Report and plan of the tilt monitor Daisuke Okamoto Tohoku University.

Similar presentations


Presentation on theme: "Report and plan of the tilt monitor Daisuke Okamoto Tohoku University."— Presentation transcript:

1 Report and plan of the tilt monitor Daisuke Okamoto Tohoku University

2 About the tilt monitor Tilt monitor is the new type of the cavity beam monitor. Measure the beam orbit tilt independently(not beam position) θ Measure θ with high precision Beam line Tilted beam Direct tilt signal from a single cavity Focal point θ Measure the tilt due to the strong focus, and connect to focal point profile. Now, we have tested the prototype.

3 Basic principle monopole mode is excited by the beam orbit tilt excited no excited No tilted beamTilted beam Energy of the monopole mode ∝ θ 2 E field M field Beam pipe Sensor cavity weak strong

4 3e-6 2e-6 1e-6 -1e-6 -2e-6 0 04e-78e-7 1.2e-6 V[volt] Time [s] 100nrad -3e-6 Raw signal 1.2e-4 8e-5 4e-5 0 -4 -2 24 0 V 0 [volt] Tilt θ[urad] V 0 versus θ V0V0 1/e Signal extraction

5 Prototype design Frequency tuner Feed-through Sensor cavity waveguide Flange Body(copper) Beam pipe

6 The prototype was completed Basic parameter test Design frequen cy 2.8553 GHz2.856 GHz Loaded Q 29782650 Qwall1012810000 Qext42203350 Decay time 156nsec150nsec QM16FF QF21X

7 First beam test V0V0 Diode detection In principle, V 0 ∝ θ,q Confirmation of the principle, using mechanical tilt Using base rotation mechanism -10mrad ~ 10mrad Ref Tilt V0V0 We can detect the tilt monitor signal easily. For the charge jitter collection We confirmed the V 0 ∝ θ relation

8 After Correction of the charge jitter Measurement of the amplitude Mechanical tilt [mrad] V 0 [mV] [mV] V ∝ θ At the large range, the V ∝ θ seems very good Around 0 rad, there is the large offset signal and not stable. Beam test using BPM digitizer (thanks for Stewart !! )(today’s morning)

9 Offset signal(very laugh data) -3 -2 -1 0 1 2 3 [mrad] -274μm Vertical offset position -121μm 27μm We could adjust the offset position such that the signal becomes almost 0 But the dependence is strong, especially we have to be care around beam pipe.

10 2010 PLAN of the tilt monitor ・ How to use the tilt monitor data. ・ How to achieve the 35nrad Upgrade of the base (nrad rotation mechanism, mover for vertical position) Until next beam test, I will prepare some component (proper amplifier, mixer) for the BPM digitizer The synchronized BPM data is necessary for the tilt monitor. The confirmation of the principle is OK. The signal level is about 0.7 factor from the simulation.


Download ppt "Report and plan of the tilt monitor Daisuke Okamoto Tohoku University."