Initial Thoughts on the Release of Non Obligated NTS System Entry Capacity Transmission Workstream 3 rd April 2008.

Slides:



Advertisements
Similar presentations
UK Gas Entry Regime – Review of existing Interruptible Arrangements & Potential Reforms for this Winter.
Advertisements

Review of NTS entry charge setting arrangements - IA 1 July 2010.
Funding UKLink Process changes (User Pays). 2 Purpose of Presentation  Review of User Pays  Principles  Application to date  National Grid NTS observations.
Commercial Arrangements For Gas Quality Service – Process UNC Transmission Workstream 23 rd April 2007.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Long Term Entry Capacity & User Commitment Transmission Workstream 7 th August 2008.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Exit Reform Review Transmission Workstream 07 January 2010.
Moving the QSEC and AMSEC Auctions National Grid NTS, Transmission Workstream.
The Treatment of “Spare / Sterilised” Capacity – follow up Draft for discussion purposes only.
Capacity trade and transfer mechanism and the next AMSEC auction Nienke Hendriks Head of Gas Transmission Policy, Enforcement and Compliance 9 May 2007.
GRI NW Investment Workshop Chris Logue, European Policy Manager, 4 th June 2010 The Hague.
Transfer & Trades Special Transmission Workstream
Review Group 291 – Balancing Arrangements Default Cashout Workshop 3 – 21 st June 2010.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Transfers and Trades Transmission Workstream
Mod 0333: Update of default System Marginal Prices Review Group August 2010 Transmission Workstream 07/10/2010.
Discretionary Release of Non Obligated NTS System Entry Capacity Transmission Workstream 1st May 2008.
Overview Gemini 2008 Release (Summer). Gemini Release 2008 (Summer) In response to a request from National Grid Transmission a number of changes have.
Assignment of NTS Entry Capacity Transmission Workstream 06 November 2008.
Delivering Connections and Capacity RIIO-T1 and associated commercial changes - Summary June 7th 2012.
Review Group Modification Proposal Introduction of Enduring NTS Exit Capacity Arrangements.
Review Group 221 Session 3: 13 October Introduction  During this presentation we will seek views on the following questions.  What should the.
Update on Entry Capacity Substitution Transmission Workstream 6 th March 2008 Summary of consultation responses.
Force Majeure - Capacity Transmission Workstream 2 July 2009.
Exit Capacity Substitution and Revision Transmission Workstream meeting, 3 rd December 2009.
Open letter on Development of the regime ahead of winter 2007/8 Nienke Hendriks Head of Gas Transmission Policy, Enforcement and Compliance 28 June 2007.
Review of Entry Capacity and the Appropriate Allocation of Financial Risk Review Group th Sept 2008.
Optimisation of Entry Capacity Strawman Transmission Workstream 4 th May 2006.
Entry Capacity Substitution Workshop 3 11 th June 2008 Substitution Example.
Implementation of Trades and Transfers National Grid NTS 5 th June 2008.
Assignment of NTS Entry Capacity Transmission Workstream 02 July 2009.
Entry Capacity Trading Transmission Work Stream, 5 April 2007.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
September 2008 QSEC auction - Allocations Transmission Workstream
Fundamental review of entry charging principles UNC Transmission Workstream - 6 th August 2009.
Transmission workstream 6 April Overview of TPCR Third Consultation UNC transmission workstream – 6 April Mark Feather.
Entry Capacity Substitution Workshop 4 9 th July 2008 Entry Capacity Substitution Methodology Statement: Discussion Paper.
Exit Capacity Release Methodology Statement - ExCR Transmission Workstream – 5 th March 2009.
Facilitating Release of Non-obligated Entry Capacity Draft – for discussion purposes only 22 November 2007.
Assignment of NTS Entry Capacity – Questions relating to High level Business Rules Assignment Workstream, 7th April 2009.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Review Group -140 Thoughts on additional information requirements.
DRSEC Update Transmission Workstream 06 November 2008.
Trades and Transfers Workshop, 6 th November 2007.
Exit Capacity Release Methodology Statement - ExCR Transmission Workstream – 5 th Feb 2009.
Mod Entry Capacity Transfers Transmission Work Stream, 5 April 2007.
Assignment of NTS Entry Capacity Review Group 221, 10th December 2008.
Transfers and Trades Special Transmission Workstream
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Modification Proposal 0435: Arrangements to better secure firm gas supplies for GB customers Initial Workgroup discussion 1 November 2012.
Development Modification Proposal: Introduction of an Inter-day Linepack Product Review Group August 2010 Transmission Workstream 07/10/2010.
Transmission Workstream, 01 October 2009
Transmission Workstream, 2nd March 06
Capacity Methodology Statements: Impact of Mod 452
Exit Overruns in the Enduring Regime - draft MOD principles
NTS Entry Charging Review Update
PARCA Security and Termination Amounts
Exit Capacity Substitution and Revision
Transmission Workgroup June 7th 2012
Transmission Workgroup 6th March 2014
Long Term Non Firm Capacity Update
Transmission Workstream – Partial Assignment
Entry Capacity Transfer and Trade
Entry Overrun Calculation
Richard Fairholme E.ON UK
Optimisation of Entry Capacity Modification Proposal
Assignment of NTS Entry Capacity – Previous Work Undertaken
Entry Capacity Transfers - Constrained Period
Presentation transcript:

Initial Thoughts on the Release of Non Obligated NTS System Entry Capacity Transmission Workstream 3 rd April 2008

Background (1)  Concept of releasing strips of Non Obligated NTS System Entry Capacity first raised November  Discussions with the Industry reached consensus to postpone until such time as could be considered in more depth.  National Grid NTS have now been asked to revisit and bring ideas forward to April 08 Transmission Workstream with a view to introduce a new product in time for Winter 08/09.  The timeframes involved rule out the introduction of new system functionality, any solution will be based on manual processes utilising existing functionality where possible.  In light of timeframes available we are providing 3 options to form the basis of the discussion.

Background (2)  Some Shippers want monthly blocks released ahead of the winter.  Some Shippers want sub monthly released close to the time of usage.  Both groups would like Firm System Entry Capacity or as a minimum an incentive on National Grid NTS to not interrupt the capacity i.e. some degree of buy-back.  The above products are very different in terms of the complexity involved in developing them through to implementation.

Background (3)  To satisfy either product request National Grid NTS believe a mechanism to release non-obligated system entry capacity outside of the existing auction processes is needed.  National Grid NTS have chosen to focus on the longer term product as:  National Grid NTS have seen a clear demand for the product;  Ability to potentially implement ahead of this winter;  National Grid NTS believe that due to a number of new investments it may be possible to release additional non-obligated capacity this year.  We have put together 3 initial options for discussion at April 08 Transmission Workstream.

Option A – Ad-hoc Release of Non Obligated System Entry Capacity  Ad-hoc Auction Process - National Grid NTS creates new auction to release Firm System Entry Capacity ahead of the winter.  Sold in 1m blocks, more than one month in advance and less than a year ahead.  Quantity made available to be based on a risk assessment at those ASEPs where there was unsatisfied demand at the AMSEC auction.  May require less complex enabling UNC modification.  Potentially minimal system intervention required (expected to be held off-line).  Will be taken into account in the calculation of Trade and Transfer exchange rates (once the capacity has been sold it becomes Obligated Firm System Entry Capacity).  Price paid for the capacity to be equal to or greater than the corresponding MSEC Reserve Price – otherwise there may be significant charging implications.

Option B - Ad-hoc Release of Non-Obligated System Entry Capacity with Buy-Back  Ad-hoc Auction Process.  Sold in 1m blocks, more than one month in advance and less than a year ahead.  May require less complex enabling UNC modification.  Potentially minimal system intervention required (expected to be held off-line).  Associated buy-back e.g. 1 day of capacity to have 1 day of corresponding buy-back.  Not taken account of in calculation of Trade and Transfer exchange rates.  Price paid for the capacity to be equal to or greater than the corresponding MSEC Reserve Price – otherwise there may be significant charging implications.

Option C - Scheduled Release of Non-obligated System Entry Capacity with Buy-Back  Ongoing Auction Process.  System Entry Capacity Released twice per annum [August & March].  Sold in 1m blocks.  Would require detailed UNC modification proposal.  Associated System Entry Capacity Buy-Back e.g. 1 day of capacity to have 1 day of corresponding Buy-Back.  Not taken account of in calculation of Trade and Transfer exchange rates.  Price paid for System Entry Capacity to be equal to or greater than the corresponding MSEC Reserve Price – otherwise significant charging implications.

General Issues  There are a number of issues that will need to be resolved:  Can any of the options be achieved for this year (08/09)?  Do these options have any real value thereafter 2009+?  How would auction interact with Trade and Transfer.  System Requirements  Unable to incorporate into Gemini release pre winter 08/09  How would ad-hoc processes be initiated?  Criteria for determining which ASEPs would participate in these auctions.  What quantities should be released as part of a scheduled or ad hoc release?

Specific issues for System Entry Capacity with associated Buy-Back (1)  Product Classification  Neither Firm nor Interruptible System Entry Capacity  Will need to be included in the SMPS  Assumption being that any associated Buy-Back would be utilised after Interruptible Capacity had been scaled  Revenues/Costs  Impact upon National Grid NTS Entry Capacity Buy-Back incentive  Impact upon existing mechanisms  Use It Or Lose It  Discretionary Interruptible  Overrun Price  Neutrality

Specific issues for System Entry Capacity with associated Buy-Back (2)  Accrued Rights;  Can Capacity be traded?  May undermine the development of the Secondary Market;  Need to assess charging implications;  How would Shippers value the System Entry Capacity as the Trade and Transfer process will move “Firm” System Entry Capacity over and above this release of capacity.

Summary AdvantagesDisadvantages Option A  Potential for additional revenue to be passed to Shippers  Less complex to implement i.e. minimal system set up costs  Firm Product  Will impact upon the Trade and Transfer process  Potentially less Entry Capacity available than in options B and C Option B  Potential for additional revenue to be passed to Shippers  Impact upon Trade and Transfer process is minimised  Increased Entry Capacity may be made available  Not linked to Trade and Transfer process, increased likelihood of Buy-Back being called  Significantly more complex than Option A, as it is a new product Option C  Potential for additional revenue to be passed to Shippers  Impact upon Trade and Transfer process is minimised  Increased Entry Capacity may be made available  More formal and codified process  Not linked to Trade and Transfer process, increased likelihood of Buy-Back being called  More complex than Option B  Embeds an additional process into an already congested schedule  Systems need to be developed to support on-going process

Way Forward  Request Industry view on all 3 options  Views on any alternative approaches