PRODUCTION AND OPERATIONS MANAGEMENT
Advertisements

 Projects are usually infrequent or one- time.  No two projects are the same.  Projects are usually fairly long.  Several months to many years  Involve.
3 - 1 Course Title: Production and Operations Management Course Code: MGT 362 Course Book: Operations Management 10 th Edition. By Jay Heizer & Barry Render.
2 – 1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. Project Management 2.
© 2004 by Prentice Hall, Inc., Upper Saddle River, N.J Operations Management Project Management Chapter 3 - Heizer.
WEEK 15A – PROJECT MANAGEMENT (CHAPTER 3) Characteristics, tools, Pert/CPM, critical path, slack calculation, crashing SJSU Bus David Bentley1.
1 1 Slide © 2009 South-Western, a part of Cengage Learning Slides by John Loucks St. Edward’s University.
Project Development Scheduling and Probability of Completion.
Chapter 3 (Continued) Outline Recap CPM (continued)  Assign time estimates to each activity  Compute the longest time path through the network.
Project Management Project management is a systemized approach to: ◦ defining, ◦ organizing ◦ planning ◦ monitoring ◦ controlling projects.
Managing Projects. Project Management Questions zWhat activities are required to complete a project and in what sequence? zWhen should each activity be.
1 1 Slide © 2008 Thomson South-Western. All Rights Reserved Slides by JOHN LOUCKS St. Edward’s University.
© 2007 Pearson Education Project Management Chapter 3.
TECHNIQUES FOR PLANNING & MANAGING PROJECTS.
Project Scheduling Professor Stephen Lawrence Leeds School of Business University of Colorado Boulder, CO
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Project Management OPIM 310-Lecture.
Chapter 16 – Project Management
© 2000 by Prentice-Hall Inc Russell/Taylor Oper Mgt 3/e Chapter 6 Project Management.
2 – 1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. Project Management Chapter 2.
Project Scheduling Professor Stephen Lawrence Graduate School of Business Administration University of Colorado Boulder, CO
Analyzing Cost-Time Trade-Offs There are always cost-time trade-offs in project management. – You can completing a project early by hiring more workers.
Construction Engineering and Management
의사결정론의 개요 중앙대학교 경영대학 박해철. The Classical Areas of Management Finance Marketing Organizational Behavior/Personnel Management Accounting Management Information.
MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved. W6 6.2 Operation Management Operation Management Managing Projects Techniques.
Project Management 1.
© 2007 Pearson Education Project Management Chapter 3.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Copyright 2006 John Wiley & Sons, Inc. Project Management OPIM 310.
Project Management Chapter 2
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Planning.
© 2004 by Prentice Hall, Inc., Upper Saddle River, N.J Network Planning Methods Example CPM : Saint Paul’s Hospital Network Planning Methods.
Chapter 6. Terminology AOA and AON diagrams Determining Project Duration, Critical Path Special.
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. KR: Chapter.
Project Scheduling A. A. Elimam FinishStart. Project Scheduling Need to plan and control large/time consuming projects.
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Fifth Edition © 1999 Addison Wesley Longman. All rights reserved. 時間管理補.
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Chapter 4.
Managing Project Processes Managing Project Processes.
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Activity.
Network Planning Methods Example PERT & CPM
LM733-PRODUCTION OPERATIONS MANAGEMENT
Lecture 09 Project Management ISE Dept.-IU Office: Room 508.
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Chapter 17 Project Management Part.
1 1 Project Scheduling PERT/CPM Networks. 2 2 Originated by H.L.Gantt in 1918 GANTT CHART Advantages - Gantt charts are quite commonly used. They provide.
1 1 Slide © 2005 Thomson/South-Western Chapter 10 Project Scheduling: PERT/CPM n Project Scheduling with Known Activity Times n Project Scheduling with.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Chapter 6 Project Management To Accompany.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Project Planning and Budgeting Recall the four stages Project Definition and Conceptualization Project Planning and Budgeting Project Execution and Control.
© 2005 Prentice Hall, Inc. Managing Projects Dr. Mohammad Hamsal.
Chapter 7 – PERT, CPM and Critical Chain Operations Management by R. Dan Reid & Nada R. Sanders 4th Edition © Wiley 2010.
(M) Chapter 12 MANGT 662 (A): Procurement, Logistics and Supply Chain Design Purchasing and Supply Chain Analysis (1/2)
Project Management – Part 1. Overview What is a project? Project management techniques Activity lists Network diagrams Critical path analysis Gant charts.
© 2007 Pearson Education Project Management. © 2007 Pearson Education Bechtel Group, INC.  Bechtel is a $16.3 billion-a-year construction contractor.
Operations and Project Management Session 3 Extra Some Additional Details on CPM and PERT.
Project Management Chapter 8.
Project Management (專案管理)
Project Management Chapter Topics
Chapter 17 Project Management McGraw-Hill/Irwin
Hospital Establishment
Developing a Project Plan
PROJECT MANAGEMENT WITH CPM/PERT.
Project Planning and Budgeting
Probabilistic Time Estimates
Project Scheduling: Lagging, Crashing and Activity Networks
Örnek-2Örnek-2 2 FinishFinish StartStart CG B 10 D 35 H J E 24 I 15 A F K ABCDEFGHIJKABCDEFGHIJK — — A B B A C D A E,G,H F,I,J Immediate.
Chapter 16 – Project Management
Learning Curve Analysis
Planning and Managing Projects
Managing Risk Chapter 7.
Presentation transcript:

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Planning and Managing Projects Chapter 8

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Implement changes 6 Redesign process 5 Implementing Changes Document process 3 Define scope 2 Evaluate performance 4 Figure 8.1 Identify opportunity 1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Develop Marketing Plan Install Operating Control Base Select BankSelect NameFind Location Provide Staffing Provide Physical Facilities Establish Business Structure Work Breakdown Structure Figure 8.2 Strategic Plan Define Business Opportunity Plan for Action Proceed With Startup Plan Start a New Business

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Activity Relationships Activity Relationship AOAAON Figure 8.3

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Activity Relationships Activity Relationship S precedes T, which precedes U. AOAAON 12 S 3 T 4 U STU Figure 8.3

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Activity Relationships Activity Relationship S and T must be completed before U can be started. AOAAON S T U T S 4 U Figure 8.3

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Activity Relationships Activity Relationship T and U cannot begin until S has been completed. AOAAON T U S T U 2 S Figure 8.3

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Activity Relationships Activity Relationship U and V cannot begin until both S and T have been completed. AOAAON U V S T 3 S T U V Figure 8.3

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Activity Relationships Activity Relationship U cannot begin until both S and T have been completed; V cannot begin until T has been completed. AOAAON S T U V 13 Dummy SU TV Figure 8.3

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Activity Relationships Activity Relationship T and U cannot begin until S has been completed; V cannot begin until both T and U have been completed. AOAAON ST 5 V U Dummy STV U Figure 8.3

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Example 8.1 Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff. BSelect site and do site survey. CSelect equipment. DPrepare final construction plans and layout. EBring utilities to the site. FInterview applicants and fill positions in nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment. HConstruct the hospital. IDevelop an information system. JInstall the equipment. KTrain nurses and support staff.

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson Example 8.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AON Network Example 8.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AON Network Start A Example 8.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AON Network Start A B Example 8.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AON Network Start A B C Example 8.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AON Network Start A B C D Example 8.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AON Network Start A B C D E Example 8.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AON Network Start A B C D E F Example 8.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AON Network Start A B C D E F G Example 8.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AON Network Start A B C D E F G H Example 8.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AON Network Start A B C D E F G H I Example 8.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AON Network Start A B C D E F G H I J Example 8.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AON Network Start A B C D E F G H I J K Example 8.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AON Network FinishStart A B C D E F G H I J K Figure 8.4 Example 8.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AOA Network Example 8.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AOA Network A Start 1 2 Example 8.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AOA Network A B Start Example 8.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AOA Network A B C D Start Example 8.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AOA Network F A B C D H E G I Start Example 8.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AOA Network F A B C D H E G J I Start Example 8.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AOA Network F A B C D H E G J I Dummy Start Example 8.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AOA Network F A B C D H E G K J I Finish 9 Dummy Start Figure 8.5 Example 8.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital Completion Time FinishStart K6K6 I 15 F 10 C 10 D 10 E 24 G 35 H 40 J4J4 A 12 B9B9

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital Completion Time FinishStart K6K6 I 15 F 10 C 10 D 10 E 24 G 35 H 40 J4J4 A 12 B9B9

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital Completion Time FinishStart K6K6 I 15 F 10 C 10 D 10 E 24 G 35 H 40 J4J4 A 12 B9B9

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital Completion Time FinishStart K6K6 I 15 F 10 C 10 D 10 E 24 G 35 H 40 J4J4 A 12 B9B9

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital Completion Time FinishStart K6K6 I 15 F 10 C 10 D 10 E 24 G 35 H 40 J4J4 A 12 B9B9

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital Completion Time FinishStart K6K6 I 15 F 10 C 10 D 10 E 24 G 35 H 40 J4J4 A 12 B9B9

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital Completion Time FinishStart K6K6 I 15 F 10 C 10 D 10 E 24 G 35 H 40 J4J4 A 12 B9B9 Path Expected Time (wks) A-F-K28 A-I-K33 A-C-G-J-K67 B-D-H-J-K69 B-E-J-K43

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital Completion Time FinishStart K6K6 I 15 F 10 C 10 D 10 E 24 G 35 H 40 J4J4 A 12 B9B9 Path Expected Time (wks) A-F-K28 A-I-K33 A-C-G-J-K67 B-D-H-J-K69 B-E-J-K43

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital Completion Time FinishStart K6K6 I 15 F 10 C 10 D 10 E 24 G 35 H 40 J4J4 A 12 B9B9 Figure 8.6

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Example 8.2 St. Adolf’s Hospital Earliest Start and Earliest Finish Times

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Earliest Start and Earliest Finish Times Example 8.2

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Earliest Start and Earliest Finish Times Example 8.2

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Earliest Start and Earliest Finish Times Example 8.2

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Earliest Start and Earliest Finish Times Example 8.2

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Earliest Start and Earliest Finish Times Example 8.2

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Earliest Start and Earliest Finish Times A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Finish Start Example 8.2

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Earliest Start and Earliest Finish Times A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Finish Start Example 8.2

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Earliest Start and Earliest Finish Times A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Finish Start Example 8.2

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Earliest Start and Earliest Finish Times

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Latest Start and Latest Finish Times Example 8.3 Finish Start

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Latest Start and Latest Finish Times A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Latest finish time Finish Start Example 8.3

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Latest Start and Latest Finish Times A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Latest start time Latest finish time Finish Start Example 8.3

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Latest Start and Latest Finish Times Finish Start Example 8.3

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Latest Start and Latest Finish Times Finish Start Example 8.3

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Latest Start and Latest Finish Times Finish Start Example 8.3

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Latest Start and Latest Finish Times

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Gantt Charts Figure 8.9(a)

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Figure 8.9(b) Gantt Charts

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Figure 8.10 Activity Slack

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Activity Slack Analysis A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Finish Start Example 8.4

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Start A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Finish Activity Slack Analysis Activity Slack Example 8.4

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Start A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Finish Activity Slack Analysis Activity Slack Slack = LS – ES or Slack = LF – EF Example 8.4

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Start A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Finish Activity Slack Analysis Activity Slack Slack K = 63 – 63 or Slack K = 69 – 69 Example 8.4

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Start A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Finish Activity Slack Analysis Activity Slack Slack K = 0 or Slack K = 0 Example 8.4

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Start A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Finish Activity Slack Analysis Example 8.4

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Start A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Finish Activity Slack Analysis Node DurationESLS Slack Example 8.4

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Start A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Finish Activity Slack Analysis Node DurationESLS Slack A12022 B9000 C D10990 E F G H I J K Example 8.4

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital C 10 G 35 E 24 I 15 F B9B9 0 9 D H J4J K6K Finish Critical Path Node DurationESLS Slack A12022 B9000 C D10990 E F G H I J K Example 8.4

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital C 10 G 35 E 24 I 15 F B9B9 0 9 D H J4J K6K A Finish Start Critical Path Example 8.4

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Linear cost assumption St. Adolf’s Hospital 8000 — 7000 — 6000 — 5000 — 4000 — 3000 — 0 — Direct cost (dollars) |||||| Time (weeks) Figure 8.11 Cost-Time Relationships in Cost Analysis Crash cost (CC) Normal cost (NC) (Crash time) (Normal time) Estimated costs for a 2-week reduction, from 10 weeks to 8 weeks 5200

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital TABLE 8.1DIRECT COST AND TIME DATA FOR THE ST. ADOLF’S HOSPITAL PROJECT A12$ 12,00011$ 13,0001$ 1,000 B950,000764,00027,000 C104,00057, D1016,000820,00022,000 E24120, ,000108,000 F1010,000616,00041,500 G35500, ,000103,000 H401,200,000351,260,000512,000 I1540, ,50052,500 J410,000113,00021,000 K630,000534,00014,000 Totals$1,992,000$2,209,000 Maximum NormalNormalCrashCrashTimeCost of TimeCostTimeCostReductionCrashing per Activity(NT)(NC)(CT)(CC)(wk)Week

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Critical Path B-D-H-J-K: 69 weeks Crash Activity J by 3 $1,000/week Minimum-Cost Schedule Example 8.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Critical Path B-D-H-J-K: 69 weeks Crash Activity J by 3 $1,000/week Minimum-Cost Schedule Example 8.5 3($28,000) – 3($1,000) = $81,000

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Critical Path B-D-H-J-K: 66 weeks Crash Activity J by 3 $1,000/week 3($28,000) – 3($1,000) = $81,000 $2,624,000 – $81,000 = $2,543,000 Minimum-Cost Schedule Example 8.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 $2,543,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Critical Path B-D-H-J-K: 66 weeks Crash Activity J by 3 $1,000/week 3($28,000) – 3($1,000) = $81,000 $2,624,000 – $81,000 = $2,543,000 Minimum-Cost Schedule Example 8.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Minimum Cost Schedule A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 $2,543,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Critical Path B-D-H-J-K: 69 weeks Crash Activity J by 3 $1,000/week 3($28,000) – 3($1,000) = $81,000 $2,624,000 – $81,000 = $2,543,000 FinishStart A 12 B9B9 C 10 D 10 E 24 F 10 G 35 H 40 I 15 J1J1 K6K6

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Minimum Cost Schedule A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 $2,543,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Critical Path B-D-H-J-K: 69 weeks Crash Activity J by 3 $1,000/week 3($28,000) – 3($1,000) = $81,000 $2,624,000 – $81,000 = $2,543,000 FinishStart A 12 B9B9 C 10 D 10 E 24 F 10 G 35 H 40 I 15 J11J111 K6K6

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 $2,543,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Critical Path B-D-H-J-K: 66 weeks Crash Activity D by 2 $2,000/week Minimum-Cost Schedule Example 8.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 $2,543,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Critical Path B-D-H-J-K: 66 weeks Crash Activity D by 2 $2,000/week $28,000 + $8,000 – 2($2,000) = $32,000 $2,543,000 – $32,000 = $2,511,000 Minimum-Cost Schedule Example 8.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 $2,511,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Critical Path B-D-H-J-K: 64 weeks Crash Activity D by 2 $2,000/week $28,000 + $8,000 – 2($2,000) = $32,000 $2,543,000 – $32,000 = $2,511,000 Minimum-Cost Schedule Example 8.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 $2,511,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Critical Path B-D-H-J-K: 64 weeks Crash Activity D by 2 $2,000/week $28,000 + $8,000 – 2($2,000) = $32,000 $2,543,000 – $32,000 = $2,511,000 Minimum-Cost Schedule St. Adolf’s Hospital FinishStart A 12 B9B9 C 10 D 10 E 24 F 10 G 35 H 40 I 15 J11J111 K6K6

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 $2,511,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Critical Path B-D-H-J-K: 64 weeks Crash Activity D by 2 $2,000/week $28,000 + $8,000 – 2($2,000) = $32,000 $2,543,000 – $32,000 = $2,511,000 Minimum-Cost Schedule St. Adolf’s Hospital Start A 12 B9B9 D 10 E 24 F 10 Finish C 10 G 35 H 40 I 15 J11J111 K6K6

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 $2,511,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Critical Paths B-D-H-J-K and A-C-G-J-K: 64 weeks Crash Activity K by 1 $4,000/week Minimum-Cost Schedule Example 8.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 $2,511,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Critical Paths B-D-H-J-K and A-C-G-J-K: 64 weeks Crash Activity K by 1 $4,000/week $8,000 – $4,000 = $4,000 $2,511,000 – $4,000 = $2,507,000 Minimum-Cost Schedule Example 8.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 $2,507,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Critical Paths B-D-H-J-K and A-C-G-J-K: 63 weeks Crash Activity K by 1 $4,000/week $8,000 – $4,000 = $4,000 $2,511,000 – $4,000 = $2,507,000 Minimum-Cost Schedule Example 8.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 $2,507,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Critical Paths B-D-H-J-K and A-C-G-J-K: 63 weeks Crash Activity K by 1 $4,000/week $8,000 – $4,000 = $4,000 $2,511,000 – $4,000 = $2,507,000 Minimum-Cost Schedule St. Adolf’s Hospital FinishStart A 12 B9B9 C 10 D88D888 E 24 F 10 G 35 H 40 I 15 J11J111 K6K6

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 $2,507,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Critical Paths B-D-H-J-K and A-C-G-J-K: 63 weeks Crash Activity K by 1 $4,000/week $8,000 – $4,000 = $4,000 $2,511,000 – $4,000 = $2,507,000 Minimum-Cost Schedule St. Adolf’s Hospital FinishStart A 12 B9B9 C 10 D88D888 E 24 F 10 G 35 H 40 I 15 J11J111 K55K555

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Critical Paths B-D-H-J-K and A-C-G-J-K: 63 weeks Crash Activities B and C by 2 $7,000/week and $600/week A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 $2,507,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Minimum-Cost Schedule Example 8.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Critical Paths B-D-H-J-K and A-C-G-J-K: 63 weeks Crash Activities B and C by 2 $7,000/week and $600/week A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 $2,507,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 2($8,000) – 2($7,600) = $800 $2,507,000 – $800 = $2,506,200 Minimum-Cost Schedule Example 8.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Critical Paths B-D-H-J-K and A-C-G-J-K: 61 weeks Crash Activities B and C by 2 $7,000/week and $600/week A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 $2,506,200 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 2($8,000) – 2($7,600) = $800 $2,507,000 – $800 = $2,506,200 Minimum-Cost Schedule Example 8.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Critical Paths B-D-H-J-K and A-C-G-J-K: 61 weeks Crash Activities B and C by 2 $7,000/week and $600/week A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 $2,506,200 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 2($8,000) – 2($7,600) = $800 $2,507,000 – $800 = $2,506,200 Minimum-Cost Schedule St. Adolf’s Hospital FinishStart A 12 B9B9 C 10 D88D888 E 24 F 10 G 35 H 40 I 15 J11J111 K55K555

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Critical Paths B-D-H-J-K and A-C-G-J-K: 61 weeks Crash Activities B and C by 2 $7,000/week and $600/week A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 $2,506,200 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 2($8,000) – 2($7,600) = $800 $2,507,000 – $800 = $2,506,200 Minimum-Cost Schedule St. Adolf’s Hospital FinishStart A 12 B77B777 C88C888 D88D888 E 24 F 10 G 35 H 40 I 15 J11J111 K55K555

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Coors Field

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Probabilistic Time Estimates Figure 8.12 (a) Beta Distribution Mean mab Time Probability

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Probabilistic Time Estimates Time Probability Figure 8.12 (b) Normal Distribution Mean abm 3333 3333 Area under curve between a and b is 99.74%

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Probabilistic Time Estimates AF I CG Finish D E HBJ K Start te =te =te =te = a + 4m + b 6Mean 2 =2 =2 =2 = ( ) b – ab – a66b – ab – a666 2Variance

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Activity B Most OptimisticLikelyPessimistic (a)(m)(b) 7815 Probabilistic Time Estimates AF I CG Finish D E HBJ K Start Example 8.6

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Activity B Most OptimisticLikelyPessimistic (a)(m)(b) 7815 Probabilistic Time Estimates t e = = 9 weeks 7 + 4(8)  2 = = 1.78 ( ) AF I CG Finish D E HBJ K Start Example 8.6

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Example 8.6 St. Adolf’s Hospital OptimisticLikelyPessimisticExpectedVariance Activity(a)(m)(b)Time (t e )(  2 ) Time Estimates (wk)Activity Statistics A B C D E F G H I J K

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital  2 =  (variances of activities) z = T – T E  2  2 = = z = 72 – Probabilities Critical Path = B - D - H - J - K T = 72 days T E = 69 days Example 8.7

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital  2 =  (variances of activities) z = T – T E  2  2 = = z = = – Probabilities Critical Path = B - D - H - J - K T = 72 days T E = 69 days From Appendix 2 P z =.8078 .81 Example 8.7

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Example 8.7  2 =  (variances of activities) z = T – T E  2  2 = = z = = – Probabilities Critical Path = B - D - H - J - K T = 72 days T E = 69 days From Appendix 2 P z =.8078 .81 Project duration (weeks) 6972 Probability of meeting the schedule is Length of critical path Normal distribution: Mean = 69 weeks;  = 3.45 weeks Probability of exceeding 72 weeks is Figure 8.13

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital  2 =  (variances of activities) z = T – T E  2  2 = = z = = – Probabilities Path = A - C - G - J - K T = 72 days T E = 67 days From Appendix 2 P z =.8980 .90 Example 8.7

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. AF I CG Finish D E HBJ K Start St. Adolf’s Hospital ActivityDurationEarliest StartLatest StartSlack C101614–2 G352624–2 J46159–2 K66563–2 D10109–1 H402019–1 E I F TABLE 8.2SLACK CALCULATIONS AFTER ACTIVITIES A AND B HAVE BEEN COMPLETED

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Project Life Cycle StartFinish Resource requirements Time Figure 8.14 Definition and organization Planning Execution Close out

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Solved Problem 1 Finish Start A4A4 B7B7 C5C5 D6D6 E3E3 F 11 G4G4 H3H3 Figure 8.15

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Solved Problem 2 Finish Start A B C D E F G Figure 8.16(a) AON Network

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Solved Problem 2 Figure 8.16(b) AOA Network Finish Start F A B C D E F G Dummy

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Solved Problem 2 Finish Start Figure 8.17 A D E G C F B

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Solved Problem 2 Finish Start Figure 8.17 A D E G C F B Start 1 ESEF LSLF A