ATF2 beam operation status Toshiyuki OKUGI, KEK The 9 th TB&SGC meeting KEK, 3-gokan Seminar Hall 2009/ 12/ 16.

Slides:



Advertisements
Similar presentations
ATF2 Interaction Point Beam Size Monitor (Shintake Monitor) Status T. Yamanaka, M. Oroku, Y. Yamaguchi, S. Komamiya ( Univ. of Tokyo ), T. Suehara, Y.
Advertisements

Tests of DFS and WFS at ATF2 Andrea Latina (CERN), Jochem Snuverink (RHUL), Nuria Fuster (IFIC) 18 th ATF2 Project Meeting – Feb – LAPP, Annecy.
Summary of the discussion for the commissioning session 2 nd ATF2 Project Meeting KEK, Tsukuba, Japan 6/ 1/ 2006 T.Okugi (KEK)
ILC BDS Alignment and Tuning Studies Glen White SLAC/QMUL 8 November 2005 Progress report and ongoing plans for BDS alignment and tuning strategy.
ATF Cooling Water System Toshiyuki OKUGI, KEK 2015/ 2/ 24 ATF2 Project Meeting LAPP (Annecy, France)
Status of IPBSM Improvement N. Terunuma, KEK 2012/July/13 ATF2 Weekly Meeting.
-brief report of October runs and some inputs for the Nov/Dec planning – Nobuhiro Terunuma, KEK, ATF ATF session on LCWS13, Tokyo Univ., Nov. 13, 2013.
Simulation of IP beam size with orbit jitter + wakefield in EXT-FF ATF2 Project Meeting K.Kubo.
ATF2 Progress Report For CLIC Workshop Kiyoshi KUBO.
Analysis of ATF EXT/FF Orbit Jitter and extrapolation to IP (Data of ) ATF2 Project Meeting K. Kubo.
ATF2 Status and Plan K. Kubo ATF2, Final Focus Test for LC Achievement of 37 nm beam size (Goal 1) – Demonstration of a compact final focus.
1.Beam Tuning Simulation 2.IP Beam Position Stability 2-1 ) Magnet Vibration 2-2 ) IP position jitter subtraction for 2 nd bunch with FONT feedback 2-3.
High Resolution Cavity BPM for ILC final focal system (IP-BPM) ILC2007/LCWS 2007 BDS, 2007/6/1 The University of Tokyo, KEK, Tohoku Gakuin University,
Discussion on Milestone and schedule Toshiyuki Okugi ATF2 commissioning meeting 1 / 7 / 2009.
Personal strategy for ATF2 beam operation in 2009 Toshiyuki OKUGI 2009 / 7 /22 ATF2 weekly meeting.
ATF2 commissioning in Autumn 2009 for discussion Philip Bambade LAL & KEK LCWS09 BDS session Albuquerque, New Mexico October 1, 2009 on behalf of the commissioning.
IPBSM status and plan ATF project meeting M.Oroku.
March 7, 2007 LET Issues (Cai/Kubo/Zisman) Global Design Effort 1 Low-Emittance Tuning Issues and Plans Yunhai Cai, Kiyoshi Kubo and Michael S. Zisman.
IP-BSM Improvement Work N. Terunuma 2012/6/26 ATF2 Project Meeting.
Y. Ohnishi / KEK KEKB-LER for ILC Damping Ring Study Simulation of low emittance lattice includes machine errors and optics corrections. Y. Ohnishi / KEK.
FFS Issues in the 2011 autumn continuous operation Toshiyuki OKUGI (KEK) 1/13/2011 The 11 th ATF2 project meeting SLAC, USA.
June 30, th ATF2 Project Meeting Andrei Seryi for the ATF2 team May 2010 Continuous Run Operation.
Continuous Run in May K.Kubo. Final Focus Test Line IP; ~40 nm beam ATF Linac (1.3 GeV) ATF Damping Ring (140 m) Extraction Line Photo-cathode.
ATF2 beam commissioning status and beam time request Toshiyuki Okugi 2008 / 11 / 12 ATF2 Commissioning Meeting.
ILC BDS Static Beam-Based Alignment and Tuning Glen White SLAC 1.Aims. 2.Error parameters and other assumptions. 3.Overview of alignment and tuning procedure.
ATF DR Overview Introduction Low emittance history Present status S.Kuroda ( KEK ) GDE Review 3rd Apr.2013.
Commissioning Status of Shintake Monitor (IP-BSM) T. Yamanaka, M. Oroku, Y. Yamaguchi, Y. Kamiya, S. Komamiya (Univ. of Tokyo), T. Okugi, N. Terunuma,
Mark Woodley, SLACATF2 Project March 20-21, Summary of Tuning, Corrections, and Commissioning.
1/10 Tatsuya KUME Mechanical Engineering Center, High Energy Accelerator Research Organization (KEK) ATF2-IN2P3-KEK kick-off meeting (Oct. 10, 2006) Phase.
Results on recent technology developments at ATF - Beam extraction study by a Fast Kicker - N. Terunuma, KEK LER11, Heraklion, Crete, Greece, 2011/Oct/5.
ATF2 Commissioning Toshiyuki Okugi 2008 / 7 /9 ATF2 beam commissioning meeting, KEK.
Low emittance tuning in ATF Damping Ring - Experience and plan Sendai GDE Meeting Kiyoshi Kubo.
Operational Experience with ATF2 Beam Diagnostics Glen White, SLAC On Behalf of ATF2 Collaboration TIPP, Chicago, June
Plan in summer shutdown Magnet -SF1FF -Swap of QEA magnet - Multipole field of Final Doublet IP-BSM improvement.
EXT: Summary of activities, software development, and tuning performance 11th ATF2 Project Meeting, January M. Woodley1/29.
1 H. Hayano for the ATF collaboration Low Emittance Beam Generation in ATF H. Hayano for the ATF collaboration BPM electronics improvement emittance tuning.
Analysis of Multipole and Position Tolerances for the ATF2 Final Focus Line James Jones ASTeC, Daresbury Laboratory.
First Collision of BEPCII C.H. Yu May 10, Methods of collision tuning Procedures and data analysis Luminosity and background Summary.
IP instrumentation configuration for Autumn 2010 ATF2 runs Toshiyuki OKUGI, KEK 2010 / 7/ 1 10 th ATF2 project meeting.
ATF2 Tuning Summary Nov & Dec 2010 Glen White, SLAC 11 th ATF2 Project Meeting, SLAC Jan
ATF2 Report ALCW Kiyoshi KUBO, for ATF2 Collaboration.
SLAC ESA T-474 ILC BPM energy spectrometer prototype Bino Maiheu University College London on behalf of T-474 Vancouver Linear Collider.
Task Lists of ATF2 commissioning Toshiyuki Okugi ATF2 Project Meeting 12 / 17 / 2008.
IPBSM Operation 11th ATF2 Project Meeting Jan. 14, 2011 SLAC National Accelerator Laboratory Menlo Park, California Y. Yamaguchi, M.Oroku, Jacqueline Yan.
N. BlaskovicFONT Meeting1 ATF November 2013 shift plan N. Blaskovic.
Summary of Tuning, Corrections, and Commissioning ( Short summary of ATF2 meeting at SLAC in March 2007 ) and Hardware Issues for beam Tuning Toshiyuki.
IP diagnostics Toshiyuki Okugi 2008 / 6 /19 ATF2 Software mini-workshop LAL, Orsay.
Brief review of past studies on Wakefield ATF2 Proj. Mtg K.Kubo.
Wakefield effect in ATF2 Kiyoshi Kubo
Design for a New Optical Table of the Shintake Monitor Takashi Yamanaka The University of Tokyo ATF2 weekly meeting 2007/9/26.
Accuracy of the orbit measurement by KEKB BPM system for the study of ILC damping ring H. Fukuma (KEK) Requirement for the accuracy of BPM data.
Ultra-low Emittance Coupling, method and results from the Australian Synchrotron Light Source Rohan Dowd Accelerator Physicist Australian Synchrotron.
Hardwares for commissioning 2 nd ATF2 Project Meeting KEK, Tsukuba, Japan 5/ 31/ 2006 T.Okugi (KEK)
Simulation for Lower emittance in ATF Damping Ring Kiyoshi Kubo Similar talk in DR WS in Frascati, May 2007 Most simulations were done several.
From Beam Dynamics K. Kubo
ATF2 Status N.Terunuma, KEK
Alignment and beam-based correction
Expected hardware status and Priority of the commissioning task
Intensity dependence of Beam size at IP and Wakefield in ATF2
Orbit Response Matrix Analysis
Emittance Diagnostics
Tolerances & Tuning of the ATF2 Final Focus Line
For Discussion Possible Beam Dynamics Issues in ILC downstream of Damping Ring LCWS2015 K. Kubo.
ATF2 IP Tuning Task Simulation Updates
Beam-based alignment measurements
Beam-Based Alignment Results
ATF ICB meeting, LCWS08, UIC, Chicago, 11/18/2008
N. Terunuma (KEK) ILC2010, Beijing, March 29th, /2/28.
Linac Diagnostics Commissioning Experience
Presentation transcript:

ATF2 beam operation status Toshiyuki OKUGI, KEK The 9 th TB&SGC meeting KEK, 3-gokan Seminar Hall 2009/ 12/ 16

Improvement of cavity BPM system Diode was installed and the readout software were improved in order to avoid the sampling timing change. We established the calibration procedure. The calibration of all cavity BPMs in ATF2 beamline spends 4 hours. The calibration constants for C-band BPMs was kept within 5% accuracy more than 3days. Small readout position change between bunch population of e10. The I-Q rotations for S-band BPMs are not stable yet. We will investigate the unstability of I-Q rotation in this evening ( 12/16 swing shift). The improvement of cavity BPM systems helps the beam tuning for ATF2 beamline. Improvement of beam tuning from the 8 th TB&SGC meeting 2009/12/162The 9th TB&SGC meeting

Optics Modeling ( Orbit Response Matrix ) Orbit response measurement was used for the R12 response test. - The precision of the optics modeling was improved with cavity BPM improvement. - DAC readback was used to calculate the magnet strength instead of ADC. For example ZV7X ZH8X Good agreement Not Good 2009/12/163The 9th TB&SGC meeting Some correctors are consistent with the model, but some are not. (?) The orbit response measurement was also used for quick test of the cavity BPM calibration.

Dispersion correction Dispersions were evaluated with 2 methods. 1) Delta-f ramp in DR 2) Orbit jitter analysis SVD matrix The results are consistent each other. The vertical dispersion correction is improved not only with QS1X, QS2X sum-knob, but also with ZV5X, ZV6X and ZV7X local bump. Vertical dispersion for all ATF2 beam line is corrected within 10mm. Large horizontal dispersion at the end of straight line (500mm) sometimes exists. Delta-f ramp in DR Orbit jitter analysis SVD matrix 2009/12/164The 9th TB&SGC meeting

BBA BPM offsets with respect to magnets are measured and put to the database. All quadrupoles are aligned within 1mm range, but some BPMs for sextupoles has large offsets. Mechanical alignment of sextupoles are measured with respect to nominal beam orbit for the preparation of nominal optics. First 3 sextupoles are aligned within 1mm, the FF sextrupoles are not yet measured. 2009/12/165The 9th TB&SGC meeting Example : SF6FF Horizontal Scan Summary Table of Sextupole BBA

IP tuning We concentrate to minimize the vertical beam size only. We did not measure the horizontal beam size in 2009 autumn operation period. We can achieve the vartical beam size almost the resolution limit (around 3um) of 10um tungsten wire at IP. We minimized the vertical beam size to be 1.5um at post-IP with carbon wire scanner. 2009/12/166The 9th TB&SGC meeting Beam size measurement with Carbon wire

The hardware works in 2009 summer shutdown We align the Final Doublet and all of the sextupole magnets. We prepare the wide aperture vacuum camber to BDMP. We prepare new IP target with Screen, knife edge and wire scanner. We install the new IP-BSM laser (400mJ/pulse -> 1500mJ/pulse). IP-BSM Improvement 2009/12/167The 9th TB&SGC meeting Attach10  m tungsten wire at the tip of the holder to make 1  m beam size at IP Prepare 2 screen monitor Electron beam size measurement - Laser-laser collision for all laser mode - Electron-laser collition Prepare knife edge target to make 10  m laser spot at IP Laser beam size measurement

2009/12/16The 9th TB&SGC meeting8 Improvement of S/N In 2009 spring runIn 2009 autumn run Elecrtron beam size tuning and Laser –beam collision is easy with new target. Signal was increased by the factor 4 with new intense laser. Noise was reduced by the factor 1/10 by various hardware improvements. ( Laser wire mode ) Laser was focused at IP, and the laser spot size was around 20um. The measured beam size by the laser wire mode was 20um.

2009/12/16The 9th TB&SGC meeting9 Observation of the Fringe Pattern ( Interference Mode ) Elecrtron beam size tuning and Laser –beam collision is easy with new target. The first observation of the fringe pattern is 2009/11/13. The beam test at 2009/11/13 is the first trial of the fringe pattern observation in the 2009 autumn beam operation period. The fringe pattern is measured by changing the path length of one laser.

Max Min Beam Size Evaluation Evaluated beam size were larger than wire scanner measurement for both methods. 2009/12/1610The 9th TB&SGC meeting Fitting – uses sinusoidal function for fitting and obtain modulation depth from fitted parameters – has tendency to underestimate the modulation Max/Min – uses maximum and minimum data only to calculate the modulation depth – has a tendency to overestimate the modulation

2009/12/16The 9th TB&SGC meeting11 Consistency check was done by changing the laser crossing angle chenge. The evaluated beam size by wire scanners were limited by the its resolution (less than 2.5um). The evaluated beam sizes by fitting method were in between 3-4um for all crossing angle. The evaluated beam sizes by Min/Max method were in between 2-3um for all crossing angle. The evaluations sizes for larger crossing angle showed smaller beam for both methods. Crossing Angle Dependence

Source of Systematic Error 2009/12/1612The 9th TB&SGC meeting Crossing angle estimation Degradation of the fringe visibility Power and size imbalance between two laser beams Temporal coherence Spatial coherence Displacement from the laser waist Beam position, laser phase jitter Tilt of the interference fringe PMT linearity

The collision point was not set to the laser waist. Modulation pattern was deformed. 2009/12/1613The 9th TB&SGC meeting

Summary of IP-BSM status Improved from the 8 th TB&SGC meeting The new IP target is very useful for beam size tuning and laser-beam collision. The background was reduced to be 1/10. We observed the laser interference patterns with beam for 2-4 degrees mode. We measured 3 times the interference patterns (11/13, 11/20 and 12/4). We established the procedures of the beam size measurement by interference mode. It spend about 4 hours for the preparation work for IP-BSM measurement. The present problems to be solved We did not yet established to evaluate the beam size from laser interference patterns, because the many systematics are not yet understood. The seed laser was broken twice in 2009 autumn operation period. We must solve the problem. 2009/12/1614The 9th TB&SGC meeting