/5) 17.1.4 P1 Consultant 17.1.5 P5 Consultant 17.1.6 Minor Consultancy Services 17.1.7 Safety Coordinator (P1/5) 17.1.8 P1 Contractor 17.1.9 P1 Minor Works P5 Contractor P5 Minor Works Consultant Kick-off Meeting

10 Detailed scope SWP17.1 management by SMB;
CERN staff, fellows, VIA & project associates; Coordination of SWP17.1; Consultant Kick-off Meeting

11 Geotechnical investigations @ P1/5:
Detailed scope Geotechnical P1/5: Specifications by geotechnical engineer; (Géotechnique Appliquée Dériaz SA; Site investigations by specialist contractor; (Implenia; Factual reports by geotechnical engineer; Additional geotechnical investigations as req’d; → Interpretative report by P1/5 Consultants; Consultant Kick-off Meeting

12 Environmental impact assessment (EIA):
Detailed scope Building P1/5: Applications by CH/FR architects; Supported by CH/FR specialist consultants; Submission in 09/2016; Modifications to permit during construction phase; Environmental impact assessment (EIA): Not required for Point 1; confirmed by CH authorities; Possibly required for Point 5; awaiting response from FR authorities; Consultant Kick-off Meeting

13 Building Permit team for Point 1 (CH):
Detailed scope Building Permit team for Point 1 (CH): Architect; ( Fire safety consultant; ( Rainwater management consultant; ( Landscape architect; ( Building energy consultant; ( Acoustic consultant; ( Environmental / spoils consultant; ( Surveyor; ( Consultant Kick-off Meeting

14 Building Permit team for Point 5 (FR):
Detailed scope Building Permit team for Point 5 (FR): Architect; ( Fire safety consultant; ( Rainwater management consultant; ( Landscape architect; ( Building energy consultant; ( Acoustic consultant; ( Environmental / spoils consultant; ( - TBC) Consultant Kick-off Meeting

15 Detailed scope Consultants @ P1/5: Phase 1 – Preliminary Design;
Phase 2 – Tender Design; Phase 3 – Construction Design; Phase 4 – Construction Management; Phase 5 – Defects Liability; → Consultant to design the works & manage the construction; maîtrise d'œuvre; Consultant Kick-off Meeting

16 Detailed scope Consultants @ P1/5:
Detailed RACI interface matrix available which defines interfaces btwn P1/5 Consultants and other WP17.X & WP15 packages; Consultant Kick-off Meeting

17 Detailed scope Minor Consultants:
Independent Engineer; (to carry out peer review) Adjudicator Panel; (to resolve disputes btwn 3 parties) Legal Assistance; (to draft contracts & defend CERN’s interests) Drafting Support; (to support SMB-SE-DOP) Administrative Support; (to assist w/ administration) Other Consultants; (to advise on specialist technical issues) Consultant Kick-off Meeting

18 Detailed scope Safety Coordinator: HiLumi works are category 1 sites;
Same coordinator for P1/5; Design reviews for safety risks; Safety coordination on P1/5 worksites; (1 person full-time for P1+5 site) → Safety Coordinator will be sourced through HSE framework contracts; → either Apave ( or Dekra ( Consultant Kick-off Meeting

19 Detailed scope Main Contractors @ P1/5: Preliminaries;
Underground Structures; Surface Structures; → WP17.1 only provides ‘civil engineering scope’; → Contractor’s scope will be in line with Consultant’s RACI matrix, which defines interfaces with other WPs; Consultant Kick-off Meeting

20 Underground Structures @ P1/5:
Detailed scope Underground P1/5: PM shaft; US/UW cavern; UR gallery; UA/UL tunnels; UPR escape stairs; Vertical cores to LHC; Shaft access arrangement; (concrete lift shaft + staircase + safe room, steel staircase) Steel structure in US/UW; (mezzanine, draw bridge, crane supports incl. crane rail) Instrumentation & monitoring; Consultant Kick-off Meeting

21 Surface Structures @ P1/5:
Detailed scope Surface P1/5: Buildings: SD/SU/SE/SF/SHM/SR; (incl. steel structures / mezzanines) (incl. crane supports incl. crane rail) (excl. large doors by EN-ACE) SL galleries; Slabs: SHE/SLN; (interface plane with tanks at anchor bolts) (excl. steel structure that supports tanks) Roads & landscaping; Consultant Kick-off Meeting

22 Detailed scope Minor Works @ P1/5:
Advance works; (to prepare worksite for Main Contractor) Other works; (to facilitate and complete the Works) → some advance works start to become visible; other works remain ‘unknown unknowns’; Consultant Kick-off Meeting

23 Schedule Consultant Kick-off Meeting

24 Schedule Phase Start Date End Date Phase 1 – Preliminary Design
Phase 2 – Tender Design Phase 3.1 – Construction Design (UG) Phase 3.2 – Construction Design (SF) Phase 4.1 – Construction (UG) Phase 4.2 – Construction (SF) Phase 5 – Defects Liability Notes: Dates in Italic are estimates; Other dates have been included in Consultants’ contracts; Consultant Kick-off Meeting

25 Risks Risk Consequence Mitigation
vibration due to shaft excavation in 2018 stop excavating or stop LHC; cost & schedule impact vibration study led by WP15; technical & contractual approach by civil consultants unforeseen ground conditions redesign required; cost & schedule impact geotechnical testing as req’d; design measures spoil discharge issues cost impact plan during design polluted soil soil treatment req’d; cost impact budget allowance; plan treatment during design delayed approval of building permit applications (CH/FR) delay start construction; cost & schedule impact close follow-up w/ local authorities design delays schedule impact close design management; CERN input when req’d contractor delays due to unforeseen events close construction management; float if possible contractor claims for various reasons quality of tender design; incl. budget contingency Consultant Kick-off Meeting

26 Vibration Risk CERN bld 311 Hydraulic hammer
(preferred method for shaft excavation) Further to the recommendations at internal review March 2015, civil works planning have been brought forward two years and vibration testing carried out at several worksites Thon underground car park (roadheader) Consultant Kick-off Meeting

27 WP 17.1 Team Consultant Kick-off Meeting - 31.05.2016 WP17
Laurent Tavian Integration Project Office SWP Leaders WP15 PO SWP17 WP17.1 P. Mattelaer Point 1 Project Manager Underground Structures Surface Structures P. Cardon Point 5 L. Lopez S. Mcilwraith Steering Committee SMB management Building Permit M. Poehler HL-LHC Executive Committee Support Fellow Engineers, CAD designers, Site Supervisors ≠ names IPT-PI Procurement DG-LS Legal HSE-SEE Health & Safety Consultant Kick-off Meeting

28 Questions? Consultant Kick-off Meeting


Download ppt "Pieter Mattelaer (SMB-DI)"

Similar presentations


Ads by Google