Building for Learning Project Photo Progress Report Month of May 2010 Project commencement 21 st September 2009
Lecture Theatre taking shape with multilevel ceiling and first layers of paint.
Upstairs entry area with ceiling panels ready to add. Building front without scaffolding
Balcony rendered and stairway constructed.
Toilets, wet areas and kitchen completed.
Downstairs hallway ceiling panels returned
Last of outside Hebal added and service units commissioned and room 9 painted.
Outside rendering completed and prior to renewed streetscape with Wodonga Council.
Final Admin area being plastered and toilet basins and cubicles added.
Council partnership streetscape starts
Room 8 and 9 carpet and ceiling panels returned.
The mighty ‘Dave’ finished the final front render
Harry – holding the verandah up with one finger Reg – always looking around to see the camera!!!!
Jess helping lift installation and building front