Download presentation
Presentation is loading. Please wait.
Published byJoel Norman Modified over 8 years ago
1
Microboone Cryostat Mike Zuckerbrot Fermilab
2
Basic Overview of Microboone Microboone’s 2 Phases of Operation Phase 1 operations ran from about December 2013 – June 2014 The Phase 1 system contained all major equipment except for the Cryostat/TPC and the Argon condensers The Argon Buffer Dewar stood in place of the Cryostat during Phase 1 Installation is currently underway for Phase 2 system Fermilab - Microboone Cryostat2
3
Basic Cryostat Overview BNL played large part in cryostat and TPC design and procurement Vendor given specifications for leak tightness and cleanliness as well as basic vessel specifications ASME U-Stamped Pressure Vessel 30 psig – full vacuum 35,125 gal total volume Will operate with ~33,700 gal LAr or ~4.1% ullage 7/16” thick shell, 150” ID, ~40’ long, reinforcing outer ribs ASME F&D welded heads Shipped in temporary steel saddles, 4 pick-points Fermilab - Microboone Cryostat3
4
Basic Cryostat Overview 3D Model and Nozzles (not all shown) Liquid inlet top of downstream end, liquid outlet bottom of upstream end o Liquid outlet presents additional ODH risk Liquid return line has small internal phase separator Gas recirculation lines have long internal sparger pipes Fermilab - Microboone Cryostat4
5
Basic Cryostat Overview Delivered to Fermi by vendor Head cut off by vendor TPC built at Fermi and inserted into vessel Cleaned before/after TPC insertion Head welded back on by vendor Leak tested by Fermi after welding Transported to LArTF and lowered in through removable roof Fermilab - Microboone Cryostat5
6
Components and Instruments Redundant level and pressure instrumentation 2 probes and differential pressure measurement for level Absolute and gauge pressure transmitters Will operate at 18 psia with about 33,700 gals of LAr Pneumatic fail closed shutoff valves on all major ports Especially important on ports below liquid level, minimizes amount of piping which if ruptured would not be able to be isolated Dielectric isolation of piping and instruments Dielectric flange gaskets/kits and welded ceramic breaks Dielectric flange gaskets found to have cold leaks in 35t, not recommended for jacketed piping 2 internal purity monitors and ports to send boil off to gas analyzers for contamination measurements Multiple RTDs near interior shell and on TPC Fermilab - Microboone Cryostat6
7
Components and Instruments Dual 4x6 relief valves and safety switchover system 3000 Watts of heater power spread on bottom of external shell with RTDs for monitoring temperature May be used to increase outgassing/filtering during initial recirculation Help to control temperature gradients if they develop during cooldown or filling Chimney purge system for feedthroughs Small bellows pump for constant purge Vapor gets recondensed and filtered Automated system to raise/lower level Fermilab - Microboone Cryostat7
8
Design Considerations Insulation 2 lb/cf spray on Polyurethane foam, sprayed on in layers, mesh after first couple layers to secure Originally specified as a jacketed vessel Foaming is cheaper, potentially safer (no risk of vacuum failure) Higher heat load, but still within project parameters Spray on foam with a mastic vapor barrier is far more effective than the foam block type insulation Fermilab - Microboone Cryostat8
9
Design Considerations Vessel Support High density Polyurethane foam saddles SS saddles and hanging sling design considered Foam saddles give more overhead clearance, simpler and cheaper than SS saddles, and less heat leak Saddles sit on 2 flat metal plates, epoxied to top plate Cryostat gets epoxied to saddles Upstream plates welded together Downstream plates greased to slide Allows vessel to thermally contract Fermilab - Microboone Cryostat9
10
Design Considerations Vessel Heads Cryostat has welded heads Vessel specification included the requirement that the endcap be able to be cut and rewelded, R-Stamped Flanged head was considered Head does not realistically have to be removed multiple times, flange isn’t necessary Concerns over leak tightness of the seal on the large head External Pumps and Condensers External pumps based on LAPD system, easier for routine maintenance and general access External condensers with filtering always recommended for ultra high purity systems Internal condenser adds contamination to the liquid by raining the higher- contamination ullage gas into the liquid Both pumps successfully ran during phase 1, no operational experience with Microboone specific condensers Fermilab - Microboone Cryostat10
11
Design Considerations Initial Purification The Microboone cryostat is initially purified using the piston purge method Method has been repeated and verified to be successful in other experiments (LAPD, 35t, etc…) Was also repeated in Microboone phase 1 operations with the Argon Buffer Dewar, bringing the vessel down to low ppm levels (1-2 ppm) for O2, H2O, and N2 starting from being filled with air o Multiple bottom-to-top volume changes using high purity gas o From air to < 0.5 ppm O2 and H2O, < 2 ppm N2 o Obtained Microboone’s 3 ms (<100 ppt O2 equiv.) electron drift lifetime requirement Cryostat rated for vacuum as well as a fail safe purification method, stemming from a time when there was uncertainty of how well the piston purge method would scale upward Before the slow cooldown process, gas will be recirculated using the cooldown compressor through a large capacity molecular sieve to remove as much water as possible Fermilab - Microboone Cryostat11
12
Final Comments Final Comments 30 psig – full vacuum rating increases amount of material and overall cost, not necessary for piston purged vessels o Also increases amount of cooling power required for initial cooldown Having the vessel fabricated with the main shutoff valves, including actuators and supports, welded on by the vendor would have been beneficial Tighter specifications on nozzle tolerances o Straightness, roundness, minimum inner diameter Fermilab - Microboone Cryostat12
13
Microboone Cryogenic System Mike Zuckerbrot Fermilab
14
Presentation Outline Overview of Microboone Phase 1 and Phase 2 System Phase 1 System Design and Operation Purification System Components Additional Components for Phase 1 Operational Experience and Data Phase 2 - Cryostat Cooldown System Basic Concepts and Major Components Phase 2 - Purification System Additions to Phase 1 System Design of Major Components Fermilab - Microboone Cryostat14
15
Overview of Microboone Microboone Phase 1 System Operated from late December 2013 – early June 2014 Contained several of the major components to be used in the phase 2 purification system No Cryostat or detector, Argon Buffer Dewar stood in place LAr pumps, filters, 11k gal Nitrogen dewar, regeneration system, gas analyzers, inline purity monitor Additional components used in the Phase 1 system include the Argon Buffer Dewar and the High Voltage Cryostat Fermilab - Microboone Cryostat15
16
Overview of Microboone Microboone Phase 2 System Installation is currently underway for the Phase 2 system Additional major cryogenic components include o Cryostat o Argon Condensers o Complete Liquid Nitrogen system including large Phase Separator o Cryostat Cooldown system including compressor, heat exchanger, molecular sieve Fermilab - Microboone Cryostat16
17
Microboone Phase 1 System Late additional to overall plan, designed and implemented in a short time span Conceptually implemented to test and operate the major cryogenic components of the purification system LAr pumps, filters, N2 dewar, regeneration system, gas analyzers High Voltage Cryostat and repurposed inline purity monitor added later for R&D purposes 11k gal Argon Buffer Dewar in lieu of the Cryostat Internal liquid Nitrogen powered Argon condenser Filled with leftover LAr from D0 as well as LAr supplied by 35t once their run had been completed Fermilab - Microboone Cryostat17
18
Microboone Phase 1 System Gas Analyzers H20 o Vaisala dew point meter – gross measurement o HALO – 0-20 ppm, res. to <2ppb O2 o DF310 – 0-5000 ppm o DF560 – 0-20 ppm, res. to <1ppb N2 o LDETEK – 0-100 ppm, <1ppm Fermilab - Microboone Cryostat18
19
Microboone Phase 1 System Argon Buffer Dewar Internal Argon condenser, LN2 coolant supplied from neighboring dewar Initially purified using piston purge method o ~15 bottom-to-top volume changes of HP Argon gas o From air to < 0.5 ppm O2 and H2O, < 2 ppm N2 o Likely didn’t require that many volume changes, was purged over a weekend Cooled by flowing Argon gas with condenser active until ~100 gallons of LAr was present in the dewar Initial fill with ~1,000 gals of leftover D0 LAr o 0.2 ppm H2O, 0.55 ppm O2, 2.5 ppm N2 Filled with 2 more 2,000 gal tanker loads from 35t o 140 and 430 ppb H2O, 9 and 11 ppb O2, 9 and 19 ppm N2 Fermilab - Microboone Cryostat19
20
Microboone Phase 1 System LAr Pumps – Overview Same pump as used in LAPD Vacuum jacketed, flanged top with c- seal 100 mesh strainers on suction, flex hoses on suction and discharge 2 pumps in parallel, both ran separately for ~2000 and ~1000 hours during phase 1 Bearing change required about every 5000 hours Flanged internals and overhead lifting system for easy removal and maintenance Fermilab - Microboone Cryostat20
21
Microboone Phase 1 System LAr Pumps – Initial Startup Initial startup was difficult, required piping geometry change and extra instrumentation on the suction line Eliminated high points on piping, added level probe and automatic vent to eliminate all vapor bubbles, constant bleed Heat load on foam insulated piping was high, required constant flow of ~0.5 gpm or more to prevent rapid boiling in the lines Pump must be fully primed to start If fully primed, expected flow rate differential pressure are steadily established almost instantly Pump switchover was less challenging, done within a few hours Fermilab - Microboone Cryostat21
22
Microboone Phase 1 System LAr Pumps – Other Notes During operations the each pump tripped off once for unrelated reasons A pump restart is just as involved as an initial startup, requiring a significant amount of time and venting to refill the system with liquid and establish flow before the restart One trip was caused by unstable Argon Buffer Dewar pressure, when pressure is rapidly dropped the liquid starts to flash and the pump loses prime o Stable pressure was important, may be less of an issue with a larger liquid supply but still important for the experiment Both pumps leaked into the vacuum jackets while cold, had to continuously run on vacuum pump on the active one o Under investigation, internal plumbing shouldn’t be duplicated until the issue is understood and corrected Fermilab - Microboone Cryostat22
23
Microboone Phase 1 System Filter Skids Primarily based on the LAPD filter skids 2 filter skids, each with a molecular and copper sieve vessel Run one at a time, allows for changeover when saturated so interruption to purification process is minimized Top-down flow to prevent bed lift, check valve on outlet to prevent backflow Slotted plate and mesh screens encapsulate filter media 5 micron sintered metal filter vessel on outlet for particulates Ports to send gas to analyzers after each vessel 9 RTDs in each vessel Fermilab - Microboone Cryostat23
24
Microboone Phase 1 System Filter Skids One filter skid used in phase 1 operations Never fully saturated, started with very clean liquid o Plot on left – 40 ppb O2 down to 0 within a weekend, ~5,000 gals Attempted to bring second filter online, was difficult due to long, small diameter, return line o Plot on right shows several downward steps in O2 concentration from cooling the skid down o Indications that the flow through the active skid was not well distributed, center media likely saturated, outer media had remaining capacity Fermilab - Microboone Cryostat24
25
Microboone Phase 1 System Regeneration System Leased 500 gallon argon dewar and tube trailer with premixed 97.5/2.5% Argon Hydrogen o Flow and ratio of each set by mass flow controllers Both sieves heated simultaneously with Argon gas to about 200 C o 18-24 hours to heat and regenerate molecular sieve Slowly bleed in mixture to regenerate copper sieve and throttle down on the Argon gas flow o Must watch carefully for self heating of the copper media o Can be done within 8-12 hours if already hot Regenerating both sieves simultaneously provides some extra efficiency Fermilab - Microboone Cryostat25
26
Microboone Phase 2 System Phase 2 system additions Cryostat and cooldown system Condensers LN2 coolant systems Most of the cryogenic piping in phase 1 and 2 all analyzed for thermal stresses using Ansys FEA Goal is one full cryostat volume change per day running both pumps in parallel Purity requirement is < 100 ppt O2 equivalent or 3 ms electron drift lifetime Was obtained during phase 1, measured with same inline purity monitor present in phase 2 Initial liquid purification may require 5-10 filter switchovers and regenerations Fermilab - Microboone Cryostat26
27
Microboone Phase 2 System Argon condensers 2 identical condensers, one is a spare or could be used during abnormally high heat load situations like filling Based on the LAPD design, scaled up for larger system Heat transfer of boiling LN2, condensing Ar, and two phase pressure drop calculations extremely thorough 2 inner coils for LN2 flow, outer shell for argon gas Extra coil support and restraints to prevent excessive vibrations from flashing liquid Foam insulated with 4” of a two part Polyurethane mixture Fermilab - Microboone Cryostat27
28
Microboone Phase 2 System Cryostat cooldown system Argon gas diaphragm compressor, positive displacement machine presents additional relief requirements 3 pass plate-fin heat exchanger, requires slow cooldown as well Large capacity molecular sieve Will recirculate warm gas to remove as much water as possible before cooldown Same piping supplies gas for the piston purge Slow cooldown over 2-3 weeks to about 100K before filling Slow cooldown rate set by the TPC requirements Alternative designs should be considered, very expensive and complex system with regards to equipment and design Sprayer nozzles? TPC wire frame design? Fermilab - Microboone Cryostat28
29
Final Comments Final Comments Regeneration system o In house mixing system far cheaper over time than purchasing premixed gas in tube trailers o Does present additional safety concerns due to flammable gas Used equipment o Should be cautious when implementing used equipment o Thorough evaluation and testing Building o Round building is cheaper if it’s a pit o Increases design time, but roundness not as critical as overall size Fermilab - Microboone Cryostat29
Similar presentations
© 2025 SlidePlayer.com Inc.
All rights reserved.