Organic waste Pretreatment plant Tender- and site-presentation.

Similar presentations


Presentation on theme: "Organic waste Pretreatment plant Tender- and site-presentation."— Presentation transcript:

1 Organic waste Pretreatment plant Tender- and site-presentation

2 Todays programme Welcome Introduction to A + and the project - expectations and the project’s role in future waste handling The tender Site presentation – helmets mandatory Questions and answers

3 Presentation of AffaldPlus, the future waste handling and expectations

4 AffaldPlus is owned by 6 municipalities: Faxe Næstved Ringsted Slagelse Sorø Vordingborg 300.000 inhabitants (150.000 households) and approximately 30.000 companies (mostly SME’s or retail). Facilities: 2 W-t-E-plants 1 NG-fired PCH-facility) 2 Landfills 3 Composting facilities 22 Recycling Centers (1,8 mio. visitors/y) 1 facility for sorting and shipment of recyclables

5 340.000 t waste handled in total 340.000 t waste handled in total 180.000 140.000 20.000 40.000 Garden waste 35.000 Demolition & Constructionwaste 18.000 Soil 15.000 Paper & cardboard 15.000 Wood Landfill 57.000, others 30.000 more to be moved by 2018 Incineration Reuse

6 2022 goals of the government 50 % recycling (by weight) of 7 specific materials/fractions from households (paper, cardboard, glass, metals, plastics, wood and organics/biowaste) => ”mandatory” to collect and recycle organics (and wood) (together 25-30 %)

7 Biowaste 20.000 tons of organics from households 4.000 tons garden waste (only easy degradable organics like grass, leaves, flowers, fruit) Demands from the government Energy recovery Recycling of nutrients => Anaerobic digestion => Pretreatment of waste

8 A + expectations (demands) Fully automized (no staff nescessary at site during processing – also the cleaning of the components during the day No loss of easy degradable organics in the reject from the proces No plastics (or stones or metals) in the product. Energy efficient

9 Forbehandling af kildesorteret BIOAFFALD – Pretreatment of source separated Bio-waste Besigtigelsesmøde d. 10 maj 2016 Pre-bid meeting May 10th. 2016

10 Delivery from technical supplier: Main project: delivery of equipment installation of equipment (mechanical, electrical and Scada/SRO) running in and test 3 month trial operation training of staff delivery of spare parts advisory services for building and civil works Optional services: supply and installation of turbidity monitoring equipment for the outputs delivery, installation, running in and 3 month trial operation of equipment for hygienisation. service on maintenance and repair

11 Services not included (to be executed by other contractors) Demolition and dismantling of existing contructions in and outside building Foundation work and other type of structural strengthning Renewing of floors and other surfaces. Electrical work not connected to the equipment functions. Building and civil works required for the construction of access area, reception building and tank storage for outputs etc.

12 Area for pre-treatment installations

13 Design data – Capacity Source/type: Households: source separated biowaste from kitchen and from garden Quantity/composition Per year: 24.000 tons (20.000 tons bio waste from Kitchen and 4.000 tons garden waste) Per 14 days (2 weeks): In average 925 tons Max over 14 days: approx. 1325 tons Min over 14 days: approx. 500 tons Max over one day: approx. 175 tons Composition: Not known in details – see next slide (and Questions and Answers). Arriving trucks: two chamber normal collection trucks (average size load approx. 3,3 tons) walking floor/mulitlift trucks with traylor (load size 17 - 35 tons)

14 Bio waste - Composition Single Family HousesMultistorey dwellings

15

16 Performance requirements Outputs: Storage capacity in tanks for minimum 24 hours maximum production To be transported to external biogasfacility or digester (wet technology) Max content of plastic and metal larger than 2mm: 0,5% of DS. Content of heavy fractions as soil, gravel, glass to be minimized to avoid sedimentation later in the chain Content of "long items" from garden waste to be minimized to avoid blocking Reception installations: To comprise a unloading silo (capacity for one max day) and a buffer storage (capacity for two max. days) Room for unloading of large traylor trucks Room for unloading of at least two normal collection trucks at the same time) Automatic operation of reception installations and internal transport to pre-treatment equipment Operation: To comprise one single line. Work 100% automatically and without permanent supervision of operations - except from staff at control room Operational hours: Max 12 hours and 5 days, 52 weeks per year. In special cases 24 hours operation per day. Water to the pre-treatment process can be taken from treated waste water from neighbouring sewage treatment plant (information on water quality is available)

17 Bid documentation List of prices: Technical information: Technical concept: layout/equipment provided Capacities/operational strategy/ Operation: automation/staffing/consumption energy-water/servicing/cleaning/odour control Training staff from Affald Plus Function-efficiencies: mass flow/loss of biomass/sorting plastic-metak-heavy fractions/large items/DS outputs/water balance Quality plan during installation Documentation of performance ›

18 Time schedule - bidding and project execution Bidding: Submission deadline: May 30th. Expected date of selecting prefered supplier: July 1st. Expected signing date: August 1st. Execution: Advisory services: August 1st. – November 30th. 2017 Design, supply, installation and test: September 2nd. – November 30th. 2017 (including time for execution of services/works carried out by other contractors) 3 months trial period.: December 1st. 2017 – February 28th. 2018.

19 Evaluation criteria ParameterWeighing Economic value, total50% Price all deliveries25% Costs of 10 years of operation (e.g. staff, energy, water, repair/ maintenance) 25% Delivered technology, total50% Layout and technical quality10% Capacity and operational stragetgy5% Daily operation10% Function and efficiencies25%

20 Information portal: Tender documents, questions and answers and other new messages: Website: www.affaldplus.dk/udbudwww.affaldplus.dk/udbud Information from 3D scanning: Server: ftp://ftp2.cowi.dkftp://ftp2.cowi.dk Login: AffaldPlus Password: Ojhqwo52 Please refer to Q&A for further information


Download ppt "Organic waste Pretreatment plant Tender- and site-presentation."