Β*-dependence on collimation R. Bruce, R.W. Assmann C. Alabau Pons, F. Burkart, M. Cauchi, D. Deboy, M. Giovannozzi, W. Herr, L. Lari, G. Muller, S. Redaelli,

Slides:



Advertisements
Similar presentations
R. Bruce, M. Giovannozzi, S. Redaelli With essential input from G. Arduini, R. De Maria, S. Fartoukh, M. Fitterer, R. Tomas, J. Wenninger, aperture team.
Advertisements

Collimation with retracted TCSGs R. Bruce, R. Kwee, S. Redaelli.
Combined cleaning in IR3 - MD results and simulations Adriana Rossi R.W.Assmann, R. Bruce, F. Burkart, M. Cauchi, D. Deboy, L. Lari, S. Redaelli, G. Valentino,
LHC Collimation Working Group – 19 December 2011 Modeling and Simulation of Beam Losses during Collimator Alignment (Preliminary Work) G. Valentino With.
Critical beam losses during Commissioning & Initial Operation Guillaume Robert-Demolaize (CERN and Univ. Joseph Fourier, Grenoble) with R. Assmann, S.
Collimation MDs LHC Study Working Group Daniel Wollmann for the Collimation-Team, BLM-Team, Impedance-Team, … LHC Study Working Group,
1 Analysis of MD on IR1 and IR5 aperture at 3.5 TeV – progress report C. Alabau Pons, R. Assmann, R. Bruce, M. Giovannozzi, G. Müller, S. Redaelli F. Schmidt,
Sat/Sun 26/27 th March Sat 18h20: Stable beams. Fill #1653. Sun 10h02: Stable beams continued. vdM scans. Length calibrations. 16h59: Beam dump. Delivered.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
The ATS MD part III (Achromatic Telescopic Squeezing scheme) Participants: Any (active) volunteers Goal: 1)MD1 (S. Fartoukh & R. Assmann  10h): “Pre-squeeze’’
* IP5 IP1 IP2 IP8 vertical crossing angle at IP8 R. Bruce, W. Herr, B. Holzer Acknowledgement: S. Fartoukh, M. Giovannozzi, S. Redaelli, J. Wenninger.
GRD - Collimation Simulation with SIXTRACK - MIB WG - October 2005 LHC COLLIMATION SYSTEM STUDIES USING SIXTRACK Ralph Assmann, Stefano Redaelli, Guillaume.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
External Review on LHC Machine Protection, CERN, Collimation of encountered losses D. Wollmann, R.W. Assmann, F. Burkart, R. Bruce, M. Cauchi,
Off-momentum tail scraping for passive abort gap cleaning (MD 444) D. Mirarchi, R. Bruce, S. Redaelli On behalf of the LHC Collimation Team LHC Study Working.
LHC Technical Committee, 23/05/20071 LHC Commissioning Phases Squeeze presented by Massimo Giovannozzi on behalf of the LHCCWG Particular thanks to S.
LHC Studies Working Group – 03 July 2012 Beam Scraping and Diffusion + Asynchronous Dump MD G. Valentino, R. W. Assmann, F. Burkart, L. Lari, S. Redaelli,
LSWG day: Impedance and beam induced heating Nicolas Mounet *, Daria Atapovych, Nicolò Biancacci, Elias Métral, Tatiana Pieloni, Stefano Redaelli, Benoit.
The Large Hadron Collider Contents: 1. The machine II. The beam III. The interaction regions IV. First LHC beam [R. Alemany] [CERN AB/OP] [Engineer In.
R. Assmann - LHCCWG Two Beam Operation R.W. Aßmann LHCCWG Acknowledgements to W. Herr, V. Previtali, A. Butterworth, P. Baudrenghien, J. Uythoven,
R. Bruce, Today’s meeting ATS optics proposed for use in 2015 (see LBOC, Evian) Several differences compared to nominal optics – Checks needed!
Machine development - results and plans – critical results, what’s to be done? R. Assmann 15/07/2011 R. Assmann for the LHC MD coordination team (R. Assmann,
Simulations of TCT beam impacts for different scenarios R. Bruce, E. Quaranta, S. RedaelliAcknowledgement: L. Lari, C. Bracco, B. Goddard.
Progress with beam Mike Lamont. BUNCH TRAINS AND CROSSING ANGLES AT INJECTION Werner Herr et al 2.
LHC Collimation Working Group – 20 February 2012 Collimator Setup Software in 2012 G. Valentino R. W. Assmann, S. Redaelli and N. Sammut.
Aperture in case of an asynchronous beam dump with ATS optics R. Bruce, E. Quaranta, S. Redaelli With valueable input from: A. Bertarelli, C. Bracco, F.
Improving Collimator Setup Efficiency LHC Beam Operation Committee, G. Valentino, R.W. Assmann, R. Bruce, F. Burkart, M. Cauchi, D. Deboy, S.
Work in progress: Improved models of collimation margins with TCT damage limit R. Bruce, L. Lari 1 Input and discussions: R. Assmann, A. Bertarelli, C.
Collimator settings for 2012 R. Bruce, R. Assmann for the collimation team
Injection and protection W.Bartmann, C.Bracco, B.Goddard, V.Kain, M.Meddahi, V.Mertens, A.Nord, J.Uythoven, J.Wenninger, OP, BI, CO, ABP, collimation,
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Cryo back at 17:30 Beam back at 19:00 IR2 aperture until ~03:00 Since then no beam from the SPS:  Connector problem on MKD  Connector eroded, needs to.
LHC Machine Operational Status and Plans LHCC, 22nd September 2010 Steve Myers (On behalf of the LHC team and international collaborators)
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Injection status W. Bartmann, C. Bracco, B. Goddard, V. Kain, A. Macpherson, M. Meddahi, S. Redaelli, J. Uythoven, J. Wenninger LIBD Meeting, 20 th Sept.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Summary Session 5 Chamonix 2011, 24. – Session 5: “High Intensity: Present and Future” R. Assmann & S. Redaelli Thanks to Frank Z. for his notes…
Collimation Aspects for Crab Cavities? R. Assmann, CERN Thanks to Daniel Wollmann for presenting this talk on my behalf (criticism and complaints please.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
LHC Collimation Working Group Monday, 21 March 2016 Analysis of collimator BPMs in the 2015 run A.Valloni, G. Valentino with input from R. Bruce, A. Mereghetti,
How low can we go? Getting below β*=3.5m R. Bruce, R.W. Assmann Acknowledgment: T. Baer, W. Bartmann, C. Bracco, S. Fartoukh, M. Giovannozzi, B. Goddard,W.
R. Bruce, M. Giovannozzi, S. Redaelli With essential input from G. Arduini, R. De Maria, S. Fartoukh, M. Fitterer, R. Tomas, J. Wenninger, aperture team.
C. Bracco, R. Bruce, B. Goddard, C. Wiesner, A. Lechner, M. Frankl
Operating IP8 at high luminosity in the HL-LHC era
Ralph Assmann, Giulia Papotti, Frank Zimmermann 25 August 2011
MD Planning Fri – Sat (26. – 27.8.)
HL-LHC Aperture Update
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
Β*-reach in 2017 R. Bruce, S. Redaelli, R. De Maria, M. Giovannozzi, A. Mereghetti, D. Mirarchi Acknowledgement: collimation and optics teams, BE/ABP,
Halo scraping and loss rates at collimators
Tuesday TOTEM and transverse loss map (1) OK
Week 35 – Technical Stop and Restart
Summary of Week 26 Main aims: G. Arduini, B. Holzer, M. Lamont
MD#2 News & Plan Tue – Wed (19. – 20.6.)
Yesterday morning Held 1647 for a while – SPS kicker problem
Collimation after LS1: cleaning and β* reach
Global aperture measurements at 450 GeV with 170 mrad crossing angle
Saturday 7th May Sat – Sun night
Collimation margins and *
Collimators: Operations - Baseline Assumptions
Improving Collimator Setup Efficiency
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
Collimation qualification during the first weeks of the 2011 run
Summary for LPC (March 7th, Ralph Assmann)
Plan for 1 m b* J. Uythoven & J. Wenninger
LHC collimation review follow-up Impedance with IR3MBC option & comparison with phase 1 tight settings N. Mounet, B. Salvant and E. Métral Acknowledgements:
Another Immortal Fill….
Large emittance scenario for the Phase II Upgrade of the LHC
Operational Results of LHC Collimator Alignment using Machine Learning
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

β*-dependence on collimation R. Bruce, R.W. Assmann C. Alabau Pons, F. Burkart, M. Cauchi, D. Deboy, M. Giovannozzi, W. Herr, L. Lari, G. Muller, S. Redaelli, A. Rossi, G. Valentino, D. Wollmann Acknowledgment: T. Baer, W. Bartmann, C. Bracco, S. Fartoukh, B. Goddard, R. Tomas, G. Vanbavinckhove, J. Wenninger, S. White

Introduction Main limitations when going to smaller β* Magnetic limits: max gradient in quadrupoles and chromaticity Beam-beam limit … R. Bruce Aperture limit: decreasing margins in triplet when decreasing β*. Present LHC limit! IP1

Importance of collimation for β* Triplet aperture must be protected by tertiary collimators (TCTs) TCTs must be shadowed by dump protection Dump protection must be outside primary and secondary collimators Hierarchy must be satisfied even if orbit and optics drift after setup  margins needed between collimators R. Bruce , β* =3.5 m 2011, β* =1.5 m nominal, β* =0.55 m 2010, β* =3.5 m 2011, β* =1.5 m nominal, β* =0.55 m

Collimation system with margins defines min. aperture that can be protected Possible values of β* depend on the settings of all collimators and therefore on machine stability and frequency of collimation setups! To optimize β*, we have to review Triplet aperture Machine stability and necessary margins in collimation hierarchy R. Bruce Importance of collimation for β* 2010, β* =3.5 m 2011, β* =1.5 m nominal, β* =0.55 m 2010, β* =3.5 m 2011, β* =1.5 m nominal, β* =0.55 m

Aperture calculations Using 2 methods: n1 (theory based, adding uncertainties) Measured aperture 2010: measurements at injection. Scale beam size to pre-collision (larger β x and γ), add orbit offsets in relevant plane Solve for top energy aperture 2011: new local triplet aperture measurements at top energy R. Bruce MQXB.B2L1 s= m 2mm separation

Example of 3.5 TeV measurement Procedure for “gentle” measurements: 1. Open TCT by 0.5 sigma ( μm in H-V) 2. Increase local bump in IR in steps of 0.25 sigma until losses seen 3. Check relative height of BLM spikes: TCT vs MQX (Q2). Go back to 1. Start from initial settings: TCTs at 11.8 sigmas. Orbit at TCT and Q2 TCT positions [mm]18.8 σ 18.3 σ 17.8 σ TCT losses [Gy/s] Q2 losses [Gy/s] Loss spikes while the orbit is increased, touching TCT or MQX R. Bruce Courtesy S. Redaelli

Aperture results Found aperture is very close to the ideal mechanical aperture During design phase, pessimistically added margins for different tolerances Measured aperture thus better than expected R. Bruce ModelBPM (CO Xing + ΔCO bump ) 3.5 TeVIP5-H (crossing)CO Xing =5.8 mm (120 μrad)ΔCO bump =17.7 mm24.4 mm n σ x σ=4.8 mm4.8 mm (n σ = 4) A mm = 28.3 mm29.2 mm Example: IR5 horizontal plane Reference: MD note in preparation Presentations by S. Redaelli and M. Giovannozzi in LMC and LSWG Mechanical aperture: 28.9 mm (30 mm without tolerance)

Margins in cleaning hierarchy Orbit: separate analysis on following slides 10% β-beating. Bias in correction at TCT-triplet wanted Positioning error (small!) Setup error (small!) Small lumi scans can be included in the margin R. Bruce

Orbit stability Check reduction in margin during all fills with stable beams Relative change needed between both devices (collimators or aperture) Consider change w.r.t. reference orbit used during setup For margin TCT-aperture, take phase advance into account (only one jaw relevant) R. Bruce

Orbit stability triplets/TCTs First half of 2011 in many cases better than 2010 Very good stability within fills change in minimum margin TCT-triplets during all 2011 stable beams 1.1 σ margin needed for 99% coverage (gain 0.5 σ). R. Bruce TCT Upstream triplet Downstream triplet Reference from collimation setup IR1 B2 HIR5 B1 V Still room for improvement? IR5 H B1

Margins between collimators Analysis shows 99% of the time in stable beams, the triplets in IR1 and IR5 are shadowed by the TCTs with a 1.1 σ margin in first part of 2011 run 99% of the time in stable beams, all horizontal TCTs are shadowed by the dump protection with a 1.1σ margin in first part of 2011 run We should not reduce the margin between IR7 and dump protection R. Bruce

Damage risks What does a 99% coverage mean in terms of damage risks? Assume 1 asynchronous dump per year Assume 1% of the time the margin dump-TCT is violated (uncorrelated to async. dump) Assume 1/3 of the time spent in stable beams => 1 event in 300 years could be dangerous for the TCTs Assume 1% of the time the margin TCT-triplet is violated => 1 event in years could be dangerous for the triplets This considers only orbit. Simultaneously all other errors have to add up pessimistically at both locations. => The real risk is much lower! In case of the TCT being hit by a bunch there is no catastrophic damage, most likely it will be scratched and we can use a spare surface (see talk A. Bertarelli in Chamonix 2011) R. Bruce

Operational margins and settings Summing linearly we get the margins and the settings The year 2011 started with  *=1.5m, but refined aperture measurements in September showed that  *=1.0m can be obtained with the same settings R. Bruce

Future improvements If machine stability improves, smaller margins in hierarchy possible Moving in primary collimators closer to beam (smaller than nominal emittance!) and the rest of the system gains aperture Probably only possible at 3.5 TeV – at 7 TeV impedance becomes problematic Tested tight collimator settings in MDs in 2011 (primary collimators at 4   nominal gaps in mm at 7 TeV). Excellent cleaning performance obtained, but improved orbit stability during squeeze needed (work underway - S. Redaelli) Refined analysis for present machine underway R. Bruce

Possibilities for HiLumi LHC Upgraded collimators with built-in BPM buttons allow collimators to be quickly re-centered without touching beam, which makes smaller margins possible. We can probably not go below nominal gaps (in mm) of the primary collimators due to impedance at 7 TeV To go to very small β*, we thus need larger aperture as in upgrade scenario (see S. Fartoukh et al.) R. Bruce

Conclusions β* is dependent on margins in collimation system. Present limitation on β* in the LHC. Choice of β* should maximize performance without risking safety A review of both aperture and all margins allowed β* to be reduced from 3.5m in 2010 to 1.5m in beginning of 2011 and later to 1.0m Presently the aperture tolerances are better than expected but we run with larger margins in the collimation hierarchy. Main cause: long-term orbit stability Future improvements from collimation possible Larger aperture needed for HiLumi-LHC parameters R. Bruce