Scheduling. Scheduling: The allocation of resources over time to accomplish specific tasks. Demand scheduling: A type of scheduling whereby customers.

Slides:



Advertisements
Similar presentations
Operations Scheduling
Advertisements

Johnson’s Rule Johnson’s rule: A procedure that minimizes makespan when scheduling a group of jobs on two workstations. Step 1. Find the shortest processing.
Scheduling.
Scheduling for Low-volume Operations Chapter 15 Operations Management by R. Dan Reid & Nada R. Sanders 2nd Edition © Wiley 2005 PowerPoint Presentation.
© The McGraw-Hill Companies, Inc., 1998 Irwin/McGraw-Hill Module 11 Operations Scheduling Chapter 16 (pp ) Work Center and definitions  Objectives.
Operations Management For Competitive Advantage 1 Operations Scheduling Operations Management For Competitive Advantage Chapter 15.
Scheduling.
© The McGraw-Hill Companies, Inc., Chapter 16 Operations Scheduling.
Operations Scheduling
PowerPoint presentation to accompany Operations Management, 6E (Heizer & Render) © 2001 by Prentice Hall, Inc., Upper Saddle River, N.J Operations.
1-1 McGraw-Hill/Irwin ©2009 The McGraw-Hill Companies, All Rights Reserved 1 Chapter 19 Operations Scheduling.
Operations Scheduling
Scheduling. Production Planning Process Process Planning Strategic Capacity Planning Aggregate Planning Master Production Scheduling Material Requirements.
DOM 102: Principles of Operations Management Operations Scheduling
Scheduling Chapter 19.
Short Term Scheduling Introduction What – Scheduling or timing of operations Where – Timing of operations affects the overall strategy Why – Reduce costs,
Short-Term Scheduling
Operations Management
© 2007 Pearson Education Scheduling Chapter 16. © 2007 Pearson Education Scheduling  Scheduling: The allocation of resources over time to accomplish.
Inputs and Outputs to Aggregate Production Planning
Scheduling. Characteristics of a “job” Constituent operations Constituent operations Due date Due date Time of arrival in shop Time of arrival in shop.
MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 6 SCHEDULING E
22–1. 22–2 Chapter Twenty-Two Copyright © 2014 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Scheduling.
1 ISQA 459/559 Mellie Pullman Scheduling Shop Floor.
1 Chapter 15 Scheduling. 2 Scheduling: Establishing the timing of the use of equipment, facilities and human activities in an organization Answering “when”
Scheduling – Day 2. Production Planning Process Process Planning Strategic Capacity Planning Aggregate Planning Master Production Scheduling Material.
CHAPTER 19 Scheduling Operations Management, Eighth Edition, by William J. Stevenson Copyright © 2005 by The McGraw-Hill Companies, Inc. All rights reserved.
Chapter 16: Learning Objectives
Operations Scheduling. Scheduling in a Process-Focused Environment.
Operations Management Contemporary Concepts and Cases Chapter Thirteen Scheduling Operations Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights.
Industrial Systems Engineering Dept. İzmir University of Economics
1. Facility size 2. Equipment procurement Long-term
Scheduling.
McGraw-Hill/Irwin Copyright © 2007 by The McGraw-Hill Companies, Inc. All rights reserved. 16 Scheduling.
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Chapter 17.
15-1Scheduling William J. Stevenson Operations Management 8 th edition.
15-1Scheduling William J. Stevenson Operations Management 8 th edition.
McGraw-Hill/Irwin Copyright © 2007 by The McGraw-Hill Companies, Inc. All rights reserved. 16 Scheduling.
1 1 Slide Short – Term Scheduling Professor Ahmadi.
Scheduling Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill.
Scheduling Process and Production Management.
Topics To Be Covered 1. Tasks of a Shop Control Manager.
1 Slides used in class may be different from slides in student pack Chapter 19 Operations Scheduling  Work Center Defined  Typical Scheduling and Control.
Scheduling for Low-volume Operations Chapter 15 Operations Management by R. Dan Reid & Nada R. Sanders 2nd Edition © Wiley 2005 PowerPoint Presentation.
Chapter 17 Scheduling. Management 3620Chapter 17 Schedule17-2 Overview of Production Planning Hierarchy Capacity Planning 1. Facility size 2. Equipment.
1 Manufacturing Operations Scheduling B2 [ ] B2 [ ] E5 [ E5 [ P9 [---] P9 [---] D1 [ D1 [
Scheduling. Definition of scheduling Establishing the timing of the use of equipment, facilities and human activities in an organization In the decision-making.
Scheduling for Low-volume Operations
CHAPTER SEVENTEEN SCHEDULING Chapter 17 Scheduling.
Scheduling Seminar exercises Process and Production Management.
CHAPTER 4 : SCHEDULING Presented by: HAMKA BIN TAIP
Scheduling Operations IDS 605 Spring Data Collection for Scheduling l Jobs l Activities l Employees l Equipment l Facilities Transparency 18.1.
Chapter 16 & 9 Scheduling Work & Employees. Scheduling Outline What needs to be scheduled? –doctor’s office, restaurant, mfg. plant, hospital –employees.
© The McGraw-Hill Companies, Inc., Chapter 16 Operations Scheduling.
0 Production and Operations Management Norman Gaither Greg Frazier Slides Prepared by John Loucks  1999 South-Western College Publishing.
Scheduling.
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Scheduling.
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved. Supplement J Operations Scheduling.
 Allocation of resources over time to accomplish specific tasks.  Scheduling is done in the short term time horizon i.e. months, weeks or days.  Effective.
Scheduling Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill.
16 Scheduling (focus on sequencing; FCFS, SPT, EDD pages , and Johnson’s rule pages ) Homework; 6, 7, 11.
15 - 1© 2014 Pearson Education, Inc. Short-Term Scheduling PowerPoint presentation to accompany Heizer and Render Operations Management, Eleventh Edition.
Scheduling Operations
Chap 11 Learning Objectives
8 Job Sequencing & Operations Scheduling CHAPTER Arranged by
Sequencing Sequencing: Determine the order in which jobs at a work center will be processed. Workstation: An area where one person works, usually with.
Production and Operations Management
Scheduling Seminar exercises
Inputs and Outputs to Aggregate Production Planning
Presentation transcript:

Scheduling

Scheduling: The allocation of resources over time to accomplish specific tasks. Demand scheduling: A type of scheduling whereby customers are assigned to a definite time for order fulfillment. Workforce scheduling: A type of scheduling that determines when employees work. Operations scheduling: A type of scheduling in which jobs are assigned to workstations or employees are assigned to jobs for specified time periods.

Performance Measures Job flow time: The amount of time a job spends in the service or manufacturing system. Also referred to as throughput time or time spent in the system, including service. Makespan: The total amount of time required to complete a group of jobs. Past due (Tardiness): The amount of time by which a job missed its due date or the percentage of total jobs processed over some period of time that missed their due dates. Work-in-process (WIP) inventory: Any job that is waiting in line, moving from one operation to the next, being delayed, being processed, or residing in a semi-finished state. Total inventory: The sum of scheduled receipts and on- hand inventories. Utilization: The percentage of work time that is productively spent by an employee or machine.

Gantt Charts Gantt chart: Used as a tool to monitor the progress of work and to view the load on workstations.  The chart takes two basic forms: (1) the job or activity progress chart, and (2) the workstation chart. The Gantt progress chart graphically displays the current status of each job or activity relative to its scheduled completion date. The Gantt workstation chart shows the load on the workstations and the nonproductive time.

Gantt Progress Chart Plymouth Ford Pontiac Job4/204/224/234/244/254/264/214/174/184/19 Current date Scheduled activity time Actual progress Start activity Finish activity Nonproductive time Gantt Progress Chart for an Auto Parts Company

Gantt Workstation Chart Gantt Workstation Chart for Hospital Operating Rooms

Operations Scheduling Operations schedules are short-term plans designed to implement the master production schedule.  Operations scheduling focuses on how best to use existing capacity.  Often, several jobs must be processed at one or more workstations. Typically, a variety of tasks can be performed at each workstation. Job shop: A firm that specializes in low- to medium- volume production and utilizes job or batch processes. Flow shop: A firm that specializes in medium- to high- volume production and utilizes line or continuous processes.

Shipping Department Manufacturing Process Raw Materials Legend: Batch of parts Workstation

Job Shop Dispatching Dispatching: A method of generating schedules in job shops whereby the decision about which job to process next is made using simple priority rules whenever the workstation becomes available for further processing. Priority sequencing rules: The rules that specify the job processing sequence when several jobs are waiting in line at a workstation.

Job Shop Dispatching Earliest due date (EDD): A priority sequencing rule that specifies that the job with the earliest due date is the next job to be processed. First-come, first-served (FCFS): A priority sequencing rule that specifies that the job arriving at the workstation first has the highest priority. Shortest processing time (SPT): A priority sequencing rule that specifies that the job requiring the shortest processing time is the next job to be processed. (Due date – Today’s date)/Total shop time remainingCritical ratio (CR): A ratio that is calculated by dividing the time remaining until a job’s due date by the total shop time remaining for the job. CR = (Due date – Today’s date)/Total shop time remaining –Total Shop Time = Setup, processing, move, and expected waiting times of all remaining operations, including the operation being scheduled.

Scheduling Jobs for Multiple Workstations Priority sequencing rules can be used to schedule more than one operation. Each operation is treated independently. Identifying the best priority rule to use at a particular operation in a process is a complex problem because the output from one process becomes the input for another. Computer simulation models are effective tools to determine which priority rules work best in a given situation. When a workstation becomes idle, the priority rule is applied to the jobs waiting for that operation, and the job with the highest priority is selected. When that operation is finished, the job is moved to the next operation in its routing, where it waits until it again has the highest priority.

Scheduling Problems One machine, many jobs Two machines, many jobs Three machines, many jobs Many machines, many jobs

One machine, many jobs Total time is independent of sequence SPT minimizes average flow time Examples- Mumbai airport

Two machines, many jobs All Jobs follow same sequence – Johnson’s Rule Jobs have different sequence – Jackson’s Rule Johnson’s 3 machine rule

Johnson’s Rule Johnson’s rule: A procedure that minimizes makespan when scheduling a group of jobs on two workstations. Step 1. Find the shortest processing time among the jobs not yet scheduled. If two or more jobs are tied, choose one job arbitrarily. Step 2. If the shortest processing time is on workstation 1, schedule the corresponding job as early as possible. If the shortest processing time is on workstation 2, schedule the corresponding job as late as possible. Step 3. Eliminate the last job scheduled from further consideration. Repeat steps 1 and 2 until all jobs have been scheduled.

Eliminate M3 from consideration. The next shortest time is M2 at Workstation 1, so schedule M2 first. Eliminate M5 from consideration. The next shortest time is M1 at workstation #1, so schedule M1 next. Eliminate M1 and the only job remaining to be scheduled is M4. Johnson’s Rule at the Morris Machine Co. Example 16.5 Johnson’s Rule at the Morris Machine Co. Time (hr) MotorWorkstation 1Workstation 2 M11222 M245 M353 M41516 M5108 Sequence = M1M2M3M4M5 Shortest time is 3 hours at workstation 2, so schedule job M3 last. Eliminate M2 from consideration. The next shortest time is M5 at workstation #2, so schedule M5 next to last.

Workstation M2 (4) M1 (12) M4 (15) M5 (10) M3 (5) Idle—available for further work Day Idle2 M2 (5) M1 (22) M4 (16) M5 (8) M3 (3) Idle 1 Gantt Chart for the Morris Machine Company Repair Schedule The schedule minimizes the idle time of workstation 2 and gives the fastest repair time for all five motors. No other sequence will produce a lower makespan. Johnson’s Rule at the Morris Machine Co. Example 16.5 Johnson’s Rule at the Morris Machine Co.

Classwork Job A B

Johnson’s 3 Machine Rule Domination – Largest on B is not greater than smallest on A or C. Domination guarantees optimality Conversion – Convert into a 2 M/C problem as M1 = A + B, M2 = B + C Find optimal sequence for this 2 machine problem Schedule on 3 machines based on the sequence above

Job A B C M M Classwork