MEP Coordination. Excerpt from Clash Report
Togar Suites. Union, NJ BmSDC Garage Clash Report, Clash #3 MEP Coordination. Simple Clash Detected Beam (W8 x 28) meets Pipe (8” Sanitary Line) …Hello?
SK-6 GS2-4 “Clash No. 3: We recommend increasing the size of the beam from W8x28 to W24x55 and providing an opening in the steel beam at the location of the conflict between the pipe and beam. Refer to GS2-4 for the location and SK-6 for the detail.” Togar Suites. Union, NJ BmSDC Garage Clash Report, Clash #3 MEP Coordination. Recommendation from Engineer
Without BIM cost of a W8 x 28………………….. $1300 cost of replacement W24 x 55….... $2500 removing the beam with a crane…... $205 installing new beam with a crane….. $195 field prep of penetration…………..... $464 Net Cost $4,932 With BIM cost of a W24 x 55………….. $2500 credit W8x28……………… shop prep of penetration.….…. $210 Net Cost $1,410 MEP Coordination. Cost Comparison
Without BIM Net Cost = $4,932 With BIM Net Cost = $1,410 Collision Analysis. Cost Comparison cont. 5 days of general conditions…… $22,000 5 days delay to other trades...Not Included cost of 5 days lost use……….Not Included liquidated damages…………..Not Included Total Cost = $26,932 Total Cost = $1,410