Developing a Project Plan

Slides:



Advertisements
Similar presentations
Developing a Project Plan CHAPTER SIX Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Advertisements

Developing a Project Plan CHAPTER SIX Student Version Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Chapter 6: Developing a Project Plan
Project Management 6e..
Chapter 17 Project Management McGraw-Hill/Irwin
Developing the Project Plan
Where We Are Now Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved.
Project Management Project Management
Developing a Project Plan
OPSM 639, C. Akkan1 Network Planning Purposes of network planning –Determine the intended timing of activities –Determine the estimates of resource requirements.
CSSE Sep.2008 Constructing and Analyzing the Project Network Diagram Chapter 6.
Developing a Project Plan
PERT / CPM PERTProgram Evaluation & Review Technique CPMCritical Path Method.
CSSE 372 Week 6 Day 2 Constructing and Analyzing the Project Network Diagram  PERT Chart PERT was invented for the Nautilus submarine project. Ok, maybe.
1 University of Wales Bachelor of Science (Industrial Engineering and Management) Year 3 Copyright © 2012 MDIS. All rights reserved.Section
Chapter 4: Schedule, cost, and situation analysis (pt. 1) ISE 443 / ETM 543 Fall 2013.
9-1 Project Scheduling: Networks, Duration Estimation, and Critical Path Chapter 9 © 2007 Pearson Education.
Project Scheduling: Networks, Duration estimation, and Critical Path.
MGMT 483 Week 8 Scheduling.
9-1 Project Scheduling: Networks, Duration Estimation, and Critical Path Chapter 9 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
5/4/20151 NETWORK SCHEDULING TECHNIQUES. 5/4/20152 Network Diagrams  PMI defines the scheduling process as: “the identification of the project objectives.
Project Development Scheduling and Probability of Completion.
Project Management OPER 576 Project Networks Greg Magnan, Ph.D. April 29, 2004.
Project Scheduling: Networks, Duration Estimation, and Critical Path
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Day 15.
© 2000 by Prentice-Hall Inc Russell/Taylor Oper Mgt 3/e Chapter 6 Project Management.
Time Management Ahmed Awad, Ph.D., PMP. Time Management It includes the processes required to ensure timely completion of the project. b Activity Definition.
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall o P.I.I.M.T o American University of Leadership Ahmed Hanane, MBA, Eng, CMA, Partner.
Where We Are Now. Where We Are Now Developing the Project Plan The Project Network A flow chart that graphically depicts the sequence, interdependencies,
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Developing a Project Plan Chapter 6.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Copyright 2006 John Wiley & Sons, Inc. Project Management OPIM 310.
Why is project Management important
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6.
Project Management (專案管理)
Project Management Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.
Project Planning and Budgeting Recall the four stages Project Definition and Conceptualization Project Planning and Budgeting Project Execution and Control.
0 Production and Operations Management Norman Gaither Greg Frazier Slides Prepared by John Loucks  1999 South-Western College Publishing.
Chapter 7 – PERT, CPM and Critical Chain Operations Management by R. Dan Reid & Nada R. Sanders 4th Edition © Wiley 2010.
Project Planning & Scheduling What is a “project”? Objectives and tradeoffs Planning and Control in Projects Scheduling Methods Constant-Time Networks.
Project Management Fundamentals - Planning Tools 1.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Chapter 4 MIS Project Management Lecturer Sihem Smida Sihem Smida Developing a project plan.
Scheduling Scheduling : is the process of converting a project action plan into an operating time table. Why scheduling ? To answer the following questions:
Chapter 16 – Project Management
PROJECT MANAGEMENT.
Project Management (專案管理)
Project Management -- Developing the Project Plan
Project Management: PERT/CPM
Project Scheduling KULIAH 10 Magister Sistem Informasi
Chapter 17 Project Management McGraw-Hill/Irwin
Project Planning & Scheduling
Project Management (PERT/CPM) PREPARED BY CH. AVINASH
Project Scheduling KULIAH 10 Magister Manajemen
Project Planning & Scheduling
Project scheduling Precedence diagram method & Resource scheduling
Project Planning and Budgeting
Developing a Project Plan
Project Scheduling: networks, duration estimation, and critical path
Time Planning and Control Precedence Diagram
ENM448-Project Planning and Management
Chapter 16 – Project Management
Presentation transcript:

Developing a Project Plan Chap 6 Developing a Project Plan

Developing a Project Plan Chap 6 The specific actions of the project are identified in the Work Packages The resources, time and cost have been identified, based on the work defined in the Work Packages. These costs have been assigned to a person or group identified in the Resource Allocation Matrix. Now it is necessary to identify the relationship of each activity. Which tasks must be started or completed before the next activity can begin. A network diagram is one method of showing this relationship

What is a Network Diagram? Chap 6 A D C G E H F B Network Diagram A visual flow diagram of the sequences, interrelationships and dependencies of all the all the activities necessary to complete the project. An activity is an element of the project that consumes time. More than one WBS work plan can be included in an activity. Networks provide the project schedule by identifying the dependencies, sequencing and timing of the activities. Activity time is derived from the task times in the work packages. Ask the three questions

Network Terminology Chap 6 Activity – An element of the project that requires time. Merge Activity – an activity that has more than one activity immediately preceding it. Parallel Activities – Activities that can take place at the same time. Path – A sequence of connected dependent activities Critical Path – The path with the longest duration through the network. Any increase of time to the CP will result in a equal increase in the project. Event – A point in time when an activity is started or completed. It does not consume time Burst Activity – An activity that has more than one activity immediately following it.

Basic Rules to Follow Networks flow from left to right Chap 6 Networks flow from left to right An activity cannot begin until all preceding connected have been completed. Arrows on networks indicate precedence and flow Each activity should have a unique id number An activity ID number must be larger that of any preceding activities Looping or recycling thru a set of activities are not allowed. Conditional statements are not allowed. Use a common start and end when you have multiple starts and or projects.

Deterministic Time Estimates Chap 6 Steps 1. Calculate the length of each path 2. Determine the critical path 3. Determine the expected length of the project 4. Define slack time for each activity Compute ES, LS, EF, LF for each activity Algorithms Early Start (ES): Early Finish (EF): ES + t Late Start (LS): LF - t Late Finish (LF): Slack (SL): LS - ES or LF - EF

Example - Deterministic Chap 6 Activity Description Time Precedence A Prepare BOM 1 - B Prep assembly charts 3 A C Order & await delivery of materials 7 A D Organize production line 2 B E Specify inspection procedures 1 B F Setup inspection stations 2 D,E G Train workers 3 D H Assemble product 7 C,F,G Find ES, EF, LS, LF, Slack, CP and project duration.

Deterministic Precedent Diagram Chap 6 A C B E D F G H

Probabilistic When the task time to complete varies. Chap 6 When the task time to complete varies. Uses a BETA distribution to evaluate Uses estimates of: Most optimistic (a) Most likely (m) Most pessimistic (b) Algorithms: Expected event time to complete: te = (a + 4m + b) / 6 Variance (2e): = (b - a)2 / 36 Expected path time to complete: t path =  t e Path Variance(path): =  2e

Probabilistic Example Chap 6 Activity Description a b m Precedence A Prepare BOM 0.6 1.8 0.9 - B Prep assembly charts 2.0 4.0 3.0 A C Order & await delivery of materials 5.0 9.0 7.0 A D Organize production line 1.2 3.6 1.8 B E Specify inspection procedures 0.7 1.3 1.0 B F Setup inspection stations 1.0 5.0 1.5 D,E G Train workers 2.0 3.6 3.1 D H Assemble product 6.0 8.0 7.0 C,F,G Find: te , e, t path , path, ES, LS, LF, EF, SLACK, CP Finding ES, LS, LF, EF & Slack is the same as deterministic. Finding the probability that project will complete in time t Algorithm: Z = (t - t cp ) / cp Find P(Z) using normal distribution table. Probability that the project will not be completed is 1 - P(Z)

Probabilistic Precedent Diagram Chap 6 A B E D F G H C Z = t – tcp / cp Z = 16 – 16/.7 Z = 0 P(Z) = .5 Z = 17 – 16)/.7 = 1.42 P(Z) = .992 cp = ( )0.5 = (.04+.11+.16+.07+.11)0.5 = .70

Advanced Network Techniques Chap 6 Laddering Laddering is used when it is not necessary for a task to be completely finished before the next activity is started. Trench 1/3 Trench 1/3 Trench 1/3 Pipe 1/3 Pipe 1/3 Pipe 1/3 Refill 1/3 Refill 1/3 Refill 1/3 Use of Lags Represents the minimal amount of time before the next task can begin. Can be used to represent wait times Can be used to constrain the start and finish of an activity Make sure lag is not used as a “slush” factor to reduce risk Lag 12 hrs Paint Box Finish – to- Start

Activity Relationships Chap 6 Start – To – Start (SS) Primarily used when activities can be performed simultaneously Can be used to compress the project by changing finish –to- start relationships by using start – to – start with lags Can be used in cases of laddering Trench Pipe Refill Lag 3 hrs Finish – to –Finish (FF) The finish of one depends on the finish of another. An example is documentation of the other activity (i.e. testing, design, minutes of a meeting) Start – to – Finish (SF) One activity will continue until another event starts.

Hammock Activities An activity that spans over a segment of a project. Chap 6 An activity that spans over a segment of a project. The activity duration is determined after the network plan is drawn. Used to identify the use of fixed resources or costs over a project segment. The duration is determined from the early start of the initial activity of the segment to the early finish of the last activity. The hammock activity does not add to the project time but parallels one or more activities. copy machine movie camera quality control Useful for assigning and controlling indirect costs

Project Plan Example Boulangerie Fashion Show European Restaurant Chap 4 Boulangerie Fashion Show European Restaurant

Chap 6 Questions