ERCOT Emergency Interruptible Load Program Kent Saathoff Ken Donohoo Paul Wattles Mark Patterson Steve Krein PUC Demand Response Workshop Oct. 2, 2006.

Slides:



Advertisements
Similar presentations
INSULATING PRICE RESPONSIVE LOAD FROM RUC CAPACITY SHORT CHARGE Mark W. Smith J. Kay Trostle August 2008 DSWG.
Advertisements

QSE Managers Working Group Meeting Notes 9 April, 2010 Report to WMS 21 April, 2010 David Detelich - Chairperson.
1 Generation Adequacy Task Force Report to TAC April 7, 2005.
February 25, 2011 Demand Side Working Group EILS Update Mark Patterson ERCOT, Manager Demand Integration.
ERCOT Load Forecast Uncertainty V2 August 2, 2006.
ERCOT Emergency Load Response Sam Jones Paul Wattles Steve Krein PUC Demand Response Workshop Sept. 15, 2006.
Enhancing Interruptible Rates Through MISO Demand Response: WIEG Annual Meeting June 19, 2008 Presented by: Kavita Maini, Principal KM Energy Consulting,
1 TAC Review of PRR 650 August 3, Board Charge to TAC Board remanded PRR 650 to TAC for: “an analysis of how to ensure that consumers pay only.
Loads Acting as a Resource Relationships with QSEs and LSEs
Joel Koepke, P.E. ERCOT Operations Support Engineer ERCOT Experiences During Summer 2011.
Floyd Trefny Director of Product Development Future of Demand Response In ERCOT A Presentation to the Workshop – September 15, 2006 Project Number
Intermittent Resources and Demand Response Integration 2007–2016 Long-Term Reliability Assessment Workshop Bill Bojorquez VP, System Planning August 16,
© 2013 McNees Wallace & Nurick LLC October 17, 2013 Robert A. Weishaar, Jr. ON SITE ENERGY – INTERPLAY WITH PJM DEMAND RESPONSE PROGRAMS Harrisburg, PA.
Welcome New York Independent System Operator. (Pre-NYISO) Regulated Market Physical contracts Regulated industry Cost Based System Two Party Deals Bundled.
1 New England Demand Response Resources: Present Observations and Future Challenges Henry Yoshimura Demand Resources Department ISO New England, Inc. Holyoke,
ERCOT Demand Side Working Group Mary Anne Brelinsky Eagle Energy Partners.
1 Welcome to Load Participation Orientation Elev MenWomen Phones Info Presentation and other Load Participation information will be posted at:
1 WMS Report TO TAC March In Brief Three Working Group Reports Three Working Group Reports Three Task Force Reports Three Task Force Reports EILS.
Updated Cost/Benefit Analysis for PRR Part A/S Bidding Proposed Methodology.
“Demand Response: Completing the Link Between Wholesale and Retail Pricing” Paul Crumrine Director, Regulatory Strategies & Services Institute for Regulatory.
Demand Response Workshop September 15, Definitions are important Demand response –“Changes in electricity usage by end-use customers from their.
PRS - RPRS Task Force Status Summary - August 14, PRS RPRS Task Force Status Summary Prepared for WMS and PRS August 2006.
E x p e r i e n c e C o m m i t m e n t SM ERCOT Nodal – Fuel Cost Analysis Verifiable Cost Working Group October 6, 2008.
RPRS ERCOT System Wide Insufficiency Charge Presented at the Technical Advisory Committee June 1, 2006.
Grabbing Balancing Up Load (BUL) by the Horns December 2006.
PJM©2013www.pjm.com Economic DR participation in energy market ERCOT April 14, 2014 Pete Langbein.
SM April Peak Week Operations Review Presentation to ISO Business Issues Committee May 22, 2002.
ERCOT Emergency Interruptible Load Program Paul Wattles Steve Krein WMS Oct. 13, 2006.
Weather Sensitive ERS Training Presenter: Carl Raish Weather Sensitive ERS Training Workshop April 5, 2013.
1 Reliability Deployment Task Force (RDTF Meeting) December 20 th 2011 December 20, 2011.
1 WMS Report TO TAC January In Brief Two Working Group Reports Two Working Group Reports Two Task Force Reports Two Task Force Reports One PRR.
PJM© Demand Response in PJM 2009 NASUCA Mid-Year Meeting June 30, 2009 Boston, MA Panel: Price Responsive Demand – A Long-Term Bargain.
Resource Adequacy Task Force (RATF) Update to WMS June 12, 2013.
DAM Overview: Processes & Tools in the DAM Shams Siddiqi, Ph.D. Crescent Power, Inc. (512) April 2, 2008.
ERCOT Emergency Interruptible Load Service Customer & Stakeholder Workshops July 2007.
Emergency Demand Response Concept Overview and Examples Presented to: ERCOT December 3, 2004 Presented by: Neenan Associates.
Load Resources Negative RRS Bidding in the Nodal Market Credit Working Group January 30, 2008.
09/17/2006 Ken Donohoo ERCOT Peak Day August Initial Settlement Data by Fuel Type.
Operations Report Kent Saathoff System Operations ERCOT.
Floyd Trefny, P.E. Director of Wholesale Market Design Nodal Market Tools to Manage Wind Generation January 29, 2009 Presentation to the Renewables Technology.
Business Case NPRR 351 Floyd Trefny Amtec Consulting Brenda Crockett Champion Energy Services.
Programs/Products that ERCOT Does Not Presently Offer ERCOT Demand Side Working Group New DR Product Options Subgroup Jay Zarnikau Frontier Associates.
1 WMS Report TO TAC April In Brief Two Working Group reports Two Working Group reports Two Task Force Reports Two Task Force Reports BENA presentation.
PRR 705 ERCOT Emergency Interruptible Load Service PRS January 22, 2007.
1 WMS Report TO TAC April 2007 (which is in March)
Overview of Governing Document for Weather-Sensitive ERS Pilot Project Stakeholder Workshop Mark Patterson, ERCOT Staff March 1, 2013.
DSWG Update to WMS 2/9/2011. EILS Procurement Results from 1/31 Business Hours 1 HE 0900 through 1300, Monday thru Friday except ERCOT Holidays; 425 hours.
EILS Discussion February WMS. Charge to WMS from PRS The benefit. The cost based on the EILS PRRs. Changes in Market since April 17, 2006.
Lead from the front Texas Nodal 1 High-Level Overview of draft NPRR implementing PUCT Rule Posting Requirements January 8,
Operations Update ERCOT Board Meeting March 18, 2003.
1 TAC Report to the ERCOT Board November 14, 2006.
Capacity, Demand and Reserves Report Bill Bojorquez May 4, 2007.
ERCOT Monthly Operational Overview (January 2015) ERCOT Public February 15, 2015.
Capacity, Demand and Reserves Report Bill Bojorquez Board of Directors Meeting May 16, 2007.
Emergency Interruptible Load Service Paul Wattles ROS Subgroup Feb. 7, 2006.
Operations Update Kent Saathoff TAC Meeting March 6, 2003.
Update: 30-Minute Emergency Response Service (ERS) Pilot Project Mark Patterson, ERCOT October 7, 2013.
Day-Ahead Market Discussion/Clarification TPTF April 24, 2006.
1 WMS Report To TAC October In Brief One Working Group Report One Working Group Report One Task Force Report One Task Force Report Three Staff.
07/27/2006 Overview of Replacement Reserve Procurement ERCOT Staff PRS RPRS Task Force.
1 TAC Report to the ERCOT Board July 18, TAC Summary 4 PRRs for approval (3 unanimous) 4 PRRs for approval (3 unanimous) 5 Nodal PRRs for approval.
Overview of FIP Issues in the RUC, Verifiable Cost, and other Nodal Market Processes November 12, 2008 VCWG Meeting.
©2003 PJM 1 Presentation to: Maryland Public Service Commission May 16, 2003.
Long-term Solution Task Force Ellis Rankin & Bob Wittmeyer Co-Chairs.
Texas Nodal Program ERCOT Readiness & Transition (ERT) Supplemental Information TPTF January 12, 2009 Kevin Frankeny.
ERCOT Market Education Market Role in Emergency Operations OTS 2016.
TAC Report to the ERCOT Board
Pilot Project Concept 30-Minute Emergency Response Service (ERS)
ERS Procurement Methodology
Intermittent Resources and Demand Response Integration 2007–2016 Long-Term Reliability Assessment Workshop Bill Bojorquez VP, System Planning August.
Presentation transcript:

ERCOT Emergency Interruptible Load Program Kent Saathoff Ken Donohoo Paul Wattles Mark Patterson Steve Krein PUC Demand Response Workshop Oct. 2, 2006

2 2 PUC Demand Response WorkshopOctober 2, 2006 Emergency Interruptible Load Program Thanks for all the feedback!

3 3 PUC Demand Response WorkshopOctober 2, 2006 Emergency Interruptible Load Program We’re back to clear up any questions you may have.

4 4 PUC Demand Response WorkshopOctober 2, 2006 Emergency Interruptible Load Program Purpose of the EILP: To provide ERCOT Operations with an additional emergency tool to lessen the likelihood of involuntary firm load shedding (a.k.a. rolling blackouts)

5 5 PUC Demand Response WorkshopOctober 2, 2006 Emergency Interruptible Load Program What the EILP is: Service provided by loads willing to interrupt immediately prior to the need for involuntary firm load shedding, in exchange for a payment –Deployed only in emergency situations, when no more resources are available at any price from the market or other sources in real time –Part of EECP, deployed just prior to final step (rolling blackouts) –Closest cousins: Black Start and RMR

6 6 PUC Demand Response WorkshopOctober 2, 2006 Emergency Interruptible Load Program What the EILP is NOT: It is not a market-based program in which loads bid into day- ahead or real-time markets. EILP loads: –Cannot bid into Balancing Energy market –Cannot bid into Ancillary Services markets –Cannot participate as price-responsive load –Will not suppress energy prices during an EECP event It is not a resource that is deployed to recover or replace regular ancillary services It is not a resource that will ever be deployed ahead of available market resources It is not a backstop for insufficient planning reserve margins, or a tool to meet long-term capacity needs

7 7 PUC Demand Response WorkshopOctober 2, 2006 Emergency Interruptible Load Program How the need for EILP relates to the Planning Reserve Margin: Low reserve margin is related to this program ONLY as one indicator of an increased likelihood for the need –EILP is less likely to be needed in times of large generation surpluses EILP will NOT impact the reserve margin –Will not be part of the reserve margin calculation –Unlike LaaRs, which are built into the reserve margin calculation as an offset to total peak demand

2006 Post-mortem

9 9 PUC Demand Response WorkshopOctober 2, % Reserve Margins Percentage difference between peak load forecast and available generation/resources 12.5% is the target minimum reserve margin established by ERCOT stakeholders and Board *1,100 MW of mothballed units have been returned to service Over 26,000 MW of new generation added after passage of Senate Bill 7 Since 1999: 2,800 MW retired 8,700 MW mothballed* Future generation is officially counted only if interconnection agreement completed Announced generation without interconnection agreements (excludes wind) 2008 is a major concern

10 PUC Demand Response WorkshopOctober 2, 2006 Aug. 17, 2006 (System peak) Operations Data 64,731 MW 63,259 MW 57,376 MW

11 PUC Demand Response WorkshopOctober 2, 2006 Aug. 17, 2006 (System peak) Operating Capacity 593 MW of forced outages Unit deratings included

12 PUC Demand Response WorkshopOctober 2, 2006 Daily peak loads & temperatures, August 2006

13 PUC Demand Response WorkshopOctober 2, 2006 Projections of Peak Demand through 2011

14 PUC Demand Response WorkshopOctober 2, 2006 Generation unit forced outages & deratings, Summer

ERCOT EILP

16 PUC Demand Response WorkshopOctober 2, 2006 Emergency Interruptible Load Program When the EILP may be needed: Emergencies can occur at any time: –Cold weather months (due to natural gas curtailment & higher forced outages) –Shoulder months (due to unforeseen weather events & large amounts of scheduled maintenance) –Traditional summer peaks –Anytime, as may be caused by: generation outages (scheduled, forced or both) transmission outages beyond likely contingencies extreme weather events multiple simultaneous contingencies

17 PUC Demand Response WorkshopOctober 2, 2006 EILP Cost/Risk relative to other types of Demand Response EILP 4CP LM SOP RRS ISO-NE SW CT REWARD/COST RISK

18 PUC Demand Response WorkshopOctober 2, 2006 Recap… Background –Under normal circumstances, adequate resources (RRS, NSRS, RPRS) are on line or available to deal with most situations –Historical need for additional resources due to abnormal events (usually weather related) Cold weather events can lead to abnormally high load combined with fuel curtailments (Dec. 1989, Feb. 2003) Shoulder month events caused by unusual weather at unexpected times (100º weather on April 17, 2006, with 20% of capacity offline for seasonal maintenance) –When abnormal events occur, additional ERCOT tools could reduce the possibility of a need for involuntary firm load shedding and the associated public health and safety risks

19 PUC Demand Response WorkshopOctober 2, 2006 ERCOT Emergency Operations Operating Procedures to be discussed at TAC 10/6/06 Event/ActionTrigger Operating Condition Notice Physical responsive reserve below 3300 MW ADVISORY Physical responsive below 3000 MW ALERT: Start RMR units, suspend unit testing, deploy RPRS & NSRS Physical responsive below 2500 MW Emergency Electric Curtailment Plan Step 1: Dispatch all generation & DC Ties, issue public media appeal Physical responsive below 2300 MW Step 2: Deploy LaaRs Physical responsive below 1750 MW Step 3: Instruct transmission operators to shed firm load Frequency below 59.8 hz

20 PUC Demand Response WorkshopOctober 2, 2006 ERCOT Emergency Operations A proposed new tool for the ERCOT toolbox Event/ActionTrigger Operating Condition Notice Physical responsive reserve below 3300 MW ADVISORY Physical responsive below 3000 MW ALERT: Start RMR units, suspend unit testing, deploy RPRS & NSRS Physical responsive below 2500 MW Emergency Electric Curtailment Plan Step 1: Dispatch all generation, public media appeal, DC Ties Physical responsive below 2300 MW Step 2: Deploy LaaRs Physical responsive below 1750 MW Step 3: Instruct transmission owners to shed firm load Frequency below 59.8 hz New Step: Deploy EMERGENCY INTERRUPTIBLE LOAD

21 PUC Demand Response WorkshopOctober 2, 2006 EILP Deployment Scenario Emergency Electric Curtailment Plan Event Step 1Step 2‘Step 2A’Step 3 All available generation deployed LaaRs deployed EILP deployed Rolling blackouts (firm load shedding) (Moving MCPE to the price cap during EECP is currently under consideration by stakeholders working on the Nodal transition) Loads respond to scarcity pricing

22 PUC Demand Response WorkshopOctober 2, 2006 Emergency Interruptible Load Program Loads would be deployed: –After all market-based resources have been deployed –Under low frequency conditions –Prior to rolling blackouts Quantity would be based on averting historical firm load shedding events which have occurred in winter peak or shoulder months –Initial proposal: 1000 MW, based on history Need for program and quantity to be procured could be adjusted periodically based on various operating conditions Low probability of deployment Controlled load interruption vs. uncontrolled

23 PUC Demand Response WorkshopOctober 2, 2006 Advantages of the EILP Shedding voluntary load from prepared end-use customers is preferred over involuntary load shedding from unprepared customers Provides ERCOT operations an additional tool in emergency situations Shedding load is 100% effective to maintain balance with generation ERCOT believes that EILP cost will be lower than the societal cost of rolling blackouts

24 PUC Demand Response WorkshopOctober 2, 2006 Potential Program Characteristics Procurement –Loads, through their QSEs, would bid to provide service (similar to Black Start) –Contract is with the QSE –Initial 2-year contract term After that, evaluate annually Possible renewal or re-bid if deployments exceed predefined number of hours

25 PUC Demand Response WorkshopOctober 2, 2006 Potential Program Characteristics Dispatching and Operations –Dispatched By ERCOT thru QSEs –Deployed as a single block after all existing generation resources and LaaRs are deployed Under low frequency conditions but before any firm load shedding –Quick response required (10 minutes or less) –Require interval data metering for measurement and verification But no telemetry or under frequency relay requirement –Limit number of hours to be curtailed in any given year

26 PUC Demand Response WorkshopOctober 2, 2006 Potential Program Characteristics Payment Option 1: CAPACITY & ENERGY –Initial up-front payment based on bids at time of contract award –Pay for performance based on actual load response QSE receives energy imbalance credit equal to MWh delivered (based on validated performance) times the MCPE, or price cap in place –Subject to clawback for underperformance

27 PUC Demand Response WorkshopOctober 2, 2006 Potential Program Characteristics Payment Option 2: Energy-Only with DEFINED PRICE –No up-front payment –Energy-only payment for performance based on actual load response QSE receives a double energy imbalance credit/payment equal to: MWh delivered (based on validated performance) x MCPE price cap in place (guaranteed amount, known in advance) x 2 –Subject to clawback for underperformance –In this case, subscription to the program would be first-come, first-serve (as opposed to competitive bidding) Similar to Standard Offer Programs

28 PUC Demand Response WorkshopOctober 2, 2006 Potential Program Characteristics Payment Option 3: ‘Energy Only’ with COMPETITIVE PRICE –No up-front payment –Energy-only payment under a call agreement –Open bid process (QSEs bid on customers behalf) ERCOT recommends a ‘descending clock auction’ Bids should represent value of lost load –QSEs paid auction clearing price x MWh delivered (based on validated load performance) –Subject to clawback for underperformance

29 PUC Demand Response WorkshopOctober 2, 2006 Potential Program Characteristics Clawback for underperformance Eligible customer must not: –Participate as LaaR –Participate as BUL or voluntary load response… Unless sufficient EILP load is also available ERCOT will verify: –Actual curtailed demand based on review of 15-minute interval data Using actual load from last full interval prior to instruction, minus actual load from next full interval following 10-minute response period –Prior performance under high price periods and 4 CP days No energy payment will be provided (other than energy imbalance credit) if load underperforms –If QSE has received a capacity payment (i.e., under payment option 1), it will be subject to performance-based clawback

30 PUC Demand Response WorkshopOctober 2, 2006 Potential Program Characteristics Allocation (Option 1) –Charged to QSEs representing load on load-ratio share Allocation (Option 2) –Allocate using RPRS methodology (including PRRs 666, 676 & 687) Short-scheduled LSEs bear a higher portion of the cost ERCOT is open to recommendations on how to accommodate self-providing of EILP

31 PUC Demand Response WorkshopOctober 2, 2006 Emergency Interruptible Load Response Potential Program Participants –Large Commercial and Industrial Accounts –Government and Municipal Facilities –Retail Chains –Others??? Program should be open to QSEs serving both competitive and NOIE load

32 PUC Demand Response WorkshopOctober 2, 2006 Potential Paths to Implementation ERCOT-sponsored PRR –A similar program has already failed to pass through subcommittees PUC rulemaking –Similar concept has already been subject to public comment (Project 31972) –Would be difficult to enable program by Spring ‘07

33 PUC Demand Response WorkshopOctober 2, 2006 Some Final Thoughts…. The new energy-only market must attract a robust level of price-responsive load, especially during periods of scarcity of supply –How much load will respond to scarcity pricing? –How much load is even capable of demand response today? ERCOT is anxious to work with the Commission and the market to enable increased demand response –The EILP proposal should not distract from this greater goal

34 PUC Demand Response WorkshopOctober 2, 2006 Questions?