DP Johnson, 2005 Dealing with Production Bottlenecks Mini-case Be Sure To Review Notes Area And Related Word Document Forward to Instructors.

Slides:



Advertisements
Similar presentations
Group 1 Ray Quintero, Lei Tian, Jiayin Liu, Morvarid Amirfathi, Rabeeh Sahranavard, Max Tubbs Production Control & Queuing.
Advertisements

PRODUCTION AND OPERATIONS MANAGEMENT
Short-term Capacity Optimization
Question:- A company assembles four products (1, 2, 3, 4) from delivered components. The profit per unit for each product (1, 2, 3, 4) is £10, £15, £22.
© 2007 Pearson Education Constraint Management Chapter 7.
© The McGraw-Hill Companies, Inc., 1998 Irwin/McGraw-Hill Module 11 Operations Scheduling Chapter 16 (pp ) Work Center and definitions  Objectives.
Drum –Buffer-Rope Skorkovský Based on : R. Holt, Ph.D., PE.
Theory of Constraints Scheduling APICS PDM January 14, 2009.
Theory of Constraints Part II: TOC Concepts
Critical Chain Project Management
Case Study 6: Concentrate Line at Florida Citrus Company
DOM 102: Principles of Operations Management Operations Scheduling
Theory of Constraints. IF: Clients never changed their minds And Vendors always supply, whatever we ask for, on time, And We do not have any absenteeism.
Systems Thinking and the Theory of Constraints Any intelligent fool can make things bigger, more complex, and more violent. It takes a touch of genius.
The Production Process
23–1. 23–2 Chapter Twenty-Three Copyright © 2014 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Chapter 18 Synchronous Manufacturing and the Theory of Constraints
1 Ardavan Asef-Vaziri Nov-2010Theory of Constraints 1- Basics Practice; Follow the 5 Steps Process Purchased Part $5 / unit RM1 $20 per unit RM2 $20 per.
7 – 1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. Constraint Management 7 For Operations Management, 9e by Krajewski/Ritzman/Malhotra.
© The McGraw-Hill Companies, Inc., Synchronous Manufacturing and Theory of Constraints.
Systems Thinking and the Theory of Constraints Any intelligent fool can make things bigger, more complex, and more violent. It takes a touch of genius.
Operations Management Contemporary Concepts and Cases Chapter Thirteen Scheduling Operations Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights.
SchedulingProducingControllingSchedulingProducingControlling.
Operations and Production Management
Introduction to Theory of Constraints
Chapter 4 Process Design.
Announcement-exam rules
PowerPoint Authors: Susan Coomer Galbreath, Ph.D., CPA Charles W. Caldwell, D.B.A., CMA Jon A. Booker, Ph.D., CPA, CIA Cynthia J. Rooney, Ph.D., CPA McGraw-Hill/Irwin.
1 1 Slide Short – Term Scheduling Professor Ahmadi.
CHAPTER 3 PROCESS MANAGEMENT. WHAT IS PROCESS MANAGEMENT ? The selection of the inputs, operations, work flows and methods that transform inputs into.
Topics To Be Covered 1. Tasks of a Shop Control Manager.
TOC 1 Theory Of Constraints. TOC 2 Theory of Constraints How does TOC differ from the conventional shop control theory? Throughput definition * Emphasis.
Course: ETLS Managing for Improved Performance Professor: George G. Gleeson Student: Kou Song.
Operations Management Operations Scheduling
Theory of constraints Slovak University of Technology Faculty of Material Science and Technology in Trnava.
McGraw-Hill/Irwin © 2006 The McGraw-Hill Companies, Inc., All Rights Reserved. 1.
Synchronous Manufacturing and Theory of Constraints
The Theory of Constraints
Advaned Planning and Scheduling J.Skorkovský, KPH.
SchedulingProducingControllingSchedulingProducingControlling.
© The McGraw-Hill Companies, Inc., Chapter 17 Synchronous Manufacturing and the Theory of Constraints.
1 Session 18 Implementation of TOC at Tosoh, SMD Laura Blum Production and Inventory Control Manager.
1 Theory of Constraints Short-term Capacity Optimization.
Supplier Capacity Worksheet User Instructions September 2015 Revised December 2, 2015.
Theory of Constraints Part I: Introduction. Theory of Constraints (or TOC) Relatively recent development Looks at the practical aspect of making organizational.
The Goal A Process of Ongoing Improvement Eliyahu M. Goldratt and Jeff Cox.
SchedulingProducingControllingSchedulingProducingControlling.
6-1 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
AXUG Partner Showcase – Introducing Preactor
MEL751: Module on Theory of Constraints
McGraw-Hill/Irwin ©2009 The McGraw-Hill Companies, All Rights Reserved
Strategic Capacity Management
Synchronous Manufacturing and Theory of Constraints
Analytical Tools for Process Analysis and Improvement
The Theory of Constraints
Synchronous Manufacturing
Constraint Management
Performance Measures, Capacity Planning & Scheduling
The Goal.
SE503 Advanced Project Management
Introduction to Scheduling Chapter 1
Process Analysis “If you cannot describe what you are doing as a process, you do not know what you are doing.” W.E. Deming.
Goldratt's Theory of Constraints (TOC)
Manufacturing Production Planning
GATORADE MX Production
Theory of Constraints An Introduction
Theory of Constraints Part II: TOC Concepts
Theory of Constraints An Introduction
Theory of Constraint.
Synchronous Manufacturing and Theory of Constraints
Presentation transcript:

DP Johnson, 2005 Dealing with Production Bottlenecks Mini-case Be Sure To Review Notes Area And Related Word Document Forward to Instructors

DP Johnson, 2005 Dealing with Production Bottlenecks Mini-case The concepts and approach applied in these examples come from the book “The Goal” by Eli Goldratt. This book is required reading for anyone interested in manufacturing, production operations and productivity improvement

The Goal  Every system was built for a purpose  Must define the system’s global goal  Actions of and decision about subsystems must be judged on impact towards the global goal From “The Goal” by Eli Goldratt

Constraints  Anything that limits a system from achieving higher performance vs its goal  Critical Constraint The active constraintThe active constraint The one that is currently limiting the systemThe one that is currently limiting the system From “The Goal” by Eli Goldratt

Flow and Constraints #’s are Maximum Production Rates In Units/Hour

Flow and Constraints % / 50% Split #’s are Maximum Production Rates In Units/Shift

Five Steps  Identify the System’s Constraints  Decide how to exploit the system’s constraints  Subordinate everything else to the above decision  Elevate the system’s constraints  If in the previous steps a constraint has been broken, go back to step 1 From “The Goal” by Eli Goldratt

Identify the System’s Constraints  Prioritize by impact on the goal – otherwise too much trivia  Specifically identify the active constraint  Find a numeric capacity value if possible From “The Goal” by Eli Goldratt

Decide how to exploit the system’s constraints  Find ways to maximize output of bottlenecks – aka active constraints  Find ways to offload and maximize effectiveness of this resource From “The Goal” by Eli Goldratt

Subordinate everything else to the above decision  Priorities for __________________  Do you need to run other resources at full capacity?

Elevate the system’s constraints  Can you… Increase the capacity of the bottleneck?Increase the capacity of the bottleneck?  Speed up?  Add more available time?  Reduce setup time and other downtime? Cut the constraint resource out of some processes?Cut the constraint resource out of some processes? Use alternate resources?Use alternate resources? Improve the effectivenessImprove the effectiveness  Inspection prior to bottleneck? Can we break the constraint?Can we break the constraint?

If in the previous steps a constraint has been broken, go back to step 1  Once you break the critical / active constraint there will be a new one  Find the new one and repeat the process From “The Goal” by Eli Goldratt

Flow and Constraints /50 Split ID Constraints ExploitSubordinateElevateBreak/Repeat What if demand is = 275 per shift? #’s are Maximum Production Rates In Units/Shift

Multiple Product Flows What if demand is… 150 per hour of A 150 per hour of B Flow for A Flow for B #’s are Maximum Production Rates In Units/Hour

Assembly Product Flows What if demand for assemblies is 150 per shift Flow for A Flow for B Assembly Station Combines part A and part B into one assembly which is sold as a complete product Capacity: 75 assemblies per shift 100 Production Rates In Units/Shift

Cycle Time Example 1.5 min/unit of D 1.5 min/unit of C 1.5 min/unit of D What if demand is 150 assemblies per shift and One shift has 410 available production minutes? Flow for C Flow for D Assembly Station Combines part C and part D into one assembly which is sold as a complete product Standard Time: 3 min per assembly 2 Min/unit of C 1 min/unit of D 3 Min/unit of C Machine 1 Machine 2 Machine 3 Machine 4 Machine 5

Example 1 Bobco makes a product consisting of these 9 parts which are manually assembled. There are 8 plastic parts and one turned metal part. A process flow diagram is on the next page

Example – Can you find the bottleneck if all departments run 40 hrs/week? - Can you meet a forecasted demand for 2000 units per week? Bobco

Example – Can you find the bottleneck if all departments run 40 hrs/week? - Can you meet a forecasted demand for 2000 units per week? Bobco FIND THE CAPACITY OF THE SYSTEM

Samco Mini-Case Problem   Samco makes three products A B and C. The Three are very similar..   A two metal and three plastic components assembled manually   B two metal and three plastic components assembled manually   C two metal and three plastic components assembled manually

The process map and details are shown on the following pages Parts for Product A Parts for Product B Parts for Product C

Samco

The production system is having problems. WIP is piling up all over the factory. Orders are going out late. Departments are requesting overtime to catch up, but even when overtime is authorized for all departments the situation does not improve. When overtime is authorized the backlogged orders are filled, but WIP seems to grow, adding to the confusion and congestion on the floor, which seems to generate additional request for overtime to catch up and clear out WIP and new late orders.

What can be done? The company has no money for capital investments (new equipment) but is willing to consider implementing recommendations that do not involve capital spending.