Nominal intensity bunches ● First ramp with nominal intensity bunches suffered from an instability appearing around 1.8 TeV. ● Nominal intensity bunches.

Slides:



Advertisements
Similar presentations
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Advertisements

LHC progress Saturday 2 nd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
LHC progress Thursday 30 th April 2015 Coordination: Mike Lamont, Wolfgang Hofle.
Friday, h10: Stable beams at 1.38 TeV. 09h03: Beam dump.  One bunch dropped too much in intensity and gave BPMS interlock (dump protection). 10h36:
RF de-bunching problem  The Beam Phase module measures the phase of each individual bunch and makes an average that is passed to the Low Level for updating.
Weekly summary Summary Week /19.07 M. Lamont & J. Wenninger for the OP team and for all colleagues from the various groups 8:30 meeting 1.
First measurements of longitudinal impedance and single-bunch effects in LHC E. Shaposhnikova for BE/RF Thanks: P. Baudrenghien, A. Butterworth, T. Bohl,
Monday 29 October 08:48 V/dM scan CMS end of fill #3236. Check of “fast scan”. 10:06 V/dM scan finished, start of RF studies, reducing RF voltage. 11:10.
● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
Monday h00: End of fill #1640: 3.7 pb h14: RB S12 and S23 tripped before loading rampdown table, active filter. MPE piquet. Fip_Com_Lost.
LHC progress Report LHCC Wednesday 23 rd March 2011.
LHC Status Mo Morning 20-June Bernhard Holzer, Gianluigi Arduini et al 7 runs The Week.
Elias Métral, LHC Beam Commissioning Working Group meeting, 08/06/2010 /191 SINGLE-BUNCH INSTABILITY STUDIES IN THE LHC AT 3.5 TeV/c Elias Métral, N. Mounet.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
LHC Progress Thursday 29 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
Monday :00 Injection for physics fill # :00 Stable beams fill #1816, luminosity ~1.2x1033 cm-2s-1 11:08 Beams dumped. QPS trigger on detector.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
Shortened program (2 days), as decided in LMC. MD program worked very well  all MD’s on plan with ~foreseen beam time. LHC in very good shape with excellent.
Monday 12 th November 04:50 Beam dump, trip of RF line 4B, integrated L ~120 pb-1. Access for RF. 07:00 Injecting. FBCT phasing. Line steering. 09:59 Beam.
From yesterday LHC status Wednesday 26 th Welcome Verena back on shift 07:08 Access in PM85 for piquet EPC (O.Fournier).  Fuse on RD2.R8 circuit.
LHC progress Sunday 3rd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
:00 meetingEBH 11 Saturday :00 meetingEBH 2  7:58 Fill 2483 (264 bunches) dumped by reference orbit set to zero in.
Saturday 11.9 ● From Friday – Minimum required crossing angle is 100  rad in 2010 – Plenty of aperture at triplets: > 13  (n1 > 10) – Can stay with 170.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Thursday 20 th April 01:53 RCBV17.R7B2 tripped as happened few days ago: SIS intercepted. 05:54 Stable beams, 1380b, still RF problems B1, abort gap cleaning.
Injection issues overnight 10:50 Access  QPS & EPC  Vacuum leak SPS – magnet to be replaced Monday – cycling for FT and LHC only over the weekend 12:15.
RHIC Status Haixin Huang RSC Meeting 02/18/2011. l Fixed the blue dump kicker noise problem last Friday. l Declared physics last Friday. l Smooth run.
07:00 Dump fil #2219, 123 pb -1 delivered. Trim TDI parking position to +/- 55 mm in the collimator BP trimmed the temperature kicker limit to 62 degrees.
Summary of ions measurements in 2015 and priorities for 2016 studies E. Shaposhnikova 3/02/2016 Based on input from H. Bartosik, T. Bohl, B. Goddard, V.
Wednesday 8.9 External crossing angles:
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Monday :00 Stable beams 9_6_6_6 13:40 Access.
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
Summary of Week 11: 14 – 21 March
LHC Status Su Morning 17-April R. Assmann, B. Holzer et al
Wednesday Morning 8: :30 end of fill study - octupole polarity inversion (Elias, Tatiana, Alexey, Georges, …): Goal: study the effect of the.
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
LHC commissioning Week 38
Summary of Week 16 G. Arduini, J. Wenninger
Lost at 12:05 to power converter (RTQX2.R1) problem
Wed :40 Lost S78 - QPS controller.
Week 35 – Technical Stop and Restart
Monday Morning – recovery from cryo.
Tuesday Loss maps in the night:
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Friday morning 10:30 Optics measurements and corrections.
Thursday :00: Physics fill from the night shift
Wednesday 03/11 – The Plan Finish electron-cloud program:
Saturday 7th May Sat – Sun night
(on behalf of the LHC team)
Summary Thursday h21: Stable beams fill #1303.
Thursday morning 7:20 – 12:30 faults of BLM sanity check, RQX.L8 QPS trip and iris scanner in UJ47. Access: Pt 8 for ELQA on RQX.L8 (The voltage.
Aims for the week Recover from technical stop and precycle at 10A/s
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
MD#2 News & Plan Tue – Wed (19. – 20.6.)
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
Sat morning Until 12:40: Loss maps at injection
Monday :00 – 15:00 : Stable beams 15:30 : Recover…
Summary Tuesday h23: Machine closed. Precycle started.
Wednesday 23/2 Thanks CRYO!!!.
Fri :52 Stable beams fill #2536
Wednesday h18: 228b fill lost just before start of ramp.
Another Immortal Fill….
Tuesday 6th April 8:00 Injection studies 16:00 RF studies
Saturday 15th May One bunch 1 e11 per beam 09:57: start ramp
Wednesday :35 : Beam lost because of trip of RCBXH3.L1
Saturday Morning used to complete the loss maps and asynch dumps (with RPs). All loss maps OK (B. Salvachua), but the off-p cleaning for B1 (Lead) was.
Wednesday Following the struggle with the vacuum in IR2 over the night, drop intensity to 1.2E11/bunch. Fill first B1 – pretty quiet – then B2 – quite.
Presentation transcript:

Nominal intensity bunches ● First ramp with nominal intensity bunches suffered from an instability appearing around 1.8 TeV. ● Nominal intensity bunches suffer (most likely) from head-tail instability. ● Cures / improvements: – Operate at lower Q’ (< 5). – Octupoles – Larger (closer to nominal) longitudinal emittance 8:30 meeting 1

Ramp 1e11 8:30 meeting 2 ● Ramp with larger longitudinal emittance (and octupoles), obtained by opening phase loop in the LHC for some time: 0.7 eVs instead of 0.3 eVs.

Bunch length in ramp 8:30 meeting 3 Over the previous week-end : 0.6 ns at 3.5 TeV ● With the longer bunches, the strength of the octupoles could be reduced to ~ 5-10% of the previous settings (20 A instead of 200 A) – the previous setting was ‘guessed’.

Beam becoming unstable… 8:30 meeting 4

‘Dancing’ bunches at 3.5 TeV 8:30 meeting 5 Another ramp: beam unstable at 3.5 TeV, with length < 0.8 ns

Nominal intensity bunches issues ● Beam can be stabilized with octupoles. ● Larger longitudinal emittance is very beneficial. – Increased in a controlled way in the SPS (up to ~ 0.8 eVs). – In the LHC increase by opening phase loop. ● Issues of uncaptured beam / beam in abort gap with larger longitudinal emittance / phase loop opening. – To be followed up… ● So far, even when the beam was stable at 3.5 TeV, the emittances were huge: 8 to 10 um ! – Very strong blow-up in the ramp. 8:30 meeting 6

Transverse Damper ● Used successfully on B2 V plane. – Also in ramp. ● To be continued and extended to other beam/planes. 8:30 meeting 7 Damper OFF (red) and ON (green) at 3.5 TeV

● The orbit FB had been introduced successfully for the ramp in the previous week. ● Monday-Tuesday COD trip ‘storms’ were observed: suddenly CODs trip together. Sometimes the beam survives, sometimes it doesn’t (into the collimators and then BLM dump). ● The trips could be tracked to sudden jumps in the real-time correction reference. Combination of: – Jumps in the corrections from the OFB. – Regulation issue of the CODs when running at ‘low’ current since all CODs were affected by the jumps, but only a few tripped. ● The reference jumps could be traced to incorrect energy information arriving at the OFB (via BI FE computers). – Information of energy arrives with the tune data. The orbit feedback saga 8 8:30 meeting

● A fix was introduced on Wednesday and ‘tested’ on Wednesday. ● Another ramp was lost Friday night on the same symptoms: – It turned out that the fix had not been deployed. ● Another iteration was made Saturday evening with a new fix: – We survived an event with incorrect energy. – But the FB entered into a strange state from which it could not recover and that affected also Q and Q’. >> decided to continue operation without OFB until a better fix is received (from Kyoto…). ● Orbit in the ramp (and squeeze) cleaned and stable over the weekend. – Peak rms excursions 0.3 mm OK ! The orbit feedback fixes… 9 8:30 meeting

● With OFB the orbit is dancing around in the ramp – amplitudes of few 10’s of microns (not a severe issue!). – Clearly visible on BSRT. ● The period is 200 ms, which does not really match the FB periods (25 Hz). – Could be an interference due to COD PCs operated with RST period of 200 ms? To be verified… – Some CODs (MCBY…) send back status info indicating that they are rate- limited during the ramp when the OFB is active. Dancing orbit 10 8:30 meeting

As seen by ADT 8:30 meeting 11

Cryo stop ● Cryo de-icing in S45 done. ● Various issues fixed in the 1 day stop. ● S67 was successfully commissioned with ramp rates up to 10 A/s and 6 kA. 8:30 meeting 12

Injection oscillations 8:30 meeting 13 Injection oscillations of the 5 last bunches with respect to the first bunch in bucket 1. ● Un-explained difference in V injection oscillations between bucket 1 and the other buckets (> 2000). -Leads to emittance blow-up. -We are now adjusting inj. oscillations on bucket 2001.

13 bunches ● Finally pushed the number of bunches to 13 on Monday. – Smooth, but injection is really lengthy… – Tightened orbit and corrector interlocks. ● Reaches luminosities of 1.5E29 in the first fill, 2E29 overnight. – Orbit in stable beams cleaned up for first fill. – First fill lost due to problem in BLM system (followed by another problem in another IR a bit later). – Losses and low lifetimes were observed in the second fill. We are learning… ● Second fill had very good emittances. – From fill to fill the emittance variations in V plane can be large and are not really explained. 8:30 meeting 14

2E29 !! 8:30 meeting 15