CONTRACT PRICING ALTERNATIVES Presented by: Fahad H. Al-Anazi CEM 520 February 27,1999.

Slides:



Advertisements
Similar presentations
1 CLIENT CONSULTANT AGREEMENT. 2 Negotiations Types of Consulting Contracts Standard Form of Contract Form of Contract General Conditions Special Conditions.
Advertisements

Construction Engineering 221
Contract Type Decision Guide
Contract Types and Recurring Requirements
Comparison of Major Contract Types
Advanced Project Management Project Procurement/Contract Management Ghazala Amin.
Fixed price contract: A contract that provides a price for each procurement item obtained under the contract.
CONTRACT A binding agreement between two or more parties for performing, or refraining from performing, some specified act(s) in exchange for lawful consideration.
Section 2 Production Chapter 3 Analysis of Indirect Costs Chapter 4 FPIF Contracts.
1 Appendix 4: Financial Risk Management: (Inflation) Overview: To develop an understanding of the ways in which financial risk from inflation can be minimized.
Chapter18 Contract Construction 1CE 417, King Saud University.
John Boon ZUT November Procurement Systems The organisation of the interaction between the purchaser of a new building and the suppliers of goods.
Contract Law 2014 NCHCA Education Series- January 23, 2014 Presented by Geoffrey Cantello, City of Ottawa and Ron Price, Rasmussen Starr Ruddy LLP.
On-Call Signal Contract Options for Discussion March 13, 2015 Cape Cod Joint Transportation Committee.
Project Procurement Management
Contract Types. Forms of Contracts Completion – A product is delivered –Cost or Fixed Price –Product must be delivered –Contract completed on delivery.
Bevan Brittan LLP- Highways Maintenance Contracts Nathan Bradberry, Senior Associate Johnathan Adams, Associate 6 November 2014.
Engineering Project Management Spacecraft Design Tuesday, January 21, 2003 M. McGrath.
Construction Contracts
Federal Acquisition Regulation (FAR) Part 16 Types of Contracts
Introductory to the “Basics” of Contract Types and Their Impact in the Management of Government Property Presented by: Fay K. Schulte, CPPM.
Contract Type Selection Don Shannon
State Auditor’s Office Change Order Pricing Practices Performance Audit of Eight Local Governments Puyallup City Council February 7, 2012 Chris Cortines,
Public Works Contracting Marsha Reilly Office of Program Research House of Representatives recommended.
Chapter 12 Procurement Management
Construction Contracts and Project Delivery Methods
S10 CONS5Q25 Lara Tookey. Review of estimators workings Decision on what margin to apply Bid submission details Submit your Tender.
Richard E. Thompson II, Esq.
Risk Assignment in The Delivery of a Project  RISK! –Construction projects have lot of it –Contractors manage it –Owners pay for it.
CIVL202 Construction Engineering I Tutorial 5 T1Mon11:00 – 11:50 T2Wed09:00 – 09:50.
Measurement and Payment. Construction Progress Payments –Contractor gives a bill for progress to RPR Outlines what bill is for Give details as needed.
Advanced Project Management Project Procurement/Contract Management Ghazala Amin.
Federal Acquisition Regulation (FAR) Part 16 Types of Contracts
Contingent pay- Incentives and rewards Individual Piece work: Uniform price per unit of production or pay is directly proportional to result Most piece.
TYPES OF CONTRACTS.
Construction Contracts
July 14, Rural Electric Cooperatives Procurement/Contracting Guidance Roger Jones Region VIII Disaster Assistance Division.
Chapter 11: Project Procurement Management
Project Procurement Management Lecture-8. What is Procurement? Project Procurement Management (PPM) includes the processes necessary to purchase or acquire.
Chapter 13 Estimates for Remodeling Work
Click on Next to continue Fixed Price Contracts Cost Reimbursable Contracts Time and Materials Next Involves setting a fixed total price for a defined.
Measurement and Payment
© Awad S. Hanna, PhD, P.E.1 Estimating and Scheduling CEE 492 Lecture 2 Construction Contracts.
Introduction to Procurement for Public Housing Authorities Procurement Planning: Choosing a Contracting Method Unit 2.
Block 7 Project Procurement Management. ► The processes required to acquire goods and services from outside the organization ► Purchasing  Procurement.
English for Construction Engineering Management ,建筑工 程专业英语 赖小东 授课教师:赖小东 Cell# 江西财经大学旅游与城市管理学院工程管理系.
Contracting Officer Podcast Slides
Comparison of Major Contract Types
Types of Fixed Price Contracts
Comparison of Major Contract Types
Light Rail Transit Project
Reconstruction site Investigation, Planning, Scheduling, Estimating and Design Eng. Fahmi Tarazi.
Comparison of Major Contract Types
PROJECT DELIVERY METHODS
(Additional materials)
Types of contract selection based upon following:
CMC200 FEES, FINANCING, AND PAYMENTS
Comparison of Major Contract Types
Request for Proposal & Proposal
Chapter 3 Proposed Solutions
Outsourcing: Managing Interorganizational Relations
Design-Build Acquisition and Contract Incentives July 19, 2018
ARCH 435 PROJECT MANAGEMENT
Comparison of Major Contract Types
Construction Contracts
Comparison of Major Contract Types
Design-Build Acquisition and Contract Incentives May 9, 2019
Directed Change Constructive Change
Comparison of Major Contract Types
Presentation transcript:

CONTRACT PRICING ALTERNATIVES Presented by: Fahad H. Al-Anazi CEM 520 February 27,1999

PRESENTATION OUTLINE Introduction Considerations for Selection of Pricing Methods Pricing Alternatives Contract Incentives Conclusions

Introduction Pricing alternatives are grouped in to two types: –Fixed price methods –Cost reimbursable methods Here, we will discuss all methods covering their features, costs risks, and applicability. Pricing terms: Certain pricing terms that used in contract pricing are defined as follow: Cost: contractor cost for labor, material, equipment and so on Fee: additional amount to be paid to the contractor over its incurred costs. Price: total amount to be paid by the owner Methods of pricing a contract

Lump sum Unit Price Lump Sum with escalation Fixed price incentive Fixed price prospective price redetermination Fixed price retroactive price redetermination Cost reimbursable, no fee Cost sharing cost plus incentive fee Cost plus awarded fee Cost plus fixed fee Time and Materials Cost plus percentage of the costs Owner preference Contractor preference PRICING ALTERNATIVES FIXED PRICE COST REIMBURSABLE

Considerations for Selection of Pricing Method No single pricing method is superior Combinations of pricing methods are common Performance incentives and escalation may be added to each pricing method Pricing methods must be defined properly in contractual agreements and must be carefully monitored to achieve their objectives Owners are not always free to select the pricing method Services are generally more difficult to price than goods Creative work is more difficult to price than goods or services

1. Lump Sum A definite and fixed price is agreed upon prior to contract award and is not subjected to adjustment except for changes in scope of work Risks to owner: –Possibility of large contingency amount being included in the contractual price –Changes of work: that not included in the lump sum amount and usually cost more –Breach of the contact –Reduction of bidder competition To reduce these risks: through bidder qualification procedure-thorough definition of scope-control of extra work This method is common for short duration and well-defined scope of works. It is common for smaller construction contracts

2. Unit Price Unit price method is a fixing of the price of a given unit of the work and the total price is the unit price times the the quantity of items delivered, erected, or installed Risks to owner are similar to the lump sump method Close monitoring at quantity verification is required to reduce risks to owner

3. Lump Sum With Escalation Escalation provisions can be applied to lump sum or unit prices. The purpose is to eliminate unwarranted price increases to cover contingencies in the contractor’s bid Escalation provisions call for adjustment based on –Contractor’s cost change from base amount –Published indexes of price changes for material or labor Considerations before awarding: –Selection of appropriate and applicable indexes –Careful definition of the amount to be escalated –Indexes application to progress payment, planned and actual expenditures

3. Lump Sum With Escalation Continued Costs risks to the owner are similar to the ones under lump sum. In order to reduce these risks owners should insist on clear definition and full enforcement of the items to be escalated and the method of determining escalation amounts

4. Fixed Price Incentives (Guaranteed Maximum) It allows the fee portion of the price to be adjusted (upward or downward) depending on actual costs incurred by the contractor During the contract agreement, a target cost, target fee and target price are agreed upon also, a ceiling price and share formula for overruns and under runs are defined Relations between these factors are explained in the following graph.

CONTRACTOR COST Target Fee Target cost Share line Ceiling price 60,000,00 3,000,00 66,000,00 Contractor’s Fee: $ 0 Contractor ‘Cost: $ 66,000,000 Owner’s Price: $ 66,000,000 Contractor’s Fee: $ -1,000,000 Contractor’s Cost: $ 67,000,000 Owner’s Price: $ 66,500,000 Contractor’s Fee: $ 4,500,000 Contractor’s Cost: $ 57,000,000 Owner’s Price: $ 61,500,000 0 CONTRACTOR FEE Share Ratio: Below CP : 50%-50% Above CP: 100% Contractor 4,500,000 CONTRACTOR COST Target Fee Target cost Share line Ceiling price 60,000,000 3,000,000 66,000,000 0 CONTRACTOR FEE Share Ratio: Below CP : 50%-50% Above CP: 100% Contractor 4,500,000 67,000,000 -1,000,000 FIXED PRICE INCENTIVES

4. Fixed Price Incentives Continued Risks to owner originate from –High setting of the ceiling price –Improper selection of the share formula If this method is selected, it is recommended to: –Determine a target cost and ceiling price that are reasonable and contain significant cost incentives –Negotiate a meaningful and realistic share formula –Maintain quality standards This method is used mainly for goods and services that are difficult to price in a fixed manner and it is common for large general construction contracts

5. Fixed Price Prospective Redetermination A firm fixed price is established for a portion of the work, and provisions are made for price redetermination for future work of the same type Risks associated with this type of pricing involve uncertainty at the time of agreement regarding price and quantity of future items or work This method is unused for construction contracts

6. Fixed Price Retroactive Redetermination In this method a ceiling price is negotiated prior to starting the work. After the work is completed, a final price is negotiated and it should not exceed the original ceiling price It is rarely used in construction projects

7. Cost Reimbursable, No Fee By this method the contractor is reimbursed for incurred costs only, no fee is paid This alternative has little application in commercial constructions It is generally restricted to work performed for non profit organizations such as universities and charity works or for works for research development

8. Cost Sharing Both contractor and owner share the cost of performing the work. No fee for the contractor It has no applications to construction projects It is generally restricted to nonprofit work, research projects, or for facilities that their benefit will be shared between the owner and the contractor

9. Cost Plus Incentive Fee This method is similar to a fixed-price-incentive- fee, except that the contractor is normally reimbursed for all his costs at a minimum Target cost, target fee, fee adjustment formula are factors that are determined by the contact parties Relations between the above factors are shown in the next graph:

CONTRACTOR’S COST Target Fee Target cost Share line 60,000,00 3,000,00 66,000,000 Contractor’s Fee: $ 0 Contractor ‘s cost: $ 66,000,000 Owner’s Price: $ 66,000,000 Contractor’s Fee: $ 4,500,000 Contractor’s Cost: $ 57,000,000 Owner’s Price: $ 61,500,000 0 CONTRACTOR’S FEE Share Ratio: All overruns & underruns: 50%-%50% No ceiling price 4,500,000 Target Fee Target cost Share line 60,000,000 3,000,000 Contractor’s Fee: $ 4,500,000 Contractor’s Cost: $ 57,000,000 Owner’s Price: $ 61,500, ,500,000 COST PLUS INCENTIVE FEE

9. Cost Plus Incentive Fee Continued Cost risks to the owner are similar to those under the fixed- price-incentive -fee. If the cost increases beyond minimum fee then the owner assumes all costs. Cost monitoring by the owner is required due to the absence of ceiling price Method advantages: –The contractor has some incentive to keep costs or labor hours down –Scope of work can be less specific when awarding –Agreement can be reached more rapidly than with the fixed-price method –Unnecessary contingencies in bid amounts should be eliminated This method is quite common in agreements with A-E firms and other consultants

10. Cost Plus Awarded Fee The contractor is reimbursed for all costs and receives a guaranteed minimum fee plus an awarded fee This type of pricing is used when uncertainty of work scope is too high to establish a ceiling price or when the work is first time attempt and the degree of performance is not ensured Rarely used for furnishing of goods and construction services

11. Cost Plus Fixed Fee In this method the contractor is reimbursed for all costs and receives a fixed fee for its services The fixed fee amount should bear some relation to the degree of difficulty in performing the work, the cost of the work and the duration of performance This pricing method is quite common for construction contracts and for some service- related contracts as well.

12. Time And Materials The contractor is reimbursed for all materials used at their actual cost and is paid for direct labor at a fixed rate (usually hourly) These contacts are simply obtained and can be awarded rapidly This method gives the contractor an incentive to increase the labor and materials cost so, greater effort is required to monitor materials costs and labor hours The are common for small scope of work; such as repairs or emergencies. It is quite common for construction work and professional services

13. Cost Plus Percentage Of Costs Contractor is reimbursed for all costs and given a fee that is directly proportional to some or all the costs involves in the work Cost-plus-percentage of the costs are not recommended for any application If used, they should be restricted for short duration, low-cost or emergencies work performed by reliable contractors

PROFIT INCENTIVES Cost, technical, schedule incentives can be used for all pricing methods. They are used to promote efficiency, quality, and timeliness of the contractor performance. Technical incentives punches or reward the contractor. The are used when certain performance is valuable and important to the owner Schedule incentives seek to reward contractors for early completion or penalize for the late completion.

CONCLUSION Selecting a contract type and its pricing strategies should be a logical process that considers: Nature of the work Time of performance Contractor marketplace Completeness of design information at the time of bidding Resources of owner to monitor and administer the contract

CONTRACT PRICING ALTERNATIVES Presented by: Fahad H. Al-anazi CEM 520 February 27,1999