1 Cross Border Intraday on the North Italian Borders Interim solution – Scheduling Forum Rome, 13 th March 2012.

Slides:



Advertisements
Similar presentations
1 SETSO TF SETSO TF NACMPF SG Congestion Management and NTC.
Advertisements

European Federation of Energy Traders 1 Electricity Regional Initiative Central-South Europe Region 4th Stakeholder Group meeting The Central South Region.
Deliverable I.4 Balancing (15th IG meeting, Paris, April 7th 2014)
Access to long-term capacity for electric interconnections: toward a single European set of rules 2 nd common RCC CSE-CWE regions 28 September 2010 Milan.
Assessment of differences in market designs in the CS region Milan 18 July 2008.
Action plan covering 2008 activities for the implementation of day-ahead implicit auction in Central-South Europe as a mean to allocate cross border capacity.
1 page 1 NWE Intraday - Joint TSO and PX presentation London.
Completing the EU internal energy market IFIEC, 22 November 2011
ERI CS REM, 11th IG meeting. Milan, 21 November 2008 Towards a single auction platform in the SW region Rafael Gómez-Elvira Deputy Director for European.
CM Guidelines, Implicit Auction as a Congestion Management Method Baltic Electricity Market Mini-Forum 24 April 2009 Jyrki Uusitalo, Fingrid Oyj.
SWE Day-ahead market coupling (Pre- and Post-Coupling project) Lisbon, 3 rd December th Implementation Group meeting.
Introduction of an Intraday market on the Italian borders for the year 2011 Terna proposal Electricity Regional Initiative – CSE Region 15th Implementation.
Italy-France Cross-border Intraday: Technical feasibility study CSE SG Group meeting Rome, 15 May 2012.
Feedback on the SWE coupling Public Consultation Imeplementation Group meeting – 7th april 2014.
Draft document – Work in progress
FUI Electricity region: Update on Congestion management CRE SG Meeting - 3 December 2008.
Does the Third Package provide the European TSO associations with the tools necessary to find solutions to the European energy challenge ? Pierre BORNARD.
Allocation Rules Martin Apko CAO Central Allocation Office GmbH 30 February 2009, CEE Implementation Group, Vienna.
Pamela Taylor, Ofgem Gas Target Model, 3 rd stakeholder workshop 11 th April 2011, London Connecting markets.
SWE Day- Ahead market coupling 7 April 2014 Implementation Group meeting – Paris.
Completing the EU internal energy market
European Federation of Energy Traders 1 8th SG meeting ERI South-West Europe 6 th October 2014, Madrid.
IFE-CASC.EU project Forum with market parties Paris – 18th June
SWE Day-ahead market coupling (Pre- and Post-Coupling project) Paris, 1 st March th IG meeting - SWE ERI.
Milan – 16 th November 2010 Cross Border capacity allocation in 2011: CASC Project.
1/31 Rules for Capacity Allocation by Explicit Auctions within Central West Europe Region (CWE), Central South Europe Region (CSE) and Switzerland Workshop.
CASC.EU SA and its role in Explicit auctions 16/11/2010 CASC.EU SA 1.
Deliverable I.4 Cross-border balancing model among TSOs -BALIT project- (7 th SG SWE, Lisbon, December 3 rd 2013)
SWE Day- Ahead market coupling 25 February 2014 Implementation Group meeting – Madrid Draft.
_________ CASC.EU Intraday Forum _________ ROME, March 13 th, Intraday Forum, ROME, 2012/03/13.
SPOC meeting: Trans European Replacement Reserve Exchange Amine Abada (RTE) 07 th Nov 2013.
Parallel local initiatives – Central West electricity region and the Pentalateral Forum Mr Dominique Woitrin CREG, Belgium The Regional Initiatives: Progress.
21 Kolonaki Square, Athens, T: , F: , E: W: The Energy Community of South.
Actions for establishing a Single Auction Office for CSE 9 th IG Meeting Milan, 18 th July 2008.
FR-UK-IE Regional Initiative Cross-Border Balancing Procurement 26 Nov 2007 John Prime.
Walter Boltz, Chairman ERGEG Gas Working Group 19th Madrid Forum 21 March 2011 Monitoring Report Capacity Allocation and Congestion Management.
How do CEE countries benefit from improved regional cooperation? from the Czech TSO perspective The Regional Initiatives - Progress and Prospects Joint.
Continuous Cross-Border Implicit Intraday Trade Status update XXI. Florence Forum Dec 05th, 2011.
Actions for establishing a Single Auction Office for CSE 8 th IG Meeting Milan, 3rd June 2008.
Long term allocation 2011 Italian borders Central-South and Central-West Regions 2nd Joint RCC meeting Milan, September 28 th, 2010.
Cross Border Intraday on the North Italian Borders Introduction Forum Rome, 13 th March 2012.
1 The regulators’ view on the Central West REM: Emphasis on the completion of existing initiatives Presentation for the Mini-Forum 20 June 2006.
European Commission views on intra-day and balancing markets
Achievements and next steps in the Central-South Region Central-South Region 3rd SG meeting Milan, November 16 th 2010.
1 May 2012CACM Network Code Capacity Allocation and Congestion Management for Electricity Network Code ROME, 15 th May 2012.
Congestion Management on the Italian border for the year 2005
COMMENTS TO THE SOUTH-WEST EUROPE ELECTRICITY REGIONAL ENERGY MARKET Draft detailed action plan version 1, 22 June 2007.
Joint ACER-ENTSOG update on implementation of the Balancing NC 26 th Madrid Forum 16 October 2014.
1 IG Meeting Milan, 18 th July 2008 Cost of Firmness of Capacity.
Gas Regional Initiative North West Region - Draft Framework Guidelines Capacity Allocation Mechanisms BNetzA/CRE Pre-Comitology Meeting Bonn – 26 May 2011.
1 Cross Border Intraday on the North Italian Borders Interim solution 4th Stakeholder Group Meeting Rome, 15 th May 2012.
ERGEG – Stakeholder Meeting Tuesday 14 th November 2006.
Electricity Regional Initiative Central Eastern European Region Convergence & Coherence Sven Kaiser E-Control CEE Stakeholder Group Meeting 7 th November.
SESSION 1. Part 4 IMPORTANCE OF INTRADAY AND ADJUSTMENT MARKETS José Javier González Market Operations Director OMEL 2008 APEX Conference Sydney, October.
Introduction of an Intraday market on the Italian borders for the year 2011 Electricity Regional Initiative – CSE Region Milan, 16/11/2010.
Electricity Regional Initiative Central- South Region Progress with developing regional electricity markets By: Carlo Crea, Secretary General The Regulatory.
INTEGRATION PLATFORM FOR FUI REGION November 22th, 2010 Miroslav Hašek Unicorn Systems.
Development and Implementation of a Coordinated Model for Regional and Inter-Regional Congestion Management Development and Implementation of a Coordinated.
FUI Stakeholder Meeting BritNed presentation Jan-Paul Dijckmans & Jonathan Maughan 4 November 2009.
Interconnector Physical Notification submissions following XBID (Cross Border Intra Day) market implementation; the cross border gate closure definition.
ANRE ROMANIAN ENERGY REGULATORY AUTHORITY Regulation of operation and organization of the electricity day-ahead market with the price market coupling mechanism.
Market coupling for Baltic Cable Paul Giesbertz 5 th Stakeholder Group Meeting Northern Europe ERI 26 May 2010, Copenhagen.
1 page 1 C O U P L E D NWE Day Ahead Project Update FUI IG Mtg – London 13 th September 2010 ENTSO-E Regional Group Northwest Europe C O U P L E D.
SWE Day-ahead market coupling (Pre- and Post-Coupling project) Lisbon, 3rd December th Implementation Group meeting.
Cross Border Intraday on the North Italian Borders Interim solution 4th Stakeholder Group Meeting Rome, 15th May 2012.
SWE Day- Ahead market coupling
Continuous Cross-Border Implicit Intraday Trade Status update
Regulators’ update on Congestion Management and Balancing
Trans European Replacement Reserve Exchange
Draft document – Work in progress
Presentation transcript:

1 Cross Border Intraday on the North Italian Borders Interim solution – Scheduling Forum Rome, 13 th March 2012

2 The nominations gate for using of the intraday capacity are the following: XBID1 : 15: :30 on D-1 XBID2 : 12: :35 on D France-Italian and Swiss-Italian borders Terna will be the single point of contact for the nominations of the intraday capacity. Nominations have to be done only to the scheduling system of Terna. Moreover, due to IT requirements on RTE side, an intraday IT transaction has to be asked by MPs, as stated in RTE Nomination Rules (so called Import/Export Rules). Austrian-Italian and Slovenian-Italian borders Nominations have to be done to both TSOs. Lower value rule will be applied in case of mismatch. XB ID Interim solution on the North Italian Borders - Scheduling Introduction

3  Terna will continue to use the same scheduling system (DAMAS) also for the nominations of the intraday capacity.  The modalities to enter the nominations remain the same:  Web form  Client Application  Web Service  A new Contract Type will be introduced for the Intraday nominations: A07  Dedicated UPV/UCV will be used for the two sessions of Intraday: UPV_TSO I codSDCZ  The Italian Congestion Management Rules will be updated after the approval of the Cross-border Intraday Capacity Auction Rules. XB ID Interim solution on the North Italian Borders - Scheduling Scheduling system of Terna

4 Market Party Entitled TERNAELES Nomination CAI: X01 Capacity: 10 MW PAs CAI: X01 Capacity: 10 MW Matching Registration PAs Nomination CAI: X01 Capacity: 10 MW Auctions CAI: X01 Capacity: 10 MW Matched: 2 MW Nominated: 2 MW Nominated: 5 MW Programming Authorizations (PAs) XB ID Interim solution on the North Italian Borders Exchange flows on Slovenian-Italian border Lower value rule applied in case of mismatch

5 Market Party Entitled TERNARTE Nomination CAI: X01 Capacity: 10 MW PAs CAI: X01 Capacity: 10 MW Registration PAs CAI: X01 Capacity: 10 MW Auctions CAI: X01 Capacity: 10 MW Nominated: 2 MW Programming Authorizations (PAs) XB ID Interim solution on the North Italian Borders Exchange flows on France-Italian border Nominations

6 07:0011:00 12:00 13:00 15:00 16:00 07:00 Nomination Gate: Y/M PTR schedules 12:45 Nomination Gate Day Ahead schedules, Cut Off Time at 13:30 Until 12:45 Nominations to Terna: Daily PTRs with CAI Nominations to Swissgrid: Total netted, as today Until 07:00 Nominations to Terna and Swissgrid: Y/M/LTC PTRs with CAI as today 10:40 Receiving of Daily Programming Authorizations CH IT *Details can be found in New version of the “Technical Balance Group Regulations” of Swissgrid 15:00 Receiving of Intraday 1 Programming Authorizations CH IT 15:30 Nomination Gate and Cut Off Time: Intraday 1 schedules Until 15:30 Nominations to Terna: Intraday 1 PTRs with CAI No Nominations at Swissgrid* 15:45 Receiving of modified or imposed Time Series (with Intraday 1 Nominations made at Terna) from Swissgrid * 15:10 Results from MI 2 Market in IT XB ID Interim solution on the North Italian Borders - Scheduling Scheduling process on Swiss-Italian border - Day D-1

7 10:00 11:0012:00 13:00 10:25 – 10:40 Intraday 2 Auction CH-IT *Details can be found in New version of the “Technical Balance Group Regulations” of Swissgrid 11:40 Receiving of Intraday 2 Programming Authorizations CH IT 12:35 Nomination Gate and Cut Off Time: Intraday 2 schedules Until 12:35 Nominations to Terna: Intraday 2 PTRs with CAI No Nominations at Swissgrid* 12:50 Receiving of modified or imposed Time Series with Intraday 2 Nominations made at Terna from Swissgrid * 12:15 Results from MI 4 Market in IT XB ID Interim solution on the North Italian Borders - Scheduling Scheduling process on Swiss-Italian border - Day D

8  For using Intraday Capacity CH-IT, nominations at Swissgrid are not required  The BG-R will get an modified or imposed Time Series on his day ahead A:A relationship Nominations in an Intermediate Confirmation Report (ICNF) from Swissgrid after receiving the intraday CAS from Terna.  This modified or imposed Time Series has to be included in all further intraday schedule messages sending to Swissgrid for this specific day.  New Version of the “Technical Balance Group Regulations” will be placed on Swissgrid Website in April 2012  This new version of the “Technical Balance Group Regulations” will come into force on the 30th of Mai 2012 at the expected go-live date of this ID CH-IT project XB ID Interim solution on the North Italian Borders - Scheduling Scheduling - Changes for Swiss Balancing Groups

9  APG and Terna are working together to change the matching process of the scheduling on their common border.  The new matching process is based on the SO-SO approach defined by the UCTE (now ENTSO-E) and already in use in the Central-East Europe region.  The intra-day mechanism on this border will start only after the implementation of the new matching process. The date of the go-live is expected by the end of  Further information about the new matching process and the intraday mechanism will be provided in due time before the go-live.  The SO-SO matching approach will be extended in a second step also on Slovenian-Italian border XB ID Interim solution on the North Italian Borders - Scheduling Scheduling on Austrian-Italian border

10 Thank you for your attention !! Questions and answers

11 Back Up

12 XB ID Interim solution on the North Italian Borders - Scheduling Scheduling – Example with modified Time Series, only A:A

13 XB ID Interim solution on the North Italian Borders - Scheduling Scheduling – Example with imposed Time Series, only A:A