1 Joint LHC Machine-Experiments Meeting on Experiment Protection from Beam Failures Summary and action list D. Macina TS/LEA/INT LEMIC 91.

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

12/03/2013MPP Workshop Annecy Update on Beam Failure Scenarios Jan Uythoven Thanks to: T.Baer, R.Schmidt, J.Wenninger, D.Wollmann, M.Zerlauth, other MPP.
PAC June LHC Machine Protection Rüdiger Schmidt R.Assmann, E.Carlier, B.Dehning, R.Denz, B.Goddard, E.B.Holzer, V.Kain, B.Puccio, B.Todd, J.Uythoven,
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Day ● 09:00-14:00: Collimation setup 3.5 TeV – Slowed down by losses induced by tune hump. – 48 collimators set up. – Beam dumped by ATLAS during.
Injection test? Mike Lamont For initial discussion.
Beam Dumping System – Failure Scenarios Brennan Goddard, CERN AB/BT How the dump system can fail Catalogue of primary failures Failure classes and protection.
Tuesday 10 th April - morning Access for:  point 3 Jerome Landaro TCSG one jaw didn't move  point 5 Qps expert on RPMBB.UJ56.RCBXH1.R5  point 6 TCDQ.
21/05/2012LHC 8:30 meeting Overview Week 20 Injectors, LHCb polarity, Beam-Beam Coordinators: Bernhard Holzer, Jan Uythoven.
Beam Commissioning Workshop, 19th January Luminosity Optimization S. White, H. Burkhardt.
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
Overview of Machine Protection for the LHC
January 2006Beam dump and injection inhibits / J.Wenninger1 Beam Dump and Injection Inhibits J. Wenninger AB-OP & D. Macina TS-LEA LHC experiments signals.
Daniela Macina (CERN) Workshop on Experimental Conditions and Beam Induced Detector Backgrounds, CERN 3-4 April 2008 Experiments protection from beam failures.
● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
Experimental equipment interacting with beam operation D. Macina TS/LEA Many thanks to my colleagues both from the experiments and the machine for their.
LER Workshop, CERN, October 11-12, 2006Detector Safety with LER - Henryk Piekarz1 LHC Accelerator Research Program bnl-fnal-lbnl-slac Accelerator & Detector.
Post Mortem Collimators and Movable Objects Michel Jonker Post Mortem Workshop Cern, 16 & 17 January 2007.
1 Interlock logic for LHC injection: intensity limitations Jörg Wenninger AB-OP-SPS Outcome of the join Machine-Experiments Workshop on Machine Protection.
The Large Hadron Collider Contents: 1. The machine II. The beam III. The interaction regions IV. First LHC beam [R. Alemany] [CERN AB/OP] [Engineer In.
R. Assmann - LHCCWG Two Beam Operation R.W. Aßmann LHCCWG Acknowledgements to W. Herr, V. Previtali, A. Butterworth, P. Baudrenghien, J. Uythoven,
Tuesday 17 th April 04:00 Prepare second fill for v/d Meer scans. 06:22 Stable beams, v/d Meer scans for Alice and LHCb. 13:20 End v/d Meer scans.Dump.
1 CC & MP - CC10 - CERN Crab LHC J. Wenninger CERN Beams Department for the LHC Machine Protection Panel.
Status of ABT beam tests preparation 9-Oct-14. Preparation of sector test without beam I MKI: – Open valves, conditioning to 55 kV, softstart – Check.
Simulations of TCT beam impacts for different scenarios R. Bruce, E. Quaranta, S. RedaelliAcknowledgement: L. Lari, C. Bracco, B. Goddard.
P. 1Mario Deile – Meeting on Experiment Protection from Beam Failures Protecting TOTEM Mario Deile PH-TOT
Schedule IT General Schedule 9 th, September 09 Today.
‘Review’ of the machine protection system in the SPS 1 J. Wenninger BE-OP SPS MPS - ATOP 09.
1 Commissioning and Early Operation – View from Machine Protection Jan Uythoven (AB/BT) Thanks to the members of the MPWG.
1 Machine considerations and constraints for the Safe Injection Flag and Safe Beam Flag Jörg Wenninger AB-OP-SPS Introduction to ‘injection flags’ Machine.
Outline of 2014/2015 plans V. Kain, M. Lamont, J. Wenninger 6/18/2013Optics Measurement and Correction Review
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Cryo back at 17:30 Beam back at 19:00 IR2 aperture until ~03:00 Since then no beam from the SPS:  Connector problem on MKD  Connector eroded, needs to.
Beam absorbers for Machine Protection at LHC and SPS
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
HL-LHC WP14 2 nd meeting: Intercepting devices and failure cases to be studied Anton Lechner, Jan Uythoven.
The TV Beam Observation system - BTV
Wednesday
MD Planning Fri – Sat (26. – 27.8.)
Wednesday 8.9 External crossing angles:
Introduction: FCC beam dumping system
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Overview on LHC Machine Failure Scenarios
Safe Injection into the LHC V.Kain AB/CO
Safe Injection into the LHC V.Kain AB/CO
Initial Experience with the Machine Protection System for LHC
Thursday morning – optics correction
Machine availability reaching well over 80%
CNGS Primary Beam Results 2010
Remote setting of LHC BLM thresholds?
Machine Protection Xu Hongliang.
Interlocking of CNGS (and other high intensity beams) at the SPS
LHC commissioning Week 38
LHC Injection and Dump Protection
Week 35 – Technical Stop and Restart
Beam Dump and Injection Inhibits
Planning at 5 o’clock meeting Friday
450 GeV Initial Commissioning with Pilot Beam - Beam Instrumentation
Protection against accidental beam loss at the LHC
Chamonix Workshop XIV CERN - 17th-21st January 2005
Commissioning of the Beam Conditions Monitor of the LHCb Experiment at CERN Ch. Ilgner, October 23, 2008 on behalf of the LHCb BCM group at TU Dortmund:
Machine protection and closed orbit
Beam Interlocks for Detectors and Movable Devices
Machine Protection Issues for LHCb
The LHC Beam Interlock System
Interlocking strategy
Another Immortal Fill….
What systems request a beam dump? And when do we need them?
HI2011 Commissioning Status
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

1 Joint LHC Machine-Experiments Meeting on Experiment Protection from Beam Failures Summary and action list D. Macina TS/LEA/INT LEMIC 91

2 Machine protection at the LHC : ‘organization’ Machine protection activities of the LHC and the SPS are coordinated by the LHC Machine Protection Working Group (MPWG), co-chaired by R. Schmidt & J. Wenninger. The MPWG WEB site (only from inside CERN !) The detailed description of the commissioning of the LHC Machine Protection System and the record the test results is the mandate of the Commissioning of the Machine Protection System Sub-Working-Group. It reports to the LHCCWG. Web site: New : The MPWG has asked each LHC experiment to provide a contact person (BISU) to interface on machine protection issues between machine and experiments. Antonello Di Mauro (ALICE) Siegfried Wenig (ATLAS) Alick Macpherson (CMS) Richard Jacobsson (LHCb) Anne-Laure Perrot (LHCf) Mario Deile (TOTEM)

3 Program

4 Safe beam The MPWG has adopted for the LHC a limit for safe beams (nom. emittance) of protons at 450 GeV ( <~ Cu melting point) protons at 7 TeV (scaled from 450 GeV) - under discussion!! Standard procedure: if empty machine => inject pilot bunch (5x10 9 p) BUT it is technically possible to inject a safe beam into an empty machine (no interlock forbids it) If safe beams no injection protection required and, in case of circulating beam, absorbers and collimators at relaxed settings/not required. Safe beams are used for the fine tuning of the machine protection elements at each new fill. Some interlock may/will be masked IF and ONLY IF beam is safe

5 Beam cleaning The protons that are lost must be intercepted with very high efficiency before they can quench a superconducting magnet : collimation! Unlike HERA, TEVATRON, RHIC.. the LHC cannot be operated without collimators (except at injection with low intensity). At the LHC the collimators must define the aperture (primary + secondary) which has an important impact for MP : for most multi-turn failures the beam will hit collimators first !

6 Machine Aperture GeV 7 TeV,  * 0.5 m Vertical axis : Machine aperture in units of beam sigma (  ), including alignment errors and other tolerances. Horizontal axis : Longitudinal position on left side of ATLAS (seen from the ring center). Arc ATLAS Injection : Aperture limit is the LHC ARCs (~ 7-8  ). The triplet magnets in front of ATLAS/CMS are slightly behind the ARC (~ 8-9  ).  ~5-6  ! Collisions, squeeze to  * 0.5 m : Aperture limit is defined by the triplet magnets in front of ATLAS/CMS (~ 8  )..  ~6  ! Triplet Experiments-Machine WS / June 07 End of the squeeze (  * TCT needs to be closed

7 Additional general items Software interlock –The reaction time of this system will be at the level of a few seconds. –The systems rely entirely on the machine technical network, databases, etc – clearly not as safe as HW systems ! –The Injection SIS will complement the Injection Interlock Systems: - Active from the beginning. - Stops injection through the Injection Interlock Systems. -Receives the experiments injection inhibits, either through our middleware (preferred) or through DIP. Post Mortem Analysis –All machine user systems connected to the LHC BIS must provide Post- Mortem information for diagnostics, even systems that have NOT triggered the dump. To resume beam operation after a beam dump, the PM data must be analysed and ‘understood’

8 Injection - Extraction Same principle for injection and extraction: –“kicker” magnets: fast rise time → much less than one turn, large (~ mrad) angles –septa: two(/more) apertures with different magnetic fields Injection: –Beam 1: IR 2 –Beam 2: IR 8 Extraction: –Both beams in IR 6 Injection process and extraction process can lead to single turn beam loss!! => –Everything” required for injection/(extraction) plus the LHC ring must have the right value/state –Dedicated passive protection

9 MSI Q5Q4 D2 MKI Transfer line IP2 Injection overview The injection septum MSI bends the beam into the LHC in the horizontal plane The injection kicker MKI kicks the beam in the vertical plane onto the LHC orbit Possible injection failures: –Wrong current setting in the transfer line magnets + injection septum, fast trip of power supply, failure of SPS extraction kicker (MKE) during extraction, fast trip of power supply – e.g. downstream of transfer line collimators (protection: current surveillance, fast current monitors, absorbers) –Injection kicker failures in the LHC => caught by DEDICATED MOVEABLE ABSORBER TDI behind kicker and auxiliary movable collimators TCLI in the injection regions

10 Error settings at injection Error settings at injection (empty machine) of D1/D2 and orbit correctors in the LSS may drive in beam in the experimental areas. It affects all experimental insertions. Not possible to hit directly the detectors if only one failure considered (at least in IR1/IR5) Ex. MCBXH wrong settings (30-100%) nominal at injection is 5%

11 LHC Extraction (IR6) Q5R Q4R Q4L Q5L Beam 2 Beam 1 Beam Dump Block Septum magnet deflecting the extracted beam MSD H-V kicker for painting the beam about 700 m about 500 m 15 kicker magnets MKD Clean dump Synchronisation: the kicker rise time must coincide with the particle free abort gap Particle free abort gap Energy Tracking – (required kick strength from the beam energy via magnet currents)

12 Possible failures at extraction Lost synchronisation with the abort gap Pre-fire of one of the 15 kicker modules (hard-wired system triggers all remaining 14 in µs ) Frequency: once per year possible Solution: dedicated passive protection; – TCDQ (movable) and TCS protect Q4 and general LHC apertures –TCDS protects the MSD septa In case of problems during extraction coupled with TCDQ settings, orbit or optics errors, “some” beam loss at the tertiary collimators/triplets in IR5 may occur. Difficult to quantify - detailed analysis ongoing. PhD thesis of Thomas Kramer, AB/BT. If abort gap (re-)population => caught by TCDQ and interlocking on abort gap monitor signal

13 Possible failures with circulating beam (magnet failures including operation mistakes) Usually slow and detected first in the aperture restrictions of the machine (cleaning insertions) Potential danger for the experiments (VELO and RP): uncontrolled closed bumps since they could affect only experimental areas. However: –Extremely difficult to create at 7 TeV (less difficult at 450 GeV) –They build up slowly: first losses seen by the BLMs and beam extraction before damage threshold –Only critical if combined with a fast failure => low probability

14 Summary of machine failures Errors/failures which may drive the beam into the experimental areas; –Settings errors at injection –Undetected closed bump & fast magnet failures (highly unprobable) Errors/failures which may drive the beam in the aperture restrictions in the LSS: –Injection errors (IR2, IR8) –Asynchronous beam dump (IR5)

15 Experiments (1) ATLAS –BCM+ LUCID used for beam abort –Injection errors: ok for pilot bunch, concern for Safe Beam. What is the structure of Safe Beam? –Questions: mechanism for beam blow up at the IP? How loss of vacuum close to IP is treated? ALICE –BCM used for beam dump (same system developed by LHCb). Position dictated by available space. Needs failures/error simulations to show the position is valid for the most relevant scenarios –Consequences of injection errors: old analysis. Still valid? –During injection: only BCM ON and possibly a few detectors at safe setting to monitor the losses in the experimental areas –Concern about Safe Beam

16 Experiments (2) CMS –BCM with standard LHC BLM Readout and Interface –Worry particularly about high rates of loss rather than integrated doses –Needed updated simulation (most realistic worst case scenario) for asynchronous beam dump and injection –IF BCM OFF (no protection system) => no beam allowed in the machine –IF CMS OFF but BCM ON => beam allowed –BCM and CIBU on machine power (no local UPS) –Concern about Safe Beam

17 Experiments (3) LHCb –BCM for beam dump. Readout front end same as BLMs –Entire BCM system under UPS –Concern On Safe Beam –Needs simulation for beam failures LHCf –Beam dump based on the detector itself. All scintillators hit => beam dump –The experiment will run only for a few days per year: disconnected from the BIC when not in the TAN –The whole system is on ATLAS UPS –Scintillators always ON at injection

18 Experiments (4) TOTEM –T1 and T2 should be protected by the CMS system –RP: simulation for bunch hitting the pot: For β *=1540 m only ok for bunch <= 6x10 10 p For β *= m beam wider, depends on number of bunches –TOTEM CIBU only used for the positioning of the RP. The other CIBU forced TRUE, may be used later

19 Open issues and action list (1) Safe Beam –This is a concern for all experiments. If not absolutely needed, experiments ask to lower to x10 11 p. Is this OK or just a feeling? Can be simulated/calculated? –Action: MPWG Post Mortem Data –Data from the experiments for all dumps –Experiments need PM Data from the Machine? –Details to be discussed –Action: AB/CO+ AB/OP + LEADE Safe Beam Flag to the experiments –Technically all experiments can receive it via the GMT receiver –Only LHCb has requested it –Action: BISU

20 Open issues and action list (2) Injection inhibit –By SW: decide on protocol –New idea for HW with fiber-CIBU –Action: MPWG + AB/CO + LEADE CIBU (and Protection System) Power –On UPS on two different power sources –Survive a power cut for 10 minutes –CMS philosophy: BCM must be ON whenever the machine is ON => machine power and not CMS power –Apply to all experiments? –Action: MPWG + LEADE + BISU

21 Open issues and action list (3) CMS Philosophy –No beam allowed if CMS protection system is OFF –Beam allowed if CMS not operational –Adopted by all experiments? –What is the reliability of the experiment’s protection system? Is it there a backup solution? How many unjustified dump per experiments? –Aim for 1/year/exp? Procedure after emergency beam dump –CMS request to latch their input until PM check is done. Check re-arm time scale Action?

22 Open issues and action list (4) How to detect direct hit in experimental area at injection if detector off? –Possible with BCM even if may be not always sufficient –A few additional detectors ON at safe settings? –Action: BISU TCTs for 2008 –Missing Vertical TCT in IR2 and IR8. Is this a problem for small  *? –Action: MPWG + Collimation WG Bump scenarios and wrong settings at injection –Software Interlock surveillance of D1/D2/correctors in the experimental insertions at injection & collision –Action: SIS + MPWG

23 Open issues and action list (5) Abort gap monitor –Status + connection to BIC –Action: MPWG + AB/BI Simulations –Asynchronous beam dump (including RP) => AB/BT –Consequences of the failure scenarios at injection => (AB/BT? TS/LEA? BISU?) –Error settings at injection (in particular IR2/IR8) => (TS/LEA?) -Additional failure scenarios when circulating beam (beam steering) => (AB/ABP?, AB/CO/MI??) -RP: simulations including mechanical stresses => (TS/LEA-MME?)

24 To be done in addition… Get more information and check consistency of the radiation damage threshold for similar detectors in different experiments Better define the injection inhibit philosophy Define/organize the test procedures Define/organize the commissioning procedures together with the Commissioning of the Machine Protection System Sub-Working-Group