13-12-09 -09:00: Prepared new fill B1: Q X =0.293, Q Y =0.269; lifetime = 25h ✔ B2: Q X =0.297, Q Y =0.267; lifetime = 5h ✗ Strong 50Hz and 100hz lines.

Slides:



Advertisements
Similar presentations
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Advertisements

LHC progress Saturday 2 nd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
LHC progress Thursday 30 th April 2015 Coordination: Mike Lamont, Wolfgang Hofle.
PROFIBUS controller problem (SEU) on cryo valve on DFBMH (600 A circuit RQ6.L7B1/2). Loss of cryo maintain ==> Beam dump. End of fill #1975 after ~2.5.
MD#2 News & Plan Tue – Wed (19. – 20.6.) DayTimeMDEiCMP Tue06: GeV  4 TeV: Ramp for chromaticity - missed A 08:00Ramp down 10: GeV: Large.
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
Weekly summary Summary Week /19.07 M. Lamont & J. Wenninger for the OP team and for all colleagues from the various groups 8:30 meeting 1.
Saturday 6:13 – 15:00 STABLE BEAMS  scans etc. 15:00 moved to ADJUST Squeeze to 2 m in two steps 11 – 5 – 2  remarkably smooth  tertiary collimators.
● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
ION COMMISSIONING REVISITED 1 Thanks to: John Jowett, Walter Venturini. Matteo Solfaroli.
Friday to Saturday 02:00: Machine closed. 09:00: Cryogenics all OK. Preparing pre-cycle. 10:00: Pre-cycle started. 11:30: Pre-cycle finished. 14:00: Beam.
LHC progress Report LHCC Wednesday 23 rd March 2011.
RHIC Run14 Time Meeting. Run14 Status – Apr. 22 Operations running well, 12 stores over the past 7 days with 1 “super store” of 17 hours. Repositioned.
LHC 8:30 meetingEBH 11 Thursday 24 November 2011.
Saturday 7ish – refill for RP set-up 9:15 Going for Roman pot alignment. Stefano is coming. 12:10 TOTEM: Alignment of horizontal RPs B2 finished, short.
● Main goals for week 33: – Luminosity production; – First 150 ns bunch train attempts; – Roman Pots: check movement at 3.5 TeV, with 1b; – Off momentum.
LHC Progress Thursday 29 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
● Morning: Physics fill with 25 bunches: – 07:00: Injection; – 07:25: Start ramp; – 09:00: End of squeeze and stable beams; – Emittances:  x1 = 3.0 
Saturday ● 06:00: Physics fill from the night shift ● 15:00: End stable beam mode: – problems with incorporation of settings for the squeeze ● 16:40:
CONTENT: Beam characteristics and MP concerns BI configuration Operational settings Collimators Planning Shift breakdown Thanks to: P.Baudrenghien, G.Bellodi,
Cryo back at 17:30 Beam back at 19:00 IR2 aperture until ~03:00 Since then no beam from the SPS:  Connector problem on MKD  Connector eroded, needs to.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
04h36: Cryo problem in arc 81. Access. 09h14: Injection.  TI8 injection collimator setup.  Testing new sequence.  New version of vacuum application.
Plan for 500 GeV Development Vadim, Mei. Goals 1.Explore polarization transmission to the 500 Gev CM energy. 2. Inspect the luminosity aspects (with 2.
Monday 19 th March 07:33 Lost (another) beam in the squeeze, beyond 2 m, B2 hits 1/3 resonance. 08:30 Start (another) ramp  Try to correct coupling and.
MD Planning Fri – Sat (26. – 27.8.)
Wednesday 8.9 External crossing angles:
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
-9:00: Test IP transverse adjustment (CMS) and optics verification.
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Saturday 09:40 Stable beams #1369 (56 bunch scheme)
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
Summary of Week 11: 14 – 21 March
Lost at 12:05 to power converter (RTQX2.R1) problem
Friday 31st August & night
Monday Morning – recovery from cryo.
Planning at 5 o’clock meeting Friday
Friday morning 10:30 Optics measurements and corrections.
Thursday :00: Physics fill from the night shift
450 GeV Initial Commissioning with Pilot Beam - Beam Instrumentation
BI cont. *** Summary Matching Monitor test *** We only had ~15minutes of inject and dump, but managed to see a profile with ~9e9 p (!)
Saturday 7th May Sat – Sun night
Summary Thursday h21: Stable beams fill #1303.
Aims for the week Recover from technical stop and precycle at 10A/s
MD#2 News & Plan Tue – Wed (19. – 20.6.)
Collimators: Operations - Baseline Assumptions
Saturday Nov Stop proton operation. Switch back to ions
Monday 8th December Morning used for RF work (IP z, injection), damper noise checks. Stable beams period with LHCb spectrometer OFF – lost beam after.
Thursday – Morning Energy matching at injection with H CODs
Saturday Wire scans at end of fill 1253 B1H : 4.2 B1V : 4.3 B2H : 5 B2V : 7.2 Beams dumped (after ~14h of collisions) Some issues during refill.
Cold compressor speed S45
Wednesday h10: Programmed dump. 07h54: Injection. 200b.
Monday :00 – 15:00 : Stable beams 15:30 : Recover…
Summary for LPC (March 7th, Ralph Assmann)
Monday :15 fill 3523 dumped by BPMs IP6
Summary Tuesday h23: Machine closed. Precycle started.
Wednesday 23/2 Thanks CRYO!!!.
Wednesday h18: 228b fill lost just before start of ramp.
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
LHC Morning Meeting - G. Arduini
Another Immortal Fill….
Saturday 28th 08:17 Fill #1812: Stable beams, peak luminosity ~1.1x1033 cm-2s-1 19:00 Go to adjust for RF-checks; Record fill lumi of 31.7 pb-1 for CMS.
31/3/2010 Difficult day… but at the end stable beams.
15/12/2009 Vacuum interlock in sector 78 understood  out-gassing of a Penning gauge ignited as a result of ionization or dust arcing In conclusion: NO.
Tuesday
Wednesday :35 : Beam lost because of trip of RCBXH3.L1
HI2011 Commissioning Status
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

:00: Prepared new fill B1: Q X =0.293, Q Y =0.269; lifetime = 25h ✔ B2: Q X =0.297, Q Y =0.267; lifetime = 5h ✗ Strong 50Hz and 100hz lines on Beam1 spectrum -13:00: Terminated fill: Beam2 intensity dropped to 1/3 rd (  ) -13:30: Prepared new fill but tried to inject Beam2 first  accidentally took out beam with last Beam1 injection ✗ -14:00: New stable beams with correct tune values: lifetimes 25h and 5h Transverse IP scans for CMS, LHCb and ALICE ✔ -18:30: Terminate fill when Beam2 intensity dropped to 1/3 rd  Try wire scanner with ‘stable beam mode’ on (CMS informed) ✔  Analyzed  -beat measurement at IPs  no preference for a beat ✗  Try tune adjustment (  Q with ‘stable beam mode’ off) ✔ Summary of

Summary of : First fill tunes Strong 50Hz lines in horizontal and 100 Hz lines in vertical tune of Beam1. Not visible in Beam2. These are not synchrotron lines (f rev = kHz, f sync = 63.6 Hz according to RF parameters) Beam1: Beam2:

Summary of : Transverse IP scans CMS: LHCb:

Summary of : Parasitic Wire Scans Beam2 horizontal: Beam2 vertical Comparing beam size from wire with synchrotron light monitor Wire:  x = 0.98mm  y = 3.0mm BSRT:  x = 1.10mm,  y = 2.7mm  ca factor 2 between  y and  x

Summary of : Parasitic Wire Scans Beam1 horizontal: Beam1 vertical Comparing horizontal and vertical beam size from wire measurements: Wire:  x = 0.82mm,  y = 1.5mm  also factor 2 between  y and  x Have not yet measurement at beginning of fill.  not yet possible to conclude or exclude blow up for Beam1

Summary of : Measured  -functions at IPs IPBeam1  x [m] Beam1  y [m] Beam2  x [m] Beam2  y [m] nominal [m] Ratio  x Ratio  y ± ± 19 ± ± / ± ± ± ± 2010 / ± ± 113 ± 19.6 ± / ± ± 29.5 ± ± /

Summary of : Tune Adjustments for Beam2 B1: Q x = 0.293, Q y = 0.269; lifetime = 26h B2: Q x = 0.297, Q y = 0.267; lifetime = 5h B1: Q x = 0.293, Q y = 0.269; lifetime = 25h B2: Q x = 0.312, Q y = 0.305; lifetime = 12h ✔ 1/11 1/7 1/10 1/ 3

Summary of : New Tunes for Beam2 B2: Q X =0.312, Q Y =0.305; lifetime = 12h ✔

:00: Dumped Beam1 before Beam2  no effect on Beam2 lifetime -19:30: New fill new tunes for Beam2: B1: Q x = 0.291, Q y =0.268; lifetime ≈ 10 h B2: Q x = 0.311, Q y =0.305; lifetime ≈ 10 h -22:50: Beam lost due to cryo problem in S12 Cold compressor off in sector 12 estimated time for recovery: 12 hours  10am Sunday  access ALICE  RQ6.L6B1/2 tripped during switch on to STANDBY -07:00: Cryo conditions OK preparing pre-cycle for S12  problems related to QPS Summary of

Summary of : Last 24 hours - currents

Summary of : Last 24 hours – light monitor Horizontal beam size for Beam1 seems to shrink at beginning of fill (1 st hour)  scraping at collimators? Consistent with low lifetime at start of fill (ca. 1h)

Summary of : Last 2 Fills Lifetimes Lifetimes consistently bad (ca. 1h) for first hour of fills

Finish luminosity production at 450 GeV: 16 on 16 bunches? -Tune adjustments Beam1? -Turn separation bumps on IP by IP and look for effect on beam lifetime -Inject with separation bumps on? -Chromaticity adjustments and knob commissioning (end of fill) -Orbit bumps at synchrotron light monitor (end of fill) -fill with high intensity -test  * knobs -Ramp test: Orbit correction at end of ramp and optics verification -MPS and beam dumping system at 1.1 TeV (end of ramp?) -Protection devices and collimation system setup at 1.1 TeV -intermediate energy dumps -abort gap cleaner commissioning Summary of : Plan for the weekend:

bumps at TOTEM Roman Pots -ATLAS aperture H re-check Other miscellaneous work: -finish circuit polarity checks -finish kick response measurements -orbit feedback commissioning -nQPS quench threshold test with beam (bunch intensity < ) Summary of : Plan for the weekend:

Summary of : First fill tunes 1/11 1/7 1/10 1/ 3 B1: QX=0.293, QY=0.269; lifetime = 25h B2: QX=0.315, QY=0.310; lifetime = ??h B1: QX=0.315, QY=0.310; lifetime = ??h B2: QX=0.315, QY=0.310; lifetime = ??h