PERT/Activity Diagrams, Completion Probability and the Z Score

Slides:



Advertisements
Similar presentations
Chapter 9: Probabilistic Scheduling Models
Advertisements

Chapter 6 Scheduling. 222 Learning Objectives Estimate the duration for each activity Establish the estimated start time and required completion time.
Chapter 7 Project Management
Project Management - Part 2
1 1 Slide © 2001 South-Western College Publishing/Thomson Learning Anderson Sweeney Williams Anderson Sweeney Williams Slides Prepared by JOHN LOUCKS QUANTITATIVE.
Operations Management Session 27: Project Management.
Terminology Project: Combination of activities that have to be carried out in a certain order Activity: Anything that uses up time and resources CPM: „Critical.
Scheduling the Project
1 Topics to cover in 2 nd part ( to p2). 2 Chapter 8 - Project Management Chapter Topics ( to p3)
1 1 Slide © 2004 Thomson/South-Western Chapter 12 Project Scheduling: PERT/CPM n Project Scheduling with Known Activity Times n Project Scheduling with.
Sampling: Final and Initial Sample Size Determination
Example: Frank’s Fine Floats
Project Scheduling: Networks, Duration Estimation, and Critical Path
Other Scheduling Methods Dr. Ayham Jaaron Chapter 11.
CHAPTER 4 MANAGING PROJECT PROCESSES. THE CONCEPT A project is an interrelated set of activities that has a definite starting and ending point and that.
In the name of Allah the Most Gracious the Most Merciful.
McGraw-Hill/Irwin © 2006 The McGraw-Hill Companies, Inc., All Rights Reserved. 1 Chapter 3 part 2 Project Management.
LINE DIAGRAMS Learning objectives After this lecture you will be able to: Prepare and use line diagrams Demonstrate the effect that making activities ‘continuous’
Assuming normally distributed data! Naïve Bayes Classifier.
EMGT 501 HW # Due Day: Sep 27.
SEEM 3530 Program Evaluation and Review Technique
Chapter 7 Probability and Samples: The Distribution of Sample Means
Chapter 11: Random Sampling and Sampling Distributions
MATHEMATICS 3 Operational Analysis Štefan Berežný Applied informatics Košice
Prosjektstyring bma ACTIVITY A B C D E A 4 / 5 / 6 B 8 / 10 / 13 C 9 / 12 / 16 D 7.
Project Time Management J. S. Chou, P.E., Ph.D.. 2 Activity Sequencing  Involves reviewing activities and determining dependencies.  A dependency or.
Dr. Godfried Williams1 Project Management – Topic 6 Lecture Content Planning Tools/Techniques Optimization Techniques Resource Planning & Allocation Linear.
Project Time Management J. S. Chou, P.E., Ph.D.. 2 Activity Sequencing  Involves reviewing activities and determining dependencies.  A dependency or.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Real-World Project Management Chapter 13. Characteristics of Project Management Unique one-time focus –Difficulties arise from originality Subject to.
Single Sample Inferences
PERT Program Evaluation and Review Technique Tong Wang 511D ERB.
Chapter 7 PERT Project Management for Business, Engineering, and Technology.
Q N U Schedule Risk Management By Ursula Kuehn, PMP, EVP UQN and Associates.
1 3. M ODELING U NCERTAINTY IN C ONSTRUCTION Objective: To develop an understanding of the impact of uncertainty on the performance of a project, and to.
3 common measures of dispersion or variability Range Range Variance Variance Standard Deviation Standard Deviation.
§ 5.3 Normal Distributions: Finding Values. Probability and Normal Distributions If a random variable, x, is normally distributed, you can find the probability.
3 - 1 Course Title: Production and Operations Management Course Code: MGT 362 Course Book: Operations Management 10 th Edition. By Jay Heizer & Barry Render.
Change management control Sources of Change  Project scope changes  Implementation of contingency plans  Improvement changes ISE Ch. 6 1.
CPM – Critical Path Method Can normal task times be reduced? Is there an increase in direct costs? Additional manpower Additional machines Overtime, etc…
Chapter 7 : Risk Management – part 2
Project Crashing. c=6 e=9 b=6 a=7 f=8 g=5 d=4 Given the information below, what is the total additional cost to crash the project as much as possible?
Project Management Concepts Gantt Chart – shows tasks as bars whose length indicates timing. PERT* chart (Network Diagram) – shows relationships between.
TK3333 Software Management Topic 6: Scheduling. Contents  Estimate the duration for each activity  Establish the estimated start time and required completion.
Hypothesis Means Test Extra Lesson 1 Have on the table your Estimation Moodle homework.
Prof.Dr. Ahmet R. Özdural – Class Notes_06 - KMU417 Project Planning and Organization – Fall Semester.
Q1) A precedes C. B precedes D & E. C precedes F & G. D precedes G.
PERT/CPM F G A E H I J K D St T B C
COB 300C Project Management Dr. Michael Busing. PERT ANALYSIS Optimistic-Likely-Pessimistic Project Times If you hold someone to a certain number, they.
PERT CPM assumes duration of activity is known with certainty.
Project Management – PTM721S
PERT/Activity Diagrams, Completion Probability and the Z Score
Project Management Chapter Topics
Chapter 6 Scheduling
The Normal Curve and Sampling Error
Theoretical Normal Curve
Probabilistic Time Estimates
Project Scheduling: networks, duration estimation, and critical path
Chapter 6 Scheduling
Project Management Ross L. Fink.
Year-3 The standard deviation plus or minus 3 for 99.2% for year three will cover a standard deviation from to To calculate the normal.
If the question asks: “Find the probability if...”
Uncertain activity duration (P14)
Practice #7.7 #7.8 #7.9. Practice #7.7 #7.8 #7.9.
Uncertain activity duration (P14)
Chapter 6 Scheduling
PERT/Activity Diagrams, Completion Probability and the Z Score
Combining Random Variables
Managing Risk Chapter 7.
The Mean Variance Standard Deviation and Z-Scores
Presentation transcript:

PERT/Activity Diagrams, Completion Probability and the Z Score Source: Bob Hugg, Thinking in Project Management Terms

PERT/CPM Define the goal of the project and the tasks required to complete it Place tasks in a logical order and determine the critical path The critical path is the longest time path through the network of tasks Generate a set of duration estimates for each task An optimistic, a most likely, and a pessimistic Label as a, b, c, or as TO, TL, TP

Calculate PERT for each task TE = (TP + 4TL + TO)/6 Complete the above for all tasks The sum of duration of tasks on the critical path will determine the project duration

Calculate standard deviation and variance Standard deviation is the average deviation from the estimated time As a general rule: the higher the SD, the greater the amount of uncertainty) SD = (TP – TO)/6 Variance reflects the speared of a value over a normal distribution V = (SD)2 SD and V are very useful in determining the probability of a project meeting its desired completion time

Sample table for the estimates

Consider the following tasks and activity diagram

Populate table with sample data

Table of estimates with start dates

Determine completion probability A wealth of information in the above table Critical tasks, non-critical tasks, best and worst estimates and the expected duration for each, SD and V values Calculate probability of project completion on a desired date S: the sum of all expected durations on the critical path V: the sum of all variances on the critical path D: Select a desired completion time Compute Z = (D-S)/√v Look up the value of Z (e.g., here)

An example What is the probability of completing the project in 15 days? Z = (D-S) /√V = (15 – 15.51) / √2.51 = -0.51/1.59 Z = -.321 A corresponding probability value for Z is 37.7% There is 38% probability that the project will be completed within 15 days of the start day