Advanced Simulation Methods. © The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran2 Overview Advanced Simulation Applications Beta Distribution.

Slides:



Advertisements
Similar presentations
Chapter 17 Project Management McGraw-Hill/Irwin
Advertisements

Session 8a. Decision Models -- Prof. Juran2 Overview Operations Simulation Models Reliability Analysis –RANK, VLOOKUP, MIN Inventory Order Quantities.
Chapter 18 If mathematical analysis is too difficult, we can try each possibility out on paper. That way we can find which alternative appears to work.
Session 9a. Decision Models -- Prof. Juran2 Overview Finance Simulation Models Forecasting –Retirement Planning –Butterfly Strategy Risk Management –Introduction.
Introduction to Risk Analysis Using Excel. Learning Objective.
Session 8b Decision Models -- Prof. Juran.
Terminology Project: Combination of activities that have to be carried out in a certain order Activity: Anything that uses up time and resources CPM: „Critical.
1 Topics to cover in 2 nd part ( to p2). 2 Chapter 8 - Project Management Chapter Topics ( to p3)
Project Management in Practice Fifth Edition Copyright © 2014 John Wiley & Sons, Inc. Chapter 5 Scheduling the Project.
Topic 2. DECISION-MAKING TOOLS
Simulation Operations -- Prof. Juran.
Session 7a. Decision Models -- Prof. Juran2 Overview Monte Carlo Simulation –Basic concepts and history Excel Tricks –RAND(), IF, Boolean Crystal Ball.
Outline/Coverage Terms for reference Introduction
McGraw-Hill Ryerson Copyright © 2011 McGraw-Hill Ryerson Limited. Adapted by Peter Au, George Brown College.
Spreadsheet Demonstration New Car Simulation. 2 New car simulation Basic problem  To simulate the profitability of a new model car over a several-year.
Probability Distributions and Stochastic Budgeting AEC 851 – Agribusiness Operations Management Spring, 2006.
Engineering Economic Analysis Canadian Edition
Session 9b. Decision Models -- Prof. Juran2 Overview Finance Simulation Models Securities Pricing –Black-Scholes –Electricity Option Miscellaneous –Monte.
Simulation II.
Project Management An interrelated set of activities with definite starting and ending points, which results in a unique outcome for a specific allocation.
1 SIMULATION – PART I Introduction to Simulation and Its Application to Yield Management For this portion of the session, the learning objectives are:
EMGT 501 HW #2 Answer. 020/3 X 3 05/601-1/62/3050/3 X 6 0-5/300-2/3-1/3180/3 (c).3/230with )3/80,0,0,3/50,3/20,0(*)*, ( solution Optimal   Z.
Building and Running a FTIM n 1. Define the system of interest. Identify the DVs, IRVs, DRVs, and Objective. n 2. Develop an objective function of these.
Session 7b. Decision Models -- Prof. Juran2 Example: Preventive Maintenance At the beginning of each week, a machine is in one of four conditions: 1 =
Chapter 4 Probability Distributions
Session 5a Decision Models -- Prof. Juran.
Session 10b. Decision Models -- Prof. Juran2 Overview Marketing Simulation Models New Product Development Decision –Uncertainty about competitor behavior.
Lecture Slides Elementary Statistics Twelfth Edition
Statistics for Managers Using Microsoft Excel, 4e © 2004 Prentice-Hall, Inc. Chap 6-1 Chapter 6 The Normal Distribution and Other Continuous Distributions.
Inferences About Process Quality
Lecture 17 Interaction Plots Simple Linear Regression (Chapter ) Homework 4 due Friday. JMP instructions for question are actually for.
MATHEMATICS 3 Operational Analysis Štefan Berežný Applied informatics Košice
Simulation.
Chapter 24: Comparing Means.
© Harry Campbell & Richard Brown School of Economics The University of Queensland BENEFIT-COST ANALYSIS Financial and Economic Appraisal using Spreadsheets.
Spreadsheet Demonstration
Chapter 9: Simulation Spreadsheet-Based Decision Support Systems Prof. Name Position (123) University Name.
Copyright © 2010, 2007, 2004 Pearson Education, Inc. Review and Preview This chapter combines the methods of descriptive statistics presented in.
Slide 1 Copyright © 2004 Pearson Education, Inc..
Example 2.5 Decisions Involving the Time Value of Money.
Example 9.2 Customer Response to a New Sandwich Confidence Interval for a Mean.
1 Statistical Distribution Fitting Dr. Jason Merrick.
DISCRETE PROBABILITY DISTRIBUTIONS Chapter 5. Outline  Section 5-1: Introduction  Section 5-2: Probability Distributions  Section 5-3: Mean, Variance,
Engineering Economic Analysis Canadian Edition
The McGraw-Hill Companies, Inc. 2006McGraw-Hill/Irwin 12 Financial and Cost- Volume-Profit Models.
© 2003 The McGraw-Hill Companies, Inc. All rights reserved. Project Analysis and Evaluation Chapter Eleven.
9-1 Chapter 9 Project Scheduling Chapter 9 Project Scheduling McGraw-Hill/Irwin Copyright © 2005 by The McGraw-Hill Companies, Inc. All rights reserved.
קורס סימולציה ד " ר אמנון גונן 1 ההתפלגויות ב ARENA Summary of Arena’s Probability Distributions Distribution Parameter Values Beta BETA Beta, Alpha Continuous.
Crystal Ball: Risk Analysis  Risk analysis uses analytical decision models or Monte Carlo simulation models based on the probability distributions to.
Switch off your Mobiles Phones or Change Profile to Silent Mode.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
1 3. M ODELING U NCERTAINTY IN C ONSTRUCTION Objective: To develop an understanding of the impact of uncertainty on the performance of a project, and to.
Computer Simulation. The Essence of Computer Simulation A stochastic system is a system that evolves over time according to one or more probability distributions.
Session 25 University of Southern California ISE514 November 17, 2015 Geza P. Bottlik Page 1 Outline Questions? Exam results – very good 19 grades improved.
Lecture 03.0 Project analysis Copyright © 2006 by The McGraw-Hill Companies, Inc. All rights reserved McGraw-Hill/Irwin.
CPM – Critical Path Method Can normal task times be reduced? Is there an increase in direct costs? Additional manpower Additional machines Overtime, etc…
Chapter 7 : Risk Management – part 2
Chapter 5 Probability Distributions 5-1 Overview 5-2 Random Variables 5-3 Binomial Probability Distributions 5-4 Mean, Variance and Standard Deviation.
Q1) A precedes C. B precedes D & E. C precedes F & G. D precedes G.
Slide 1 Copyright © 2004 Pearson Education, Inc. Chapter 5 Probability Distributions 5-1 Overview 5-2 Random Variables 5-3 Binomial Probability Distributions.
Probability Distributions ( 확률분포 ) Chapter 5. 2 모든 가능한 ( 확률 ) 변수의 값에 대해 확률을 할당하는 체계 X 가 1, 2, …, 6 의 값을 가진다면 이 6 개 변수 값에 확률을 할당하는 함수 Definition.
Supplementary Chapter B Optimization Models with Uncertainty
Chapter 16 – Project Management
Project Management Chapter Topics
Chapter 17 Project Management McGraw-Hill/Irwin
Project Management (PERT/CPM) PREPARED BY CH. AVINASH
Basic Project Scheduling
Basic Project Scheduling
LESSON 8: RANDOM VARIABLES EXPECTED VALUE AND VARIANCE
Presentation transcript:

Advanced Simulation Methods

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran2 Overview Advanced Simulation Applications Beta Distribution Operations –Project Management (PERT) “Textbook” method Crystal Ball Marketing –New Product Development decision

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran3 Beta Distribution Parameter Description Characteristics Min Minimum Value Any number-∞ to ∞ Max Maximum Value Any number-∞ to ∞ Alpha (α) Shape Factor Must be > 0 Beta (β) Shape Factor Must be > 0 The Beta distribution is a continuous probability distribution defined by four parameters:

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran4

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran5 The Beta distribution is popular among simulation modelers because it can take on a wide variety of shapes, as shown in the graphs above. The Beta can look similar to almost any of the important continuous distributions, including Triangular, Uniform, Exponential, Normal, Lognormal, and Gamma. For this reason, the Beta distribution is used extensively in PERT, CPM and other project planning/control systems to describe the time to completion of a task.

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran6

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran7 The project management community has evolved approximations for the Beta distribution which allow it to be handled with three parameters, rather than four. The three parameters are the minimum, mode, and maximum activity times (usually referred to as the optimistic, most-likely, and pessimistic activity times). This doesn’t give exactly the same results as the mathematically- correct version, but has important practical advantages. Most real-life managers are not comfortable talking about things like probability functions and Greek-letter parameters, but they are comfortable talking in terms of optimistic, most-likely, and pessimistic. PERT Approximations

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran8 3-step Procedure

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran9 Beta Distributions in Crystal Ball The Crystal Ball distribution gallery includes the Beta distribution, but in a form slightly different from the description above. Specifically, Crystal Ball assumes the minimum is zero. Instead of “maximum” or “pessimistic”, it asks for a “Scale” parameter.

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran10

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran11 Assume we are given optimistic, most-likely, and pessimistic times of 1, 2, and 3 time units, respectively. We first use these parameters to calculate the mean (formula (iii)), standard deviation (formula (iv)), alpha (formula (v)), beta (formula (vi)), and the difference between the maximum and minimum, as shown here: Example

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran12 Next, we create a Crystal Ball assumption cell in A2, using the parameters shown: We make a cell next to the assumption cell, adding the random number to the minimum. Cell B3 will now be a Beta-distributed random variable with the optimistic, most-likely, and pessimistic activity times we specified.

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran13 Operations Example: Project Management (PERT) Sharon Katz is project manager in charge of laying the foundation for the new Brook Museum of Art in New Haven, Connecticut. Liya Brook, the benefactor and namesake of the museum, wants to have the work done within 41 weeks, but Sharon wants to quote a completion time that she is 90% confident of achieving. The contract specifies a penalty of $10,000 per week for each week the completion of the project extends beyond week 43.

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran14

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran15

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran16 Here’s an activity-on-arc diagram of the problem:

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran17 We start a spreadsheet model like this, calculating the mean and standard deviation using the PERT formulas:

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran18 Now we calculate shape and scale parameters:

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran19 A section to keep track of each node and when it occurs A section to keep track of each path through the network, to identify the critical path in each simulated project completion A section for simulating the times of the activities Model Overview

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran20

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran21

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran22 Example: Activity C

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran23 It’s important to be careful with the nodes that have multiple activities leading into them (in this model, Nodes 3 and 8). The times for those nodes must be the maximum ending time for the set of activities leading in. Nodes with only one preceding activity are easier (see Nodes 4 and 8 below).

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran24 Now we set up an area in the spreadsheet to track each of the paths through the network, to see which one is critical. This network happens to have six paths, so we set up a cell to add up all of the activity times for each of these paths:

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran25 Now, for each path, and for each activity, we can set up an IF statement to say whether the path (or activity) was critical for any particular realization of the model:

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran26 Here’s a cell to tell whether the project was completed by week 43: Here’s a cell to keep track of the penalty (if any) Sharon will have to pay. Note that we have assumed that the penalty applies continuously to any part of a week.

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran27 Crystal Ball For each of the random activities, we create an assumption cell, as shown here for Activity A:

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran28 Here’s the model after doing this for every random activity time (Activities D, F, I, L, M, and the Dummy activity have no variability):

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran29 Now we create forecast cells to track the completion time of the whole project (B30) as well as the criticalities of the various paths (H19:H24) and activities (N2:N15). We also make forecast cells to track whether the project took longer than 43 weeks, and what the penalty was.

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran30

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran31

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran32

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran33

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran34

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran35 Question 7: Compare the PERT results to those you would have found using (a) basic CPM using the most-likely times, (b) the “by-hand” PERT method from the textbook, and (c) HOM. CPM analysis gives a completion time of 42 weeks. The critical path is A-B-D-E-F-G-J-K-L-M

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran36 “Textbook” Method The textbook method involves (a) finding the means and standard deviations for each path, (b) determining which path has the longest expected total time, and (c) summing the variances of the activities on that path to get the variance of the path. In our case, the longest path would be A-B-D-E-F-G-J-K-L-M, with a mean of weeks and a variance of 2.92 weeks.

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran37

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran38

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran39

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran40

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran41

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran42 Marketing Example: New Product Development decision Cavanaugh Pharmaceutical Company (CPC) has enjoyed a monopoly on sales of its popular antibiotic product, Cyclinol, for several years. Unfortunately, the patent on Cyclinol is due to expire. CPC is considering whether to develop a new version of the product in anticipation that one of CPC’s competitors will enter the market with their own offering. The decision as to whether or not to develop the new antibiotic (tentatively called Minothol) depends on several assumptions about the behavior of customers and potential competitors. CPC would like to make the decision that is expected to maximize its profits over a ten-year period, assuming a 15% cost of capital.

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran43

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran44 Customer Demand Analysts estimate that the average annual demand over the next ten years will be normally distributed with a mean of 40 million doses and a standard deviation of 10 million doses, as shown below. This demand is believed to be independent of whether CPC introduces Minothol or whether Cyclinol/Minothol has a competitor.

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran45 CPC’s market share is expected to be 100% of demand, as long as there is no competition from AMI. In the event of competition, CPC will still enjoy a dominant market position because of its superior brand recognition. However, AMI is likely to price its product lower than CPC’s in an effort to gain market share. CPC’s best analysis indicates that its share of total sales, in the event of competition, will be a function of the price it chooses to charge per dose, as shown below. The Cyclinol product at $7.50 would only retain a 38.1% market share, whereas the Minothol product at $6.00 would have a 55.0% market share.

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran46 Questions What is the best decision for CPC, in terms of maximizing the expected value of its profits over then next ten years? What is the least risky decision, using the standard deviation of the ten-year profit as a measure of risk? What is the probability that introducing Minothol will turn out to be the best decision?

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran47 Income statement-like calculations for each of four scenarios 3 Forecasts: NPV in $millions for each decision Yes/No New Product Better U~(0, 1) (whether or not AMI enters market) N~(40, 10) (Total market demand)

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran48

© The McGraw-Hill Companies, Inc., 2004 Operations -- Prof. Juran49 Summary Advanced Simulation Applications Beta Distribution Operations –Project Management (PERT) “Textbook” method Crystal Ball Marketing –New Product Development decision