04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 1 GDE Status Barry Barish 4-Feb-07.

Slides:



Advertisements
Similar presentations
Nick Walker – GDE meeting Frascati Discussion and Approval of the BCD Nick Walker ILC-GDE Frascati –
Advertisements

Report from the GDE director Barry Barish Snowmass 14-Aug-05.
Industry and the ILC B Barish 16-Aug May-05ILC Consultations - Washington DC2 Why e + e - Collisions? elementary particles well-defined –energy,
6-Nov-06 FALC Resource Board Global Design Effort 1 Report from the GDE Barry Barish Caltech / GDE 6-Nov-06.
20-Nov-06 FALC - KEK Global Design Effort 1 GDE Report Barry Barish Caltech / GDE 20-Nov-06 RDR Design Freeze.
Baseline Configuration - Highlights Barry Barish ILCSC 9-Feb-06.
BDS GDE context LC-ABD2 : WP4 - Beam Line Design 12 th April 2007, LC-ABD Plenary, RHUL Deepa Angal-Kalinin ASTeC, The Cockcroft Institute.
13-Feb-06 RDR: Goals and Scope Barry Barish Fermilab RDR Meeting 13-Feb-06 ILC Design/Cost WBS.
The ILC Global Design Effort Barry Barish ILC Industrial Forum Japan 28-June-05.
11-Nov-06 ILCSC - Valencia Global Design Effort 1 GDE Report and Discussion of Costs Barry Barish Caltech / GDE 6-Nov-06.
6-7 April 06 MAC Review Global Design Effort 1 RDR Overview Organization, Schedule, Approach and Goals Barry Barish GDE Caltech.
GDE expectations from the SRF community Barry Barish Cornell SRF Mtg 15-July-05.
GDE Meeting B Barish 16-Aug-05 The GDE – who, what and how? The BCD – what is it? Internal Organization toward BCD What do we want out of Snowmass? How.
5 May 06 SLAC SPC 1 ILC Global Activities GDE, FALC Barry Barish GDE Caltech.
1-Dec-06 HEPAP Univ. Subpanel Global Design Effort 1 ILC Report Barry Barish Caltech / GDE 1-Dec-06 RDR Design Freeze.
The Path Toward a Linear Collider Barry Barish HEP 2005 Lisbon, Portugal 23-July-05.
14-Dec-06 RDR Internal Cost Review Global Design Effort 1 GDE Internal Review ILC Reference Design Costing Barry Barish Caltech / GDE 14-Dec-06.
7-Feb-07 GDE/ACFA Closing Beijing Global Design Effort 1 Summary of GDE Meeting and Future Actions Barry Barish 7-Feb-07.
Status of ILC Barry Barish Caltech / GDE 17-Aug-07.
Global Design Effort - CFS CLIC 09 Workshop - WG 5 Technical Systems 1 CLIC 09 WORKSHOP Working Group 5 - Technical Systems ILC REBASELINE ILC.
22-May-06 FALC - Rome Global Design Effort 1 Report on Progress of the GDE Barry Barish GDE.
Towards an International Linear Collider Barry Barish GDE 6-June-07.
Global Design Effort U.S. ILC Cost Translation R. Stanek, et al. Vic Kuchler 1/26/07.
Towards an International Linear Collider Barry Barish Caltech / GDE 25-July-07.
6-7 April 06 MAC Review Global Design Effort 1 BCD Overview Process and Highlights Barry Barish GDE Caltech.
Sendai, March 3, 2008 TILC08 · GDE Meeting Global Design Effort 1 TILC08 · GDE Meeting on International Linear Collider · Tohoku University Sendai · Japan.
RDR Report Writing Nan Phinney SLAC for RDR team of editors.
International Linear Collider The ILC is the worldwide consensus for the next major new facility. One year ago, the choice was made between the two alternate.
27-March-10 LCWS10 - Beijing Global Design Effort 1 Barry Barish LCWS10 - Beijing 27-March-10 “Cost Containment” for the TDR.
7-March-07 ILC-fest Fermilab Global Design Effort 1 International Linear Collider Barry Barish 7-March-07.
30-May-07 LCWS DESY Meeting Global Design Effort 1 A Vision of the Future RDR to ILC Barry Barish LCWS DESY 30-May-07.
8 May 06 ILCSC Report Global Design Effort 1 GDE R&D Program RDR Status and Plans Barry Barish GDE Caltech.
1-Feb-08 P5 Global Design Effort 1 GDE - ILC Barry Barish P5 Meeting - Fermilab 1-Feb-08.
RDR Report Writing Nan Phinney SLAC. 7/20/06 VLCW06 Global Design Effort 2 GLC Report Working model is the 2003 GLC Report ch 4-7
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
Date Event Global Design Effort 1 ILC UPDATE Vancouver to Valencia Ewan Paterson Personal Report to SiD Collaboration Oct 27, 2006.
Date Event Global Design Effort 1 ILC Engineering Design Phase - Status & Plans Mike Harrison GDE/BNL.
1 Global Design Effort TILC08 - WG1 Summary WG-1: Cost Reduction Studies J. Carwardine, T. Shidara, N. Walker (For WG-1 participants)
Global Design Effort 1 Possible Minimum Machine Studies of Central Region for 2009 Reference, ILC Minimum Machine Study Proposal V1, January 2009 ILC-EDMS.
24-Aug-11 ILCSC -Mumbai Global Design Effort 1 ILC: Future after 2012 preserving GDE assets post-TDR pre-construction program.
27 Nov 07 VM Workshop Global Design Effort 1 ILC – Superconducting Linear Collider Marc Ross, Project Manager GDE Fermilab.
6-10 Nov. 06 ILCWS Valencia Global Design Effort 1 RDR Management Board Overview K. Yokoya KEK.
Global Design Effort - CFS ILC Accelerator Design and Integration Meeting 1 ILC AD&I MEETING CONVENTIONAL FACILITIES AND SITING GROUP UPDATE V.
Brian Foster - Cosener's Forum May 06 1 The ILC - Status & Plans Introduction & latest developments The GDE The baseline design and R&D efforts The path.
BCD Status: Strengths and Weaknesses Tor Raubenheimer.
Report from ILCSC Shin-ichi Kurokawa ILCSC Chair LCWS06 at IISc Bangalore March 9, 2006.
Report from ILCSC Shin-ichi Kurokawa KEK ILCSC Chair GDE meeting at Frascati December 7, 2005.
1 ILC Internal Cost Review Major Points from External Reviewers T. Elioff, J. Marx, V. Soergel, M. Yoshioka, and A. Yamamoto, (C. Wyss, absent) To be presented.
The fourth Baseline Technical Review (BTR) - Conventional Facilities and Siting March 2012 All changes made to the CFS 2007 Reference Design during.
Nick Walker – SA meeting KEK Treaty Points and Costing Guidance Nick Walker 1 st System Area Managers Meeting KEK –
Status of the International Linear Collider and Importance of Industrialization B Barish Fermilab 21-Sept-05.
25-Sept-07 P5 Fermilab Global Design Effort 1 Report from GDE Barry Barish Caltech / GDE 25-Sept-07.
Introduction and Charge Barry Barish GDE Meeting Frascati 7-Dec-05.
23-April-13 ECFA LC2013 Global Design Effort 1 Barry Barish ECFA LC2013 DESY Hamburg, Germany 27-May-13 GDE The path to a TDR.
ILC Global Design Effort Barry Barish GDE 9-March-06.
28-Jan-08 SiD Workshop Global Design Effort 1 ILC Status Impacts of US/UK Budget Actions Replan for GDE Technical Design Phase Barry Barish SiD Workshop.
Tor Raubenheimer KEK Mtg Goals KEK January 19 th, 2006.
Goals of the ILC-Asia Meeting at Pohang Fumihiko Takasaki PAL, Feb. 17, 2006.
N. Walker, K. Yokoya LCWS ’11 Granada September TeV Upgrade Scenario: Straw man parameters.
M. Ross, N. Walker, A. Yamamoto th ATF2 Project Meeting Accelerator Design and Integration – New Baseline Proposal for ILC – ‘Strawman Baseline.
24-July-10 ICHEP-10 Paris Global Design Effort 1 Barry Barish Paris ICHEP 24-July-10 ILC Global Design Effort.
1 May 06 LCFOA - SLAC Global Design Effort 1 ILC Global Design Effort Barry Barish GDE Caltech.
ILC 2007 Global Design Effort 1 Planning Damping Rings Activities in the Engineering Design Phase Andy Wolski Cockcroft Institute/University of Liverpool.
Global Design Effort1 September 20-22, 2006 MAC Review Response to 1 st MAC Mtg Barry Barish GDE.
1-2 May 2006 LCFOA Mtg Global Design Effort 1 The Baseline Configuration and the Reference Design Report Tor Raubenheimer SLAC.
The ILC Outlook Barry Barish HEP 2005 Joint ECFA-EPS Lisbon, Portugal 23-July-05.
Main Linac Technology (MLT) Meeting To be held through WebEx July 13, 2007.
ILC - Upgrades Nick Walker – 100th meeting
ILC Global Design Effort
Barry Barish Paris ICHEP 24-July-10
Presentation transcript:

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 1 GDE Status Barry Barish 4-Feb-07

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 2 Confidentiality Issue No restrictions in the presentations at ACFA / GDE Beijing, but ….. RDR and Costing will not be officially released to public until presented to ICFA/ILCSC - Thursday –Joint meeting of ICFA/ILCSC followed by press release and press conference –Therefore, presentations at ACFA/ILCSC will be posted on Indico site, but only available by password until Thursday. –Password = dontaskmax Please defer communications outside and to the press until Thursday.

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 3 GDE Began at Snowmass Aug 05

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 4 The GDE Plan and Schedule Global Design EffortProject Baseline configuration Reference Design ILC R&D Program Technical Design Expression of Interest to Host International Mgmt LHC Physics CLIC

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 5 Snowmass to a Baseline AugustSeptemberOctoberNovemberDecember 2005 Snowmass WW/GG summaries Response to list of 40+ decisions All documented ‘recommendations available on ILC Website (request community feedback) Review by BCD EC BCD EC publishes ‘strawman’ BCD Public Review Frascati GDE meeting BCD Executive Committee: Barish Dugan, Foster, Takasaki Raubenheimer, Yokoya, Walker

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 6 Baseline Configuration -- Dec 2006 ~31 km Documented in Baseline Configuration Document not to scale 1 st Milestone - ILC Baseline

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 7 Baseline to a RDR Jan JulyDec 2006 Freeze Configuration Organize for RDR Bangalore Review Design/Cost Methodology Review Initial Design / Cost Review Final Design / Cost RDR Document Design and CostingPreliminary RDR Released FrascatiVancouverValencia

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 8 ICFA FALC Resource Board ILCSC GDE Directorate GDE Executive Committee Global R&D Program RDR Design Matrix GDE R & D Board GDE Change Control Board GDE Design Cost Board GDE -- RDR Organization

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 9 RDR Management Board To carry out the RDR, we found we needed a stronger direct management. We created the RDR Management Group –Director –Executive Committee –Cost Engineers –Integration Scientist Met weekly to coordinate, review and guide the process and direct the writing the RDR (with RDR editors) Chair: Nick Walker “two fisted Nick”“two-fisted Nick”

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 10 ILCSC Parameters Report E cm adjustable from 200 – 500 GeV Luminosity  ∫ Ldt = 500 fb -1 in 4 years Ability to scan between 200 and 500 GeV Energy stability and precision below 0.1% Electron polarization of at least 80% The machine must be upgradeable to 1 TeV This report has served as our “requirements” document This group was reconvened to update and clarify Reconvened in Sept 06 and reported in Valencia Nov 06

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 11 Parameters Report Revisited The ILCSC Parameters Group has given updated selected clarification on accelerator requirements, based on achieving ILC science goals: –Removing safety margins in the energy reach is acceptable but should be recoverable without extra construction. The max luminosity is not needed at the top energy (500 GeV), however ….. –The interaction region (IR) should allow for two experiments ….. the two experiments could share a common IR, provided that the detector changeover can be accomplished in approximately 1 week.

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 12 RDR Cost Estimating “Value” Costing System: International costing for International Project –Provides basic agreed to “value” costs –Provides estimate of “explicit” labor (man-hr)] Based on a call for world-wide tender: lowest reasonable price for required quality Classes of items in cost estimate: –Site-Specific: separate estimate for each sample site –Conventional: global capability (single world est.) –High Tech: cavities, cryomodules (regional estimates)

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 13 Vancouver Cost Data

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 14 Technical Systems Vacuum systems Magnet systems Cryomodule Cavity Package RF Power Instrumentation Dumps and Collimators Accelerator Physics Global Systems Commissioning, Operations & Reliability Control System Cryogenics CF&S Installation Area Systems e- e+ damping RTML main BDS source source rings linac Cost Roll-ups

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 15 Area RDR MBCCRCCB approx.  $ BDS 2  14mr IRs supported14YES~170 M$ Single IR with push-pull detectorsupported23YES~200 M$ Removal of 2nd muon wallsupported16YES~40 M$ MLRemoval of service tunnelrejected ~150 M$ RF unit modifications (24 ® 26 cav/klys)supported 20YES ~50 M$ Reduced static cryo overheadsupported ~150 M$ Removal linac RF overheadsupported ~20 M$ Adoption of Marx modulator (alternate)rejected ~180 M$ RTMLSingle-stage bunch compressorrejected ~80 M$ Miscellaneous cost reduction modificationssupported19YES~150 M$ SourcesConventional e+ sourcerejected <100M$ Single e+ targetsupportedin prep ~30 M$ e- source common pre-acceleratorsupported22YES~50 M$ DRSingle e+ ringsupported15YES~160 M$ Reduced RF in DR (6 ® 9mm  z ) supportedin prep ~40 M$ DR consolidated lattice (CFS)supportedin prep ~50 M$ GeneralCentral injector complexsupported18(19) YES ~180 M$ Cost-Driven Design Changes

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 16 Evolving Design  Cost Reductions Some possible cost reductions (e.g. single tunnel, half RF, value engineering) deferred to the engineering phase July 2006

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 17 RDR Design & “Value” Costs Summary RDR “Value” Costs Total Value Cost (FY07) $4.87B Shared + $1.78B Site Specific K person-years (“explicit” labor = 22.2 M person- 1,700 hrs/yr) The reference design was “frozen” as of 1-Dec-06 for the purpose of producing the RDR, including costs. It is important to recognize this is a snapshot and the design will continue to evolve, due to results of the R&D, accelerator studies and value engineering The value costs have already been reviewed twice 3 day “internal review” in Dec ILCSC MAC review in Jan

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 18 ILC Value – by Area Systems Conventional Facilities Components Main Cost Driver

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 19 ILC Value –Global & Technical Systems Installation counted mostly as explicit labor Main Cost Driver

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 20 Explicit Manpower 13 K person-yrs = 22 M person-hrs * “management” includes overhead

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 21 Value Funding Profile We are not using integrated cost/schedule tools yet; but it appears feasible to develop a realistic funding profile % of Total Value per Year

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 22 How Good is our Cost Estimate? Methodology (value costing) is a practical way of developing agreed to “international” costing. –Strength: Good scheme for evaluating value of work packages to divide the project internationally –Weakness: Difficult to sort out real regional difference from differences due to different specifications, etc We have spent ½ year, developing methodology, good WBS dictionary, technical requirements and costing data requested. We spent another ½ year doing cost vetting and cost / performance optimization. VERY COMPLETE COST ANALYSIS FOR THIS STAGE IN THE DESIGN

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 23 Sanity Checks The difference is primarily in conventional facilities Comparison with TESLA costs

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 24 –Three RF/cable penetrations every rf unit –Safety crossovers every 500 m –34 kV power distribution Main Linac Double Tunnel

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 25 Cost Driver – Conventional Facilities 72.5 km tunnels ~ meters underground 13 major shafts > 9 meter diameter 443 K cu. m. underground excavation: caverns, alcoves, halls 92 surface “buildings”, 52.7 K sq. meters = 567 K sq-ft total

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 26 Design based on two 4.5m tunnels –Active components in service tunnel for access –Includes return lines for BC and sources –Sized to allow for passage during installation –Personnel cross-over every 500 meters Main Linac Tunnels

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 27 Conventional Facilities shared site-specific FY06 $ illustrative only ASIATOTAL COST=$2,247,562CIVIL ONLY=$1,377,765 Yen to US $ AMERICATOTAL COST=$2,540,439CIVIL ONLY=$1,648,052 Euro to US $1.2 EUROPETOTAL COST=$2,493,066CIVIL ONLY=$1,608,407 Euro to Yen140 US to Yen116.7 Regional Comparisons : Quote 2007$ – Escalate 2006$ by 10.6% U.S (Turner); 2-3 % other regions shared site-specific FY06 $ illustrative only

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 28 How Good is our Cost Estimate? Cost Estimate is ~ 30% level over the RDR concept. However, there are some important limitations: –The estimate is for a concept or reference design, not an engineering design. –The design will evolve, giving concerns of future cost growth. We believe this can be compensated for by deferred potential gains from value engineering –Major Cost Drivers: Conventional facilities need actual site(s) for better estimates (e.g. safety, one tunnel, shallow sites, etc) –Major Cost Drivers: Main Linac limited because of proprietary information, regional differences, gradient, uncertainties regarding quantity discounts, etc Risk analysis will be undertaken following this meeting

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 29 Cost Driver - The Main Linac Costs have been estimated regionally and can be compared. –Understanding differences require detail comparisons – industrial experience, differences in design or technical specifications, labor rates, assumptions regarding quantity discounts, etc.

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 30 Balance between cost per unit length of linac, the available technology, and the cryogenic costs Optimum is fairly flat and depends on details of technology Current cavities have optimum around 25 MV/m Gradient MV/m Relative Linac Costs (from USTOS estimate) Cavity type Qualified gradient MV/m Operational gradient MV/m Length Km Energy GeV initialTESLA upgradeLL Main Linac Gradient Choice

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 31 Cost Impact of Lower Gradient We have given high priority to S0 Cavity R&D program to demonstrate baseline 31.5 MV/m Cost impact of running the ILC linacs with a range of gradients (22-34 MV/m with an average of 28 MV/m) – assumes the power to the cavities is adjustable (one time only) – The Main Linac cost increases by 11.1% and the ILC cost increases by 6.7% assuming Main Linacs are 60% of the ILC cost. From Chris Adolphsen

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 32 4 th generation prototype ILC cryomodule Cryomodule Value Estimates TESLA cryomodule

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 33 American vs European Estimate Cold mass & vac. vessel

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 34 Cost of High Level RF by Region Note: RF Dist’n no’s from Asia & Europe scaled for CC# model Some components have no Mfg base in Asia

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 35 –11km SC linacs operating at 31.5 MV/m for 500 GeV –Centralized injector Circular damping rings for electrons and positrons Undulator-based positron source –Single IR with 14 mrad crossing angle –Dual tunnel configuration for safety and availability 2 nd Milestone – ILC Reference Design

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 36 How Good is the RDR Concept? The design has been carried out by Area Systems that have been built up into an overall design. –We have advanced in integrating that design and even in being able to evaluate proposed changes that cross several area systems (e.g. central injector – E Paterson) –A more integrated design approach is envisioned for the engineering design stage. Technical system designs still immature, resulting in lack of detailed specifications, requirements and value engineering has been deferred

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 37 Design Parameters

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 38 ILC is has about 10x the number of operating units compared to previous accelerators with similar availabilty goal (~ 85%) This will require significant improvements in: –Failure rates on component and sub-systems - magnets, PS, kickers, etc –Redundancy – power, particle sources, etc –Access for maintenance and servicing – double tunnel concept The availability issue will need much attention during engineering design phase. Design Challenges - Availability

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 39 6km Requires Fast Kicker 5 nsec rise and 30 nsec fall time The damping rings have more accelerator physics than the rest of the collider Design Challenges – Damping Rings

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 40 Electron Cloud in Damping Rings Electron cloud buildup in an arc bend of the 6.7 km ring and suppression effect of clearing electrodes biased at the indicated voltages. Simulations show ~ 100 V is sufficient to suppress the average (and central) cloud density by two orders of magnitude. NEEDS EXPERIMENTAL DEMONSTRATION 0 V 10 V 100 V

04-Feb-07 GDE/ACFA Intro Beijing Global Design Effort 41 Summary & Final Remarks We are releasing a “draft” Reference Design Report to ICFA/ILCSC on Thursday –The reference design presents a complete (but not engineered design) that can achieve the physics design parameters with acceptable risk. –Vetted and cost / performance optimized “value costing” has been obtained yielding the scope of the project, identified areas needing R&D, industrial study and value engineering. The Reference Design will provide an excellent basis and guidance for the undertaking an Engineering Design to bring us to construction readiness In Beijing, we will thoroughly expose the Reference Design, emphasize the R&D program, discuss plans for carrying out the Engineering Design to get to readiness for construction