1 Preparing & Evaluating RFPs The PMO Role Kim Brain Senior Project Manager, Brain Works Consulting, LLC

2 Introduction/Opening Remarks Who am I? 3 Key Deliverables ▫Definitions ▫Techniques ▫PMO role RFP Lessons Learned 2 Brain Works Consulting, LLC March 23, 2008

3 RFPs are Created for: Existing Products Custom Product Development Services Pre-qualification Agreements 3 Brain Works Consulting, LLC March 23, 2008

4 PMO Role - RFP Development To the Project ▫Resource ▫Coach To the Organization ▫Add Value March 23, 2008 Brain Works Consulting, LLC 4

5 RFP – Table of Contents Introduction and Overview of Requirements Rules Governing Procurement Current Operating Environment Proposed Future Operating Environment Administrative Requirements Functional Requirements Cost Proposal and Bid Format Evaluation Process March 23, 2008 Brain Works Consulting, LLC 5

6 RFP – Table of Contents Appendices ▫Model Contract ▫Administrative Requirements ▫Bidder Qualifications Response Forms ▫Data Elements ▫Bidder Response to Requirements ▫Bidder’s Library ▫Glossary of Acronyms March 23, 2008 Brain Works Consulting, LLC 6

7 RFP Development & Evaluation 3 Key Deliverables ? March 23, 2008 Brain Works Consulting, LLC 7

8 3 Key Deliverables Requirements Model Contract/Statement of Work Evaluation Plan March 23, 2008 Brain Works Consulting, LLC 8

9 March 23, 2008 Brain Works Consulting, LLC 9 RFP – Table of Contents Introduction and Overview of Requirements Rules Governing Procurement Current Operating Environment Proposed Future Operating Environment Administrative Requirements Functional Requirements Cost Proposal and Bid Format Evaluation Process March 23, 2008 Brain Works Consulting, LLC 9

10 Requirements Current Operating Environment ▫Introduction ▫Stakeholders ▫Current Business Operations ▫Current Technology Systems March 23, 2008 Brain Works Consulting, LLC 10

11 Requirements Proposed Future Operating Environment  Conceptual model  Proposed Technical Environment  Expected Future Growth  Performance  Reporting  Security  Ongoing Maintenance and Support March 23, 2008 Brain Works Consulting, LLC 11

12 Requirements Functional Requirements ▫Bidder qualifications ▫Project team qualifications ▫Project management approach ▫Technical solution requirements ▫Business and Technical requirements March 23, 2008 Brain Works Consulting, LLC 12

13 Requirements Techniques to Prepare Requirements ▫Review information/other documents ▫Facilitated sessions ▫Modeling (workflow, process, data) March 23, 2008 Brain Works Consulting, LLC 13

14 PMO Role Templates and checklists ▫RFP sections ▫Requirements checklist ▫Hardware/software specification format ▫Diagram formats/standards Coach ▫Approaches to gather requirements ▫Lessons learned March 23, 2008 Brain Works Consulting, LLC 14

15 PMO - Value Add Facilitated Discussion How can the PMO add value to the project and the organization in the gathering of the requirements for the RFP? 15 Brain Works Consulting, LLC March 23, 2008

16 Model Contract Appendices ▫Model Contract ▫Administrative Requirements ▫Bidder Qualifications Response Forms ▫Data Elements ▫Bidder Response to Requirements ▫Bidder’s Library ▫Glossary of Acronyms 16 Brain Works Consulting, LLC March 23, 2008

17 Model Contract Standard Agreement Statement of Work Provisions ▫Contract ▫Information Technology 17 Brain Works Consulting, LLC March 23, 2008

18 Model Contract Statement of Work ▫Description of project ▫Deliverables – what and when ▫Requirements ▫Payment schedule ▫Project schedule ▫Maintenance March 23, 2008 Brain Works Consulting, LLC 18

19 PMO Role Templates ▫Schedule ▫Project Management Plan ▫Model Contract ▫Required deliverables Coach ▫Clear instructions 19 Brain Works Consulting, LLC March 23, 2008

20 PMO - Value Add Facilitated Discussion How can the PMO add value to the project and the organization in the development of the model contract? 20 Brain Works Consulting, LLC March 23, 2008

21 21 Brain Works Consulting, LLCMarch 23, 2008

22 Expectations of Buyer A response that: ▫Addresses the requirements (scope) ▫Instills confidence that the vendor understands the business objectives and can provide a solution ▫Meets budget and time expectations ▫Follows the stated instructions 22 Brain Works Consulting, LLC March 23, 2008

23 Evaluation of RFP Evaluation Plan ▫Scoring guidelines ▫Evaluation criteria Evaluation Workbook ▫Scoring worksheets 23 Brain Works Consulting, LLC March 23, 2008

24 Evaluation Criteria Example criteria ▫Business ▫Technical ▫Approach ▫Cost ▫Bidder qualifications ▫Team qualifications March 23, 2008 Brain Works Consulting, LLC 24

25 Evaluation Workbook Forms ▫Customer reference ▫Technical requirements ▫Business requirements ▫Project team requirements 25 Brain Works Consulting, LLC March 23, 2008

26 Evaluation Techniques Evaluation Approach ▫Analysis ▫Facilitation ▫Coordination ▫Record keeping ▫Synthesize 26 Brain Works Consulting, LLC March 23, 2008

27 PMO Role Templates ▫Evaluation plan ▫Evaluation workbook ▫Review checklist Coach ▫Approach to conduct procurement ▫Risk areas March 23, 2008 Brain Works Consulting, LLC 27

28 Value Add Facilitated Discussion How can the PMO add value to the project and the organization in the evaluation? March 23, 2008 Brain Works Consulting, LLC 28

29 RFP Lessons Learned Be clear and specific on: ▫Requirements ▫Instructions Client resource projections Version control Cross reference evaluation workbook to RFP sections Boiler plate language 29 Brain Works Consulting, LLC March 23, 2008

30 Templates RFP Evaluation Plan Evaluation Workbook Formats 30 Brain Works Consulting, LLC March 23, 2008

31 Questions/Comments ? March 23, 2008 Brain Works Consulting, LLC 31

32 Contact Info ▫Kim Brain ▫Managing Partner ▫Brain Works Consulting, LLC ▫916 296-6200 March 23, 2008 Brain Works Consulting, LLC 32


Download ppt "Preparing & Evaluating RFPs The PMO Role Kim Brain Senior Project Manager, Brain Works Consulting, LLC."

Similar presentations


Ads by Google