Mike Andrews August 30, 2012. Weeks 1-5 Activities Rad survey open to supervised access & re-core Install crane electronics & remove shield wall Retrieve.

Similar presentations


Presentation on theme: "Mike Andrews August 30, 2012. Weeks 1-5 Activities Rad survey open to supervised access & re-core Install crane electronics & remove shield wall Retrieve."— Presentation transcript:

1 Mike Andrews August 30, 2012

2 Weeks 1-5 Activities Rad survey open to supervised access & re-core Install crane electronics & remove shield wall Retrieve helium samples from Target Take water (tritium) samples from NuMI drain system Drain water from all RAW systems & change filter Move all DI bottles to TSB Change out Target Pile fan pre-filters Drain glycol from TP chiller from reuse (900 G) Carrier & Pre-Target drain & drip ceiling cleaning

3 Weeks 1-5 Activities Lighting & electrical service upgrades Target Pile dehumidifier repairs & upgrades Horn 2 RAW system upgrades in Target Hall Relocated TP fan controls & sum box Target Pile fan coiling coil upgrade & repair Replace Pre Target Magnets Q113, Q114, & Q120 Electrical cable pulls from shaft to hobbit Target RAW system upgrades in RAW room Replace NuMI stub magnets Q111 & Q112

4 Horn 2 RAW System Upgrades

5 PT Quad Magnet Installation

6 MI Quad Magnet Installation

7 TP Dehumidifier Coil Box

8 NuMI Target Hall

9 Weeks 6-10 Activities During re-fill of TP chiller two existing TP fan cooling coils found to be leaking glycol Leaking cooling coils removed and new units ordered Continue TP dehumidifier repairs & upgrades Reconfigure SR-3 exhaust ventilation duct work Installation of new DP dehumidifier condenser unit Horn 2 RAW system upgrades Borascope & leak test heat exchangers on Horn 1 & 2 and Decay Pipe. Corrosion & leaks found. Order new heat exchanges for all three units

10 Weeks 6-10 Activities Install Target Hall equipment for remote handling ops Horn 1 RAW system upgrade Move Target & Horn 1 from chase to morgue Move Horn 2 from chase to work cell Repair Decay Pipe dehumidifiers 4 & 5 Upstream Decay Pipe RAW system upgrade Install Target Hall rail system

11 Weeks 6-10 Activities Horn 2 relocation to ME position Remove shielding blocks Cut out & remove welded sheet metal air dam Survey & reference void face points of US and DS Blue Blocks Reinstall the 3 blue blocks and 2 floor shielding blocks in the ME void Move 8 blue blocks coffins from MI65 to PW6 Complete drafting for new US & DS blue blocks Start fabrication of new US & DS blue blocks at MAB

12 DP Dehumidifier Condenser Unit

13 RAW Skid Upgrades

14 Target T-Blocks

15 Target NT-07

16 NuMI Horn 1

17 NuMI Horn 2

18 Blue Block Removal

19 Horn 2 ME Location

20 Weeks 11-15 Activities Target DI loop upgrade Continue with Decay Pipe dehumidification upgrade Horn 2 DI loop upgrade Complete MI to NuMI Pre-Target cable pulls Horn 1 DI loop upgrade Leak testing of new DI bottles & casks Decay pipe US DI loop upgrade Install cooling system for pulse power supply cooling Target & Horn 2 Impulse line upgrade

21 Weeks 11-15 Activities Horn 2 relocation to ME position Continue to fabricate new US & DS shielding blocks at MAB Install all custom shield blocks in chase Assemble, survey & install T-block support system in chase Assembly, survey & install Horn 2 carriage support system Extend air-seal over US & DS ends of Horn 2 ME void Re-install 2 US blue shielding blocks in chase Reinstall 7 R-blocks over chase US of new Horn 2 ME position

22 New Custom Shielding Blocks

23 T-Block Support System

24

25 Horn 2 Carriage Support Assembly

26 Pulse Power Supply Cooling

27 DI Bottle & Cask Leak Testing

28 Weeks 16-18 Activities Target Hall Target & Horn 1 drain system upgrade Complete install Horn 2 RAW piping to ME location Install new Target Pile fan cooling coils Absorber RAW upgrades Horn 2 relocation to ME position Rebuild the T-Block staging area downstream doghouse Move Horn 2 into new ME location in chase Move T-blocks from Horn 2 LE location to ME location Survey Horn 2 in chase Move 13 new T-blocks from MAB to Target Hall T-block storage area Install new T-blocks into old Horn 2 LE location Install air seal on Horn 2 chase opening Reconfigure battlement

29 Horn 2 Relocation

30 Horn 2 T-Block Installation

31 Horn 2 ME Assembly In Place

32 Moving Forward Now through October 30 th Battlement reconfiguration Install new air dam over Horn 2 LE position Repair damaged stripline washers Install new stripline section for Horn 2 ME location Horn 2 RAW water lines to Horn 2 Extend instrumentation cables Installation of new DI bottles & casks Complete installation of replacement cooling coils on Target Pile fan.

33 Moving Forward Now through October 30 th Start up Target Pile fan & chase dehumidification Install new heat exchangers on Horn 1&2 and Decay Pipe RAW skids Complete Absorber RAW upgrades Start up RAW skids NoVA Target & Horn 1 ready for installation Install five new multi-wires in NuMI beamline November 1 st through February 1 st Install new Target & Horn 1 Start up all support systems

34 Thanks goes to……… Abhishek “Dez” Deshpande, Karl Williams, Dirk Hurd Salman Tariq, Eric Pirtle, Dave Tinsley, Rich White Kris Anderson, Hiep Le, Chris Kelly, Rob Reilly Cory Crowley, Lee Hammond, Jim Ranson Paul Kasley, Kevin Roon, Ken Bourkland Tony Busch, Paul Sedory The crew – Cervando Castro, Keith Anderson, Mike Stiemann, Jim Zahurones, Bob Albrecht, Orlando Rivera, Chris Payne, Henry Schram, Paul Gentry T&M: Prism, SEA, Arlington, Joliet Steel, ECO