1 MC Assembly over the VV FPA Station 3 FDR Review July 13, 2007 T. Brown.

Slides:



Advertisements
Similar presentations
FEA Reference Guide See additional material herehere.
Advertisements

Beams Stephen Krone, DSc, PE University of Toledo.
C2 to C5 fit up review-R41 Review of MC Type C to C assembly clearances with C2 to C5 shell surface interface details 12/19/06 Rev 4.
STAR Detector Main Support System1 Lateral Tracking of the STAR Detector during Translation. November 23, 2005 Ralph L. Brown STAR Operations Group.
Deviations from fiducial locations are unacceptable in areas despite high accuracy at alignment points.
Beams and Frames.
Wall Form Design Example (Continued)
Vacuum Vessel Production Readiness Review
1 MC Assembly via Test Cell Crane FPA Stage 3 Peer Review August 12, 2005 T. Brown.
FDR Station 3 lift fixture, laser screens and brackets T. Brown and L. Morris with analysis support from A. Brooks December 3, 2007.
Slide HALLD TAGGER MAGNET STRUCTURAL ANALYSIS Presented by William Crahen 6/10/09 Pole Plate analysis Vacuum chamber analysis Vacuum chamber tie rods and.
MICE Collaboration Meeting at Frascati, Jun 26~29, 2005 Iron Shield Mounting Design Stephanie Yang.
GLAST LAT ProjectDOE/NASA Mechanical Systems Peer Review, March 27, 2003 Document: LAT-PR-0XXXX Section 7.1 Stress Analysis 1 GLAST Large Area Telescope:
NSTX ARMOR PLATE 2/18/10 NEUTRAL BEAM ARMOR PRELIMINARY ANALYSIS.
NCSX Modular Coil Turning Fixture FDR. FDR Charge (answers were added below after the review) Modular Coil Turning Fixture FDR - Charge to Reviewers –The.
SHEAR AND BENDING MOMENT DIAGRAMS IN HORIZONTAL BEAMS WITH
MC Type-B fit up review1 Review of MC Type B assembly clearances reviewing A-to-B and B-to-C interfaces 3/1/07 Summary: Wing interfaces look okay between.
Multiple Coil Lift Calculation. Purposes of the Study  To investigate the stress distribution in the MCWF and the lifting device.  To make sure mounting.
Reinforced Concrete Design
1 Stage 3 Peer Review October 26, 2006 T. Brown. 2 Field Period Assembly (FPA) 1.Make sure the requirements for the tooling is well defined (including.
FOOTINGS. FOOTINGS Introduction Footings are structural elements that transmit column or wall loads to the underlying soil below the structure. Footings.
Analyses of Bolted Joint for Shear Load with Stainless Steel Bushing and Frictionless Shim-Flange Interface Two cases of shim plates were investigated.
NCSX Modular Coil Turning Fixture FDR. Background Modular Coil winding forms are cast structures which provide the foundation on which the coils are constructed.
1 Stage 3 Peer Review October 26, 2006 T. Brown. 2 Field Period Assembly (FPA) – Stage 3 1.Make sure the requirements for the tooling is well defined.
LAT-TD GLAST LAT Project 1x4 Grid Lift Fixture Weld Analysis September 19, 2003 Youssef Ismail.
1 MCHP-1 clamp and MC port opening metrology review ProE model: stb-mchp-1_vvsa1_pppl_best_fit.asm stb-fpa_mech_left_side.asm, Rep: mchp-1_clamp_metrol_pts.
Tulkarem Multipurpose Sport Hall Prepared by: Moatasem Ghanim Abdul-Rahman Alsaabneh Malek Salatneh Supervisor: Dr. Shaker Albitar.
Modular Coil Assembly Bolted Joint PDR 2/22/07. Objectives The review objectives include... Define the location of additional inboard bolts Finalize the.
Supported by NSTX Centerstack Upgrade Project Meeting P. Titus October Aluminum Block Analyses.
ZDC Remote Handling Tool Structure and Force Analysis P. Debbins University of Iowa December 10, 2009.
1 MC Assembly over the VV FPA Station 3 FDR Review July 17, 2007 T. Brown.
NCSX NCSX TF Coil Procurement 1 February 3, 2006 Michael Kalish NCSX TF Coil Procurement.
NCSX Modular Coil Joint Load/Stress Calculation By Leonard Myatt Myatt Consulting, Inc.
10/31/2007Mike Viola1 NCSX Field Period Assembly + + = October 31, 2007 Mike Viola Field Period Assembly Manager.
Nonlinear Analyses of Modular Coils and Shell structure for Cooldown and Modular Coil EM Loads Part 2 – Results of Clamp Assembly, Wing Bags, Poloidal.
Results of Linear Stress Analyses for Modular Coils and Coil structure For 2T High Beta Currents at 0 Seconds and Initial Coil Shrinkage of in/in.
An Analysis of Shell Structure for Dead Load H.M. Fan PPPL September 16, 2005.
Analyses of Bolted Joint for Bolt Preload and Shear Load
Finite Element Analysis of the18 Turn Beam H. F. Fan November 5, 2004.
F. Dahlgren -SC Project Review of NCSX, April 8-10, 2008 PF, TF, & Trim Coil Supports (WBS-15) Core Base Support Structure (WBS-17) F. Dahlgren NCSX Coil.
The analysis runs in the following slides are based on a W8 x 58.0 wide beam with dimensions shown bellow.
1 NCSX WBS HANDLING/SUPPORT UPDATE PLG 7/23/03 STATUS Study is for 120 degree VVSA field period assembly. Vessel Installation Support Concept.
1 Field Period Assembly Office of Science Project Review Princeton Plasma Physics Laboratory Princeton, NJ November 2, 2005 T. Brown Princeton Plasma Physics.
SC Project Review of NCSX, April 8-10, 2008 NCSX Field Period Assembly Mike Viola NCSX Field Period Assembly Manager NCSX Project Review April 8-10, 2008.
SC Project Review of NCSX, April 8-10, 2008 NCSX Machine Assembly E. D. Perry.
LMQXFA Cold Mass Assembly Antonios Vouris Fermilab February 3, 2016.
Results of FEA for the PETS EBW tooling Riku Raatikainen
1 Assembly Tooling PU Workshop on NCSX Cost & Schedule Princeton Plasma Physics Laboratory Princeton, NJ Mar 1-4, 2007 T. Brown Princeton Plasma Physics.
NCSX VACUUM VESSEL PL Goranson Final Design Review November 17, 2005 Man Access Port /Lateral Supports NCSX.
Beam Design Beams are designed to safely support the design loads.
Field Period Assembly Wayne Reiersen SC Project Review PPPL May 2006.
Nonlinear Analyses of Modular Coils and Shell structure for Coil Cool-down and EM Loads Part 1 – Results of Shell Structure and Modular Coils H.M. Fan.
FEM Analysis of the Stage3 Support Frame H.M. Fan March 14, 2007.
1 FPA Stage 2 Peer Review May 12, 2006 T. Brown. 2 FPA Stage 2 Status Summary of Stage 2 activities Review current design status Review schedule details.
A View of NCSX Structural System and Load Path for the Base Support Structure.
1 Modular Coil Assembly Fixture (MCAF) Information Meeting February 23, 2005.
SEPT 20, 2006 T. Brown, M. Cole, P. Fogarty, P. Goranson, K. Freudenberg, D. Williamson NCSX STAGE 2 COIL TO COIL ASSY.
Analysis of TF Load Paths and Vacuum Vessel Loading H. M. Fan Jan. 22, 2009.
Forklift pick set-up interfacing with a MCHP
1 FPA Stage 2 MC Flange Assembly Issues and Design Proposals June 20, 2006 T. Brown.
1 VV Support Fixture FPA Stage 1 PDR Review August 10, 2005 T. Brown.
NCSX Modular Coil Joint Load/Stress Calculation By Leonard Myatt Myatt Consulting, Inc.
TORSION OF A SHAFT WITH A SHOULDER FILLET
Status of the PANDA Magnet Yoke Presented by E. Koshurnikov GSI, February 7, 2013.
PANDA Magnet Iron Yoke Strength Analysis
2K Cold Box Structural Analysis
Roller/rail - System for PANDA
SBN Far Detector Installation & Integration
contents Design of beams (week 11,12,13), (10,17,24 Nov.)
Stress Analysis on SunSiphon Rack Design
Presentation transcript:

1 MC Assembly over the VV FPA Station 3 FDR Review July 13, 2007 T. Brown

2 1.Are the requirements well defined? 2.Does the design meet the requirements? 3.Do the drawings define the design adequately to be used as the sole basis for fabrication and acceptance of the support fixture? 4.Does the analysis adequately underpin the design and have they been checked? 5.Has safety been adequately addressed in the design of the support fixture? 6.Can the support fixture be fabricated and installed within the budget and schedule identified in the project baseline? 7.Have all relevant chits from previous design reviews been adequately addressed? Charge

3 Scope This review covers the general arrangement of the Station 3 assembly components, the support fixtures for the MC’s and VV and the laser screens. The local alignment fixtures used to provide added positional adjustments of the MCHP and the lift fixture is not covered. This will be reviewed at a later date.

4 Requirements Assembly Position the VV to allow installation of the MCHP’s Provide movement of left MCHP support to allow final installation of right side MCHP Provide an accurate mounting for the laser path tracings Provide a method for installing the MCHP over the VV without interferences Allow access area to install Type-A flange hardware The goal for the final tolerance for the completed assembled MC period is ± 0.020”. Structural Provide a stable support for the VV to allow installation of the MCHP’s Provide a stable support for each MCHP that minimizes deflection of the interfacing MC Type-A flanges Provide a stable laser path tracing support frame

5 General Arrangement (MCHP / MC support)

6 General Arrangement (laser screen – left side)

7 General Arrangement (laser screen – right side)

8 General Arrangement (VV support)

9 Vacuum Vessel is supported and is in position to receive left MCHP Take metrology measurements Define VV position Position the VV Adjustable VV base support Adjustable VV lateral support

10 Peer review Two bolts were added since peer review VV base support

11 Diagnostic junction box geometry A clearance space of 1.5” exists between the top of the junction box and the surface of the support structure.

ksi VM stress with on 1.25” bolt ” peak deflection 3,629 lb VV load

13 VV / Screen arrangement Laser screens have been sized for laser tracings. Tracks have been extended to remove MC supports during coil installation.

14 MCHP support structure The MCHP is support off a base structure attached to the MC shell feet. The base structure rolls on rails which were extended because of assembly interferences. Support rails Base support structure

15 8 ton Hilman Roller Guide Roller A local channel is used to lock the structure in place. MCHP roller guide system The support beam was extended on the one side.

16 Support and leveler system pre-attached to MC. High load leveler support AirLoc Wedgemount bolt on spherical seat precision leveler 17,900 lb capacity +/ ” displacement Local hold down support.

17 Metrology measurements taken to establish left MCHP position The right MCHP position set to spherical seats using the crane/mechanized screw system Pre-fit Type-A interface The deflection of the flange A surface when supported off he base was evaluated.

18 CG location “CAD” weight of MCHP with support is 21,933 lbs

19 VV motion over the MCHP

20 VVSA1 metrology measured surface points added to VV 1.38” The Type-B MC winding form comes within 1.38” to the CAD defined VV surface.

21 There are no out-of tolerance points in the tightest region on VVSA1. Local measurement were made to confirm that all added surface components did not extend more than 1” off the surface.

” minimum clearance to surface components Step 0 defines the final assembled position 1” limit of surface components above vessel surface. In general there is 2” assembly space above the VV CAD surface. With ≤ 1” surface components, leaves a min. 1” assembly gap. VV / MCHP clearances

23 FEM Analysis of the Stage3 Support Frame H.M. Fan March 14, 2007

24 Shell-support interfaces Inboard shell type C Outboard shell type C Outboard shell type A FEA Model Support frame

25 FEA Assumptions Linear analysis Not including clamps in the model Weight of clamp was added to the weight of modular coil Constraints at four bottom pads of the support frame Material properties:

26 Un-deformed shape with scale of deformation = 468 Total Displacement The inboard displacements are higher than the outboard displacements. Unit of Displacement is meter (0.015”) (0.0034”) (0.0051”)

27 Vertical Displacement The maximum downward displacement occurs at the inboard region of the shell type A. Unit of Displacement is meter (0.001”)

28 Scale of Displacement = 400 Vertical Displacement of Support Frame It is better to rotate the column 90° or to add stiffeners below the beam. add a stiffener here - The plots show the deformed and un-deformed shapes

29 Maximum stress von Mises Stress Stresses in the MCWF are small. The peak stress (~2 ksi) occurs at the outboard leg of the shell type A. The max. von mises stress in the support frame (9.98 ksi) locates in the horizontal frame underneath the inboard column. Unit of stress is pascal

30 Inboard shell type C Outboard shell type A Outboard shell type C Contact Pressure at Shell-Support Interfaces Unit of stress is pascal - The contact pressures are not uniform on the contact surfaces (877 psi)

31 Forces on Top of Column Supports Forces and moments are shown in the global coordinate system: The calculated dead weight of MC and MCWF is kips. If the actual measured dead weight is greater than that, all the calculated stresses, forces, and displacements can be reasonably increased by the same ratio. Inboard column under shell type C has the highest axial load and the bending moments.

32 W6X25Ix = 53.3 in^4 Sx = 16.7 in^3 rx = 2.67 in Iy = 17.1 in^4 Sy = 5.62 in^3 ry = 1.53 in Column stress criteria are checked as follows: Column Design where:F a is the allowable axial stress in the absence of bending moment f a is the computed axial stress

33 Summation of total forces and moments at the base of the inboard column in the global coordinate system are: FX = N FY = N FZ = N MX = -332 m-N MY = 31 m-N MZ = -22 m-N orFX = lb FY = - 52 lb FZ = 9980 lb MX = in-k MY = 0.27 in-k MZ = in-k For ½ -13 UNC A307 bolt, Fy = 33 ksi, the allowable single shear load is 1.96 kip. Allowable tensile area is in 2 and the allowable bolt tension is 2.81 kip. Bolt stress X = 3” Y = 4” With bolt group as shown on the right, the maximum shear in the bolt is 0.03 kip, which is much smaller than the allowable shear 1.96 kip. The maximum tension in the bolt is 0.64 kips that also smaller than allowable tension.

34 FEM Analysis of the Stage3 Support Frame Follow-up

35 HM loading were applied to each support, ignoring the MCHP movement constraints at the top of the posts ” max deflection

36 Incorporating square tubes and local stiffeners reduced the peak deflection from 0.148” to 0.009” (also excluding MCHP moment constraints).

37 Deflected surface of Type-A flange shown is from HM’s original analysis. With additional stiffness added to base structure the Type-A flange deflection should be reduced ” 0.004” (0.0023”) (0.004”) (0.010”) (0.011”)

38 59” Review of Type-A flange bolt access

39 Review of earlier chits

40 1.Are the requirements well defined? 2.Does the design meet the requirements? 3.Do the drawings define the design adequately to be used as the sole basis for fabrication and acceptance of the support fixture? 4.Does the analysis adequately underpin the design and have they been checked? 5.Has safety been adequately addressed in the design of the support fixture? 6.Can the support fixture be fabricated and installed within the budget and schedule identified in the project baseline? 7.Have all relevant chits from previous design reviews been adequately addressed? Charge