Download presentation
Presentation is loading. Please wait.
Published byBruce Sanders Modified over 8 years ago
1
The SPL Short Cryo-module: Status Report V.Parma, CERN, TE-MSC On bahalf of the Cryomodule development team SPL seminar December 2012, 6-7 December 2012, CERN
2
The actors on stage... System/Component/ActivityPerson(s) in chargeLab Cavities/He vessel/tuner constructionO.Brunner, O.Capatina, Th.Renaglia, F.Pillon, N.Valverde, M.Esposito, I.Aviles, G.Devanz CERN CEA-Saclay SRF, magnetic shielding, Clean-Room activities, RF test stations (SM18) E.Ciapala, T.Junginger, K.Shirm, J.Chambrillon, O.Brunner CERN RF CouplerE.Montesinos, G.Devanz CERN CEA Saclay Vacuum systemsG.VandoniCERN Cryogenics, (cryo infrastructure SM18)U.Wagner, (O.Pirotte)CERN Survey and alignmentP.BestmanCERN Cryo-module conceptual designR.Bonomi, D.Caparros, O.Capatina, P.Coelho, V.Parma,Th.Renaglia, A.Vande Craen, L.R.Williams CERN Cryo-module detailed design & Integration & Cryostat assembly tooling Ph.Dambre, P.Duthil, P.Duchesne, S.Rousselot, D.Reynet CNRS/IPNO-Orsay SPL Machine architectureF.GerigkCERN ESS Cryomodule developmentsCh.DarveESS, Lund Cryo-module Technical CoordinationV.ParmaCERN ESS/CERN Fellow
3
SPL Cryomodule Workspace https://espace.cern.ch/spl-cryomodule/default.aspx
4
SPL Cryomodule Working Group 8 meetings in 2012 (from March on)
5
SPL Cryomodule exhibition (CERN, French in-kind meeting, June 2012)
7
Assembly sequence 1- String of cavities outside the clean room2- Mounting of the magnetic shields4- Mounting of the cryogenic distribution3- Mounting of the tuners and inter-cavity connections5- Mounting of the coupler cooling line6- Mounting of the thermal shield7- Insertion in the vacuum vessel8- Closing the vacuum vessel Design by CNRS-IPNO (S.Rousselot)
8
2 parts vacuum vessel Material is low-carbon steel (LHC type) Vessel as magnetic shielding: need for degaussing? Flanges in St.steel (304L)
9
Mechanical analysis at CNRS Loads when closing 242mm 1.2mm rattrapé par 2 vis contigües Effect of a gap at closure CNRS-IPNO, P.Duchesne, P.Duthil
10
…and at CERN See Paulo Azevedo’s talk Mounting of the lid: effect of flat flanges shape imperfections; CERN approach Load case 1 Load case 2 Deformed shape:
11
Pressure relief devices See Paulo Azevedo’s talk First risk analysis made HSE now in the loop (C.Parente), several meetings took place Sizing of safety relief devices: – Burst disks to protect helium circuits – Pressure relief plate to protect insulation vacuum vessel
12
Vacuum vessel detailed design Specification detailed drawings in preparation at CNRS-IPNO Drawings approval in progress Consultation of companies started Procurement to be launched beginning 2013 by CNRS-IPNO
13
Cold magnetic shield Status: Following feedback from RF (T.Junginger), a re-design has been proposed by CNRS and approved, ready for detailed drawings Cold magnetic shield Double layer Coupler sideTuner side Design by CNRS-IPNO (S.Rousselot)
14
Cryogenic distribution x y z Pumping line (XB) To cold box and SM18 2 phase tube (line X) Vapours collector Liquid container LHe Level gauge Courtesy CNRS-IPNO (S.Rousselot, P.Duthil)
15
Valve box and cryogenic scheme in SM18 Control valves grouped in a single valve box Valve box needed also for interfacing CM to cryogenic distribution in SM18 Overpressure safety devices
16
Valve box Status: Conceptual design finished Valves being ordered by TE-CRG Heater on the thermal shield will warm up thermal shield helium to the CM needs (50K) design in progress From SM18 To CM Vacuum barrier Vacuum vessel Thermal shield Courtesy CNRS-IPNO (S.Rousselot, P.Duthil)
17
Cryo valve specs JT valves (common and single valves): – Use : superfuid helium – Diameter: DN4 – WEKA standard design: h=875mm - PN25 - no thermal contact, no G10 spindle rod – Po=normally closed actuators – helium guard seal for subatmospheric applications – Kv max as controlled valve: 0.6m3/h Required max. Kv at 100% stroke: 0.1 m3/h (common), 0,02 m3/h (single) Required min. Kv at 5% stroke: 0.001 m3/h – Equal percentage – Quantity: 4 Needs agreed with TE-CRG (R.Van Weelderen) TE-CRG can start procurement Cool-down valves: – Use : liquid/gas helium – Diameter: DN4 – WEKA standard design: h=875mm - PN25 - Standard sealing to outside - no thermal contact, no G10 spindle rod – Po=normally closed actuators – Kv max as controlled valve: 0.6m3/h Required max. Kv at 100% stroke: 0.18 m3/h (common), 0,02 m3/h (single) Required min. Kv at 5% stroke: 0.004 m3/h – Equal percentage – Quantity: 4 Coupler cooling valve: – Use : Liquid/gas helium – Diameter: DN2 – WEKA standard design: h=875mm - PN25 - Standard sealing to outside - no thermal contact, no G10 spindle rod – Po=normally closed actuators – Kv max as controlled valve: 0.15m3/h Required max. Kv at 100% stroke: 0.06 m3/h (common), 0,02 m3/h (single) Required min. Kv at 5% stroke: 0.002 m3/h – Equal percentage – Quantity: 1 9 cryo valves
18
Cavity vacuum valves Choice discussed with TE-VSC (G.Vandoni) ready for procurement
19
Cryomodule instrumentation ~100 T gauges 10 Elec.heaters 4 He level gauges 4 Piezos, tuners,HOM Pressure gauges Optical Wire Position Monitor
20
Bunker integration studies at CERN SM18 bunker Valve box RF distribution Cryo line interface Cryo-module Study by P. Martinez Yanez and B.Riffaud, EN-MME
21
SPECIAL LENGTH CORRESPONDING TO CRYOMODULE ANGLE Study by P. Martinez Yanez and B.Riffaud, EN-MME Pending work: Full integration study (access, services, safety evacuation of He, …) Design and construction of an inclination table (0%-2%) for the cryomodule Study the opening of the CM top part of vessel for in-situ maintenance and construction of the handling equipment Bunker integration studies at CERN CRYOMODULE 2% INCLINATION
22
Status of supporting system mock-up See P. Azevedo’s and R. Bonomi’s talks
23
Master Schedule Preparation of SM18 infrastructure (cryogenics, RF, clean-room) Cavities production Cavities processing/RF testing RF couplers Clean room assembly of string Cryomodule (& assy tooling) design Cryomodule fabrication Cryomodule assembly Start cryomodule RF testing
24
Summary 2012, Outlook 2013 Notable progress in the design of the CM this year: – Vacuum vessel: almost ready for procurement – Magnetic shield: design finalized – Cryogenic piping: design well progressed – Thermal shield: design in progress – Cryogenic and vacuum valves: choice made, procurement can start – Instrumentation: preliminary list Assembly tooling: – Concepts only: work needs to start now Valve box: – Conceptual design made Major milestones for 2013 – Launch procurement of vacuum vessel, early 2013 – Other parts to be ordered by mid 2013 – Design of assembly tooling by mid 2013
Similar presentations
© 2024 SlidePlayer.com Inc.
All rights reserved.