1 Planning Performance Agreements and Extensions of time Date: September 2013www.pas.gov.uk

2 PPAs and EoT agreements Timely decisions are important. But not at all costs. PPAs & EoTs are part of the answer…but must live within a good overall offer They aren’t just a way of improving performance stats, but part of a good service Not a ‘sign here or else’ ( withdraw or refusal) approach

3 Tools are part of a bigger picture Need a clear pre-app ‘offer’ Clarity and confidence: –Starts with pre-app: purpose, start and end, outputs, cost –How you’ll work with developers –Offer which fits the scale of proposal A good quality pre-app leads quickly to a PPA if that is appropriate, or makes it easier to ‘rescue’ (manage the end date) of a scheme later with a EoT

4 The difference between the two PPAs – before submission of the application (ideally early on during the scoping and shaping of a scheme) EoT – after an application has been registered, but before 8/13 (16) week point

5 PPAs can help address different areas Pre-app discussions (early identification of issues) Project management (efficient and timely processing) Relationships (applicants, community, councillors) Resources (exceptional schemes/ extra resources)

6 National Planning Policy Framework (para 195) “Applicants and local planning authorities should consider…entering into planning performance agreements, where this might achieve a faster and more effective application process.”

7 Planning Performance Agreements A framework. Memo of understanding (not a legal agreement), signed before application submitted. Proportionality – match the complexity of the agreement to the issues you have to consider Agreement – they need to take account of both the needs of the applicant and the council but help establish a shared objective (but not an agreement to grant)

8 Planning Performance Agreements Project management tool: –tasks (who is doing what) –timings, including determination date* –basic principles of joint working –resources/financial matters (pre-app charge, extras) –info to include in the application *only thing they have to have

9 Why? Influence over the determination date Avoid fee refund (planning guarantee) Improves quality of the application process (on all sides) Collaborative working (trust, transparency) Better value in the long term: –Less objection, more support –Avoidance of refusals and appeals Better certainty through Member involvement

10 When? Strategic (meet objectives in the plan) EIA Complex sites (land ownership/mixed uses) Controversial Unusual – extra expertise Environmental sensitivity Non-standard planning obligations

11 A developer said: “ brings key partners together, allocates the right people (and the right number of people) to the right groups, and helps towards establishing a shared vision….and helps the LPA move from development control to being more enabling” Landowner involved in a PPA

12 A local authority said A PPA will: help limit the bureaucratic nature of planning promotes shared objectives, visions and goals allow flexibility for all involved build trust and strong partnerships give a genuine voice to local communities establish transparency and more certainty result in a well informed and robust decision

13 PPAs - tips Get agreement to the approach (Council, development sector, other stakeholders) Part of your service offer Keep away from legal Don’t overcomplicate Use it as a live project plan Have the processes which will deliver the project

14 Extension of time agreements Similar, but for post application stage. Managing end date; not last minute scramble And will most likely cover less (proportionate) Principles are the same: –Signed agreement –Timescales Will set a new date for determination (and counted for PS2 returns) Shouldn’t be used all the time as an ‘excuse’

15 PAS ongoing work Cross sector group on pre-app, PPAs EoT will refine and improve Performance Framework Learning from benchmark