Update to Proposition 1E – Early Implementation Project (EIP) Application and Local Share Reclamation Board Sub-Committee Meeting September 11, 2007.

Similar presentations


Presentation on theme: "Update to Proposition 1E – Early Implementation Project (EIP) Application and Local Share Reclamation Board Sub-Committee Meeting September 11, 2007."— Presentation transcript:

1 Update to Proposition 1E – Early Implementation Project (EIP) Application and Local Share Reclamation Board Sub-Committee Meeting September 11, 2007

2 Segment 3 Segment 1 Site 7 (Segment 1) Segment 2 Feather River Early Implementation Project

3 EIP Status Submitted Application on April 30, 2007 Received DWR EIP preliminary notification letter late August 30, 2007 Met with DWR officials to discuss requirements of letter on September 4 th Anticipated EIP project cost $188.8 million –Proposed state share: $138.5 million –Proposed local share: $50.3 million EIP elements: –Segment 2 and 3 funded, included in total cost –Segment 1 and site 7 not funded, included in total cost –Ecological Restoration not funded and not included in total cost

4 EIP Agreement Schedule Anticipated schedule: –TRLIA, Yuba County Board of Supervisors, and RD784 approve financial plan required by EIP: September 25 th –TRLIA submit financial plan & supporting documentation to DWR: September 27 th or 28 th –DWR to complete review: mid October –Agreement finalized and signed: early November –Initial funding from DWR: early/mid December

5 Local Share Status Financial plan is being prepared jointly by: Yuba County, TRLIA, and landowners Key components of Plan: –Funding strategy: Combination of many options are being considered such as: Capital Calls (2 nd funding agreement), Benefit Assessment District, and other government funds –Three year audit of TRLIA financial records is being completed by CPA –Information on current and projected O&M costs

6 Additional Local Documentation Items to be submitted by end of September: –Provide additional information on strategy to 200 year flood protection –Further define flood risk in affected area and provide Acknowledgement of flood risk via a resolution by Yuba County –Permits and environmental compliance documentation Future items (prior to actually funding): –Emergency response plan –Hydraulic modeling and design information

7 EIP Concerns Lateness of funding and potential impact on TRLIA 2008 Completion Goal Cost overruns beyond built-in contingency are the responsibility of TRLIA Reimbursable funding vs. upfront funding by State Expenses incurred before Agreement is in place are not guaranteed to be covered – subject to negotiation Ecological restoration funding from other sources

8 Summary Thankful for opportunity to obtain State funding Preparing to submit Financial Plan and other documentation by end of September Anxious to receive state funding and make major progress towards: –200 year flood protection for South Yuba County –Achieve all the benefits obtained by building the Feather River setback levee