City Administrator Report July 13, 2015. Gulf Coast Marine Fisheries Enhancement Center.

Similar presentations


Presentation on theme: "City Administrator Report July 13, 2015. Gulf Coast Marine Fisheries Enhancement Center."— Presentation transcript:

1 City Administrator Report July 13, 2015

2 Gulf Coast Marine Fisheries Enhancement Center

3 Living Shoreline Program Management NOAA/Florida DEP Design: HDR Budget NRDA Phase III: $11.7 million Timeline NRDA Trustee Approval: October 2014 Estimated completion date: Summer 2018 Activity Field investigation work (physical surveys of seabed) Cultural resources report Next Milestone Results of pre-design investigations (August 2015)

4 Government Street Stormwater Pond

5 VT MA Program Management Construction Manager at Risk: Greenhut Design: Atkins Project Administration: Hatch Mott Budget VT: $7,244,300 FDOT: $15,065,305 IRREF: $7,000,000 City/County: $8,000,000 Timeline Project start: September 2014 Est. completion: March 2017 Current Activity Environmental Assessment (EA) Design phase Next Milestone Final EA (November 2015) 30% Design approval (September 2015)

6 Deep Flex Project Management CM: Construction Management Advisors Budget Tenant: $9-$12 million (construction only) Timeline Project start: August 2014 Est. completion: May 2016 Activity Construction on hold Tenant refinancing Next Milestone Vendor bond issued by tenant (Jul 2015) Construction restart for hardening only (Aug 2015)

7 Airport Regional Stormwater Pond

8 Carpenter Creek Bank Stabilization

9 Digital Radio System Upgrade

10 Bayview Center Demolition

11 Vickrey Center Repairs Program Management Public Works & Facilities Contractor: A.E. New, Jr. Budget Repairs: (FEMA + Insurance) $574,100 HMP: (FEMA) $502,900 Timeline Repair start: April 2015 Est. completion: Sep 30, 2015 Activity Repairs and mitigation Next Milestone Closeout with FEMA: Oct 2015

12 Osceola Golf Course Clubhouse Repairs

13 FY2015 Street Rehabilitation Project

14 Firefighter Apprentice Program

15 Valley Drive @ Carpenter Creek Stormwater Treatment Project

16 Miscellaneous Zoning Inquiry for Low-THC Cannabis Dispensing Organization RESTORE Update Grant applications: HMGP, NDRC, 319 Bayou Texar Dredging Park assessment City Hall boiler