RHIC Run14 Time Meeting. Run14 Status – Apr. 15 Operations running well, 12 stores over the past 7 days with 1 lost to another “super quench”. Testing.

Slides:



Advertisements
Similar presentations
Run 14 RHIC Machine/Experiments Meeting 27 May 2014 Agenda: Run 14 Schedule (Pile) Machine Status (Robert-Demolaize) STAR and PHENIX Status (Experiments)
Advertisements

RHIC Status Haixin Huang Time Meeting 02/1/2011. Jan. 26 Ring access for six hours to fix jet and many other jobs. Difficulty to provide 28X28 store overnight.
1 RHIC Run-7 Au-Au Operation A. Drees APEX workshop, Nov 2 nd 2006 Run organization Previous run and expectation for Run7 Start-Up plan Problem areas.
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
RHIC Heavy Ion Run-11 Status Meeting Updates. Heavy Ion Run Final Update 6/24-27 ● Physics running, 41 stores – Tandem intensity issues – Access controls.
Friday, h10: Stable beams at 1.38 TeV. 09h03: Beam dump.  One bunch dropped too much in intensity and gave BPMS interlock (dump protection). 10h36:
Run 11 as run 3 Jan, Begin cool-down to 4.5K 8 Jan, Cool-down to 4.5K complete in both rings, preliminary setup begins 24 Jan, 1 week Ramp-up with 8 hr/night.
RUN 11 RHIC MACHINE/EXPERIMENTS MEETING 5 Apr 2011 Agenda: Open.
1 Near-term machine performance — The next 5 years, before e-cooling — Wolfram Fischer Run Coordinator for RHIC Run-4 Open Meeting on RHIC Planning Berkner.
Run 13 RHIC Machine/Experiments Meeting 21 May 2013 Agenda: Status Reports.
Run 13 RHIC Machine/Experiments Meeting 4 Jun 2013 Agenda: Status Reports Hydrogen Jet issue (Eyser)
● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
Overview Run-6 - RHIC Vadim Ptitsyn C-AD, BNL. V.Ptitsyn RHIC Spin Workshop 2006 RHIC Run-6 Timeline  1 Feb – Start of the Run-6. Start of the cooldown.
RHIC Status Haixin Huang Time Meeting 01/18/2011.
Machine - Experiments January 12, 2005 Machine status.
RHIC Status Time Meeting 2/3/2015 He is fixed into the ice at the center to which flow all the rivers of guilt; and as he beats his great wings as if to.
October 4-5, Electron Lens Beam Physics Overview Yun Luo for RHIC e-lens team October 4-5, 2010 Electron Lens.
Run 14 RHIC Machine/Experiments Meeting 1 July 2014 Agenda: Run 14 Schedule (Pile) Machine Status (Robert-Demolaize) STAR and PHENIX Status (Experiments)
Preparation for RHIC PP Run in 2011 Wednesday 20, 2010 RHIC Machine Planning Meeting Haixin Huang RUN website: RUN.
RHIC Run14 Time Meeting. Run14 Status – Apr. 29 Operations running well, 11 full stores over the past 7 days; setting STAR ZDC rates to 50 khz is now.
AGS pp Status Jan. 13, 2015 Time Meeting Haixin Huang.
:00: Prepared new fill B1: Q X =0.293, Q Y =0.269; lifetime = 25h ✔ B2: Q X =0.297, Q Y =0.267; lifetime = 5h ✗ Strong 50Hz and 100hz lines.
RHIC Status: Startup Run 12 V. Schoefer RHIC Spin Collaboration Meeting 1/13/12.
Machine status – December 28  Machine status - overview  Blue ring: ramp development  Yellow ring: obstruction update  Set-up and ramp-up.
LHC progress Report LHCC Wednesday 23 rd March 2011.
RHIC Run14 Time Meeting. Run14 Status – Apr. 22 Operations running well, 12 stores over the past 7 days with 1 “super store” of 17 hours. Repositioned.
Nominal intensity bunches ● First ramp with nominal intensity bunches suffered from an instability appearing around 1.8 TeV. ● Nominal intensity bunches.
RUN 11 RHIC MACHINE/EXPERIMENTS MEETING 12 Apr 2011 Agenda: Open.
APEX Report: February 26-27, 2008 Fulvia Pilat Time Meeting, March 4, 2008.
RUN 11 RHIC MACHINE/EXPERIMENTS MEETING 14 Mar 2011 Agenda: Status – cryo/budget Experiment priorities.
RHIC Run11 Summary May 6, 2011 RSC Meeting Haixin Huang Luminosity Availability Polarization RHIC setup issues.
Run 10 plan based on 25 Nov Revised Plan and  s=200 extended by 1 week Dec. 1, Begin cool down to 4.5K Dec. 4, Cooldown to 4.5K complete in both rings!
F All Experimenters' Mtg - 2 Jun 03 Weeks in Review: 05/19/03 –06/02/03 Keith Gollwitzer – FNAL Stores and Operations Summary Standard Plots.
Run 12 RHIC Machine/Experiments Meeting 17 Apr 2012 Agenda: Status reports Polarization issues update (E. Aschenauer) Other business With 17 April update.
APEX RUN-14 APEX Schedule April 1, :00am Store Elens commissioning Gu, Fischer, Luo, Simon 10:00am 4:30pm2:00pm AC dipole setup Bai Momentum Aperture.
Preparation Status of pp Run11 Haixin Huang Time Meeting 12/21/
RHIC status Chuyu Liu Time meeting Apr. 28, 2015.
Prospects for RHIC Low-Energy Operations Todd Satogata (W. Fischer, T. Roser, A. Fedotov, N. Tsoupas, M. Brennan, C. Montag, and others) “Can We Discover.
Nuclear Phase Transition Diagram Mar RHIC Monday Meeting T. Satogata DOE NSAC Long Range Plan … a whole page! (one out of 14)
RHIC Run14 Time Meeting. Run14 Status – May 27 Operations running well, 11 full stores over the past 7 days. Getting high intensity again from injectors,
RHIC Run14 Time Meeting. Run14 Status – June 24 Run14 He3-Au physics declared on 6/20 with Fill #18460; stochastic cooling is ON for Au beam, longitudinal.
Run 12 RHIC Machine/Experiments Meeting 24 Apr 2012 Agenda: Status reports Other business.
Agenda Safety Schedule Machine and system reports 2/26/2016G. Robert-Demolaize, Time Meeting1.
APEX Schedule April :30am12:30pm5pm IBS suppression lattice Litvinenko, Tepikian +team Back 2 Phys 4pm Nonlinear Chromaticity (Response.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
RHIC 250 GeV Polarized Proton Run 2009 Mei Bai RUN website: 12/16/2008RHIC Spin Collaboration Meeting.
RHIC Status April 8, 2011 RSC Meeting Haixin Huang.
Run 10 Start-up Status
RUN 11 RHIC MACHINE/EXPERIMENTS MEETING 7 Jun 2011 Agenda: √s = 200 GeV AuAu progress 27 GeV Run (or other)
RHIC Status Haixin Huang RSC Meeting 02/18/2011. l Fixed the blue dump kicker noise problem last Friday. l Declared physics last Friday. l Smooth run.
RUN 11 RHIC MACHINE/EXPERIMENTS MEETING 31 May 2011 Agenda: √s = 200 GeV AuAu progress Update on 250 GeV integrated Lumi.
RUN 11 RHIC MACHINE/EXPERIMENTS MEETING 14 Jun 2011 Agenda: √s = 200 GeV AuAu progress ZDC Calibration for AnDY – the plan Request from AnDY √s = 27 GeV.
RUN 11 RHIC MACHINE/EXPERIMENTS MEETING 29 Mar 2011 Agenda: Open.
RUN 11 RHIC MACHINE/EXPERIMENTS MEETING 22 Mar 2011 Agenda: Open.
RHIC Operation Status Yun Luo, ( 2012 June 19, Time Meeting )
Possible Run 10 plan based on 25 Nov Revised Plan Run10, 25 cryo-weeks (my guesses after Jan 12) – Dec. 1, Begin cool down to 4.5K – Dec. 4, Cooldown to.
Run 10 plan based on 25 Nov Revised Plan and  s=200 extended by 1 week Dec. 1, Begin cool down to 4.5K Dec. 4, Cooldown to 4.5K complete in both rings!
A RHIC Low-Energy Test Run With Protons Todd Satogata (W. Fischer, T. Roser, J. DeLong, M. Brennan, D. Bruno, and others) April 11, 2006 Driven by discussions.
RHIC Status Haixin Huang Time Meeting 01/25/2011.
-9:00: Test IP transverse adjustment (CMS) and optics verification.
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Summary of Week 16 G. Arduini, J. Wenninger
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Friday 16/3 08:30 – 10:15 Access for QPS and EPC (BI in point 4)
Summary Thursday h21: Stable beams fill #1303.
Friday 8/10/10 - Morning Planned to keep fill until the afternoon
Another Immortal Fill….
Monday 152 bunch operation summary
Presentation transcript:

RHIC Run14 Time Meeting

Run14 Status – Apr. 15 Operations running well, 12 stores over the past 7 days with 1 lost to another “super quench”. Testing fast gating for longitudinal cooling to reduce satellite bunches. APEX: Proof of principle of 60 cm optics in both Blue and Yellow with very reasonable lifetime despite (usual) large emittances at store. Last Friday (4/11): 3 quenches in 14 hours but problem is understood: superconducting solenoids are running at 10% of their current settings to limit frequency of event. Polarized protons setup running behind stores. Thursday (4/17): request for MD time to address PHENIX question on longitudinal position of collisions. 56 MHz SRF cavity commissioning in next few weeks, contingent on completion of all tasks scheduled for Maintenance. Maintenance tomorrow, APEX on 4/23.

Run14 Status – Apr. 8 Operations running well, 12 stores over the past 7 days. Emittances through stores are monitored so that tunes can be moved around to maximize the effect of stochastic cooling. Recovery from maintenance was delayed “first by a cooling fault in the xq1 magnet and then by problems with G10 kicker fine delay controls” [OC log]. Tried a couple of 6x6 ramps to test RF settings too, but had miscommunication with P. Sampson about it. Lesson learned… AGS main magnet running with Siemens MG after switching from Westinghouse on Thursday (4/3). Machine Development time was scheduled for Friday (4/4) AM, around PHENIX access to replace Teflon tubes: ◦ end of store attempt failed due to orbit feedback using the wrong target orbit; ◦ post PHENIX access, turns out ATR had other plans for us, and with increasing recovery time from this problem, priority was given to running physics, especially so close to the weekend. There was no beam in RHIC from ~11:00 to ~17:00. Sunday (4/6): “QLI in blue and yellow rings that fired all the DX heaters and resulted in extended cryo recovery. The ultimate cause was found to be a bad 5V supply for the blue main dipole” [OC log]. MD pushed back to 2:45pm today: Ramp Optics measurement + beta* = 60cm commissioning for both Blue and Yellow beam. Thursday (4/10): low ZDC rates run, around 3-5 kHz only – translates to 0.25e9 ions/bunch with a 111x111 fill pattern. Need tests to make sure injectors and RHIC instrumentation can run this low. APEX tomorrow, Maintenance on 4/16.

Run14 Status – Apr. 1 Stochastic Cooling: all 3 planes B+Y since 3/28; monitoring the effect of Yellow cooling on Blue emittances as the store progresses. Additionally, yesterday (3/31) the fast gate for longitudinal cooling in Yellow was turned on: main bunch and first 2 satellites only are being cooled First APEX on 3/26 was a success; dynamic β * squeeze tested, will turn operational. First commissioning test of e-lens with beam, using last bunch(es) of train. Investigated Blue QLI’s on the down ramp: no conclusive results, diagnostics hard considering the low frequency of events. Corrected store orbit feedback procedure to reduce orbit drift and seesaw ZDC rates. Recorded 2 Yellow Abort Kicker prefires. AC problems in 6 buildings: main problem was on 3/29, causing 2 QLI’s at store due to a quench detector in 1006B affected to the AC tripping. Maintenance tomorrow, APEX on 4/9.

Run14 Status – Mar x111 fills at 1.6e9 ions/bunch w/ rebucketing at store; scrubbing essentially done. New record peak luminosity for Fill with L > 60e26 cm -2 s -1. Stochastic Cooling: longitudinal in B+Y since 3/21, horizontal just about operational. Few hiccups with intensities from EBIS. Sat. to Sun. (from eLog): “2 failed ramps due to Landau trips, a bad BPM messing up orbit, and a blue [QLI] that occurred when yellow feedback was engaged at store”. => all problems were addressed and solved/understood BS3-4 storage cavities tripping; work ongoing to troubleshoot, solution imminent. Fix for main magnet regulator loop card, to reduce risks of QLI on up/down ramps. First APEX: 16 hours tomorrow (3/26), back in physics for the following OWL shift.

Run14 Status – Mar. 18 Switched over from Low Energy Run on 3/11, with first beam circulating in RHIC at regular injection energy at 04:00 on 3/12. First 6x6 ramp at 11:30 on 3/13. Set up orbit bumps for pre-fire protection in both rings: initial peak amplitude was 30mm, but caused repeated QLI’s with every regular beam dump. Amplitude scaled down to 20mm after careful aperture scan on 3/ x111 fills at 0.8e9 ions/bunch w/ rebucketing at store since 3/15 at 02:00. Physics declared with Fill 18046, 14:10 on 3/15. Slowly increasing the bunch intensity for scrubbing; goal is 1.3e9 by 3/19 at 08:00 (prior to Maintenance Day). Continuing work on Landau cavities; Stochastic Cooling commissioning (all 3 planes) should start right after we recover from Maintenance. Chromaticity measured at injection, store and along the ramp (via radial offset); linear optics measured at injection and store. eLens commissioning running in parallel to operations.