1 Impact Assessment of Parking Deck and New NPRRs/SCRs Phase 1 February 2011.

Slides:



Advertisements
Similar presentations
Credit Updates Vanessa Spells Credit Work Group ERCOT Public
Advertisements

COPS Update to TAC January 6, Voting Items Three voting items: COPMGRR015, Creating Section 8, ERCOT Settlement and Invoice Process 2. 2.
Protocol Revision Subcommittee Sandy Morris August 5, 2010.
NPRRs NPRR680 Allow QSEs to Self-Arrange AS Quantities Greater Than Their AS Obligation. This Nodal Protocol Revision Request (NPRR) proposes to allow.
May 29, 2014 Technical Advisory Committee (TAC) Update to RMS Kathy Scott June 3, 2014 TAC Update to RMS 1.
1 Business Integration Update to PRS June 2011 Includes: 2011 Project Portfolio Update Parking Deck Impact Assessment 2012 Project Prioritization.
Protocol Revision Subcommittee Presentation to the ERCOT Technical Advisory Committee January 8, 2008.
1 Review of Aging Projects Additional Materials July 16, 2015.
July 30, 2015 TAC Meeting Update to COPS Michelle Trenary August 12, 2015.
2011 Project Prioritization Troy Anderson ERCOT Program Management Office April 2010.
1 Project Update and Summary of Project Priority List (PPL) Activity to Date August 14, 2014.
Protocol Revision Subcommittee Presentation to the ERCOT Technical Advisory Committee April 8, 2010.
Protocol Revision Subcommittee Presentation to the ERCOT Technical Advisory Committee June 4, 2009.
1 Business Integration Update to PRS September 20, 2012.
PMO Update to PRS Troy Anderson Program Management Office April 20, 2007.
March 26, 2015 Technical Advisory Committee (TAC) Update to RMS Kathy Scott April 7, 2015 TAC Update to RMS 1.
Protocol Revision Subcommittee Presentation to the ERCOT Technical Advisory Committee March 4, 2010.
1 Periodic Revision Request Implementation Review – Q January 17, 2013.
Protocol Revision Subcommittee Presentation to the ERCOT Technical Advisory Committee August 7, 2008.
1 Impact Assessment of Parking Deck NPRRs/SCRs/NOGRRs Phase 1 March 2011.
2011 Project Prioritization Troy Anderson ERCOT Program Management Office September 2010.
Protocol Revision Subcommittee Sandy Morris November 3, 2011.
1 Business Integration Update to PRS January 19, 2012.
December 18, 2014 Technical Advisory Committee (TAC) Update to RMS Kathy Scott January 6, 2015 TAC Update to RMS 1.
1 Project Update and Summary of Project Priority List (PPL) Activity July 16, 2015.
TAC Meeting Update. Board Update and TAC Voting Item Kenan Ogelman, Vice Chair of TAC gave the Board Update. It included recommendation that TAC.
1 Project Update and Summary of Project Priority List (PPL) Activity to Date May 15, 2014.
Protocol Revision Subcommittee Presentation to the ERCOT Technical Advisory Committee June 3, 2010.
1 Business Integration Update to PRS January 17, 2013.
1 Project Update and Summary of Project Priority List (PPL) Activity to Date February 21, 2013.
1 Review of Aging Projects July 16, Project Prioritization – Agenda –Discussion Approach –Revision Request Project Funding History –2015 Funding.
Credit Updates Vanessa Spells Credit Work Group ERCOT Public February 18, 2015.
Project Funding Report November 1, Business Integration Update – Agenda –Project Portfolio Updatep Revision Request Funding Reconciliation.
Impact Analysis and Feasibility Study Review – NPRR164, NPRR169 and SCR752 Troy Anderson ERCOT Program Management Office January 15, 2009.
NPRRs 663NPRR Ancillary Service Insufficiency Actions. This Nodal Protocol Revision Request (NPRR) specifies the actions ERCOT will take to ensure sufficient.
1 Business Integration Update to PRS Troy Anderson ERCOT Enterprise Project Portfolio Management May 19, 2011.
Protocol Revision Subcommittee Presentation to the ERCOT Technical Advisory Committee January 6, 2010.
1 Business Integration Update to PRS Troy Anderson ERCOT Enterprise Project Portfolio Management August 18, 2011.
October 3, 2013 Technical Advisory Committee (TAC) Update to RMS Kathy Scott October 16, 2013TAC Update to RMS 1.
1 Project Priority List (PPL) Update Troy Anderson ERCOT Enterprise Project Portfolio Management January 2011.
MISUG Meeting Materials ERCOT 9/07/ MISUG Agenda 9/07/ Antitrust AdmonitionJ. Lavas9:30 a.m. 2.IntroductionJ. Lavas9:35 a.m. 3. Follow up.
QSE Managers Working Group Report to WMS, April 8, 2011 S. Looney, Luminant.
February 27, 2014 Technical Advisory Committee (TAC) Update to RMS Kathy Scott March 4, 2014 TAC Update to RMS 1.
PMO Update to PRS Troy Anderson ERCOT Program Management Office June 17, 2010.
Lead from the front Texas Nodal 1 High-Level Overview of draft NPRR implementing PUCT Rule Posting Requirements January 8,
1 Project Update and Summary of Project Priority List (PPL) Activity February 11, 2016 ERCOT Public.
Protocol Revision Subcommittee Presentation to the ERCOT Technical Advisory Committee September 3, 2009.
1 Business Integration Update April –2011 Project Portfolio Update p. 3-7 Project Portfolio Gantt Chart Recent Developments –Remaining Phases.
1 Business Integration Update to PRS October 18, 2012.
Protocol Revision Subcommittee Tom Burke January 3, 2013.
1 Project Prioritization Review May 14, Approved Revision Requests “Not Started” – Planned to Start in Future Months Revision Request Target Start.
June 26 and July 31, 2014 Technical Advisory Committee (TAC) Update to RMS Kathy Scott August 5, 2014 TAC Update to RMS 1.
Presentation to the ERCOT Technical Advisory Committee July 1, 2010.
1 Project Update and Summary of Project Priority List (PPL) Activity to Date June 11, 2014.
Project Funding Review February 7, Background ERCOT has a $15M project budget in 2013 (same as 2012) –To allow for new additions to the.
ROS Meeting – 06/12/081Texas Nodal Program - TPTF Update Texas Nodal Transition Plan Task Force ROS Meeting Stacy Bridges, ERCOT Thursday, 06/12/08.
Protocol Revision Subcommittee Sandy Morris May 5, 2011.
1 Business Integration Update to PRS Troy Anderson ERCOT Enterprise Project Portfolio Management October 20, 2011.
Protocol Revision Subcommittee Presentation to the ERCOT Technical Advisory Committee May 7, 2009.
PMO Update to PRS Troy Anderson ERCOT Program Management Office May 20, 2010.
MISUG Meeting Materials ERCOT 7/26/ MISUG Agenda 1.Antitrust AdmonitionJ. Lavas9:30 a.m. 2.IntroductionsJ. Lavas9:30 a.m. 3.Market Data Transparency.
February 26, 2015 Technical Advisory Committee (TAC) Update to RMS Kathy Scott March 3, 2015 TAC Update to RMS 1.
TAC Update Kyle Patrick. 2 Nodal ERCOT Program Update –Nodal Market Go-Live (Vote)- vote passed in which TAC certified full nodal systems for Dec 1, 2010.
PMO Update to PRS Troy Anderson ERCOT Program Management Office July 22, 2010.
Project Update and Summary of Project Priority List (PPL) Activity
Initial ERCOT Parking Deck Prioritization Recommendation
Business Integration Update
Project Update and Summary of Project Priority List (PPL) Activity to Date July 17, 2014.
Project Update and Summary of Project Priority List (PPL) Activity
Initial ERCOT Parking Deck Prioritization Recommendation
Presentation transcript:

1 Impact Assessment of Parking Deck and New NPRRs/SCRs Phase 1 February 2011

2 –Phase 1 of Parking Deck Impact Analysis and Cost Benefit Analysis Reminder of Purpose p. 3 Review of Revision Requests in this Phase p. 4 –PRS Suggested Changesp. 5 –IA/CBA Results and Target Implementations p. 6-8 –Endorsement Consideration p. 9 –Appendix Review of Parking Deck Origin and Recent Activities p Guidelines for Assigning Items to the Impact Assessment Phases p. 13 Remaining Impact Assessment Phases p Reconciliation p. 17 Parking Deck and New NPRR/SCR Prioritization – Agenda

3 –REMINDER: In February, we are reviewing the Impact Analysis and CBA documents for the first group of the Parking Deck items (named Phase 1) –Delivery targets for each NPRR/SCR/NOGRR are based on the results of the IA/CBA, resource availability, complexity and other factors –The IAs and CBAs are going through the stakeholder process for eventual consideration by TAC and the Board –Remaining phases of the Parking Deck IAs and CBAs will be reviewed in the stakeholder process in the months ahead Parking Deck and New NPRR/SCR Prioritization – Reminder

4 Parking Deck and New NPRR/SCR Prioritization Phase 1 – First Phase of Impact Analysis & Cost Benefit Analysis –NPRR208: Registration and Settlement of Distributed Generation (DG) Less Than One MW –NPRR219: TSPs Must Submit Outages for Resource Owned Equipment and Clarification of Changes in Status of Transmission Element Postings Includes NOGRR050: Resolution of Reporting Issues Related to NPRR219 –NPRR221: Day-Ahead Market and Real-Time Market Default Allocation Changes –NPRR251: Synchronization of PRR845, Definition for IDR Meters and Optional Removal of IDR Meters at a Premise Where an Advanced Meter Can be Provisioned –NPRR282: Dynamic Ramp Rates Use in SCED –* NPRR285: Generation Resource Base Point Deviation Charge Corrections –NPRR290: ERCOT Publication of DAM PSS/E Files –NPRR293: Requirement to Post PTP Obligation Quantities Awarded in DAM –NPRR302: Correct Fuel Type Language for Mitigated Offer Cap –NPRR303: Requirement to Post PTP Options Cleared in DAM or Taken to Real-Time –SCR760: Recommended Changes Needed for Information Model Manager and Topology Processor for Planning Models Includes SCR759: acLineSegment Name Length Increase in Information Model Manager Schedule –December/January- IA/CBA development –January- Market subcommittee review –February- Market subcommittee endorsement –March- TAC and Board consideration * NPRR285 will go to TAC in February. If the Board approves, ERCOT will seek to expedite the implementation of the curtailment flag portion.

5 Parking Deck and New NPRR/SCR Prioritization Summary of Changes Recommended by PRS on January 27 –Accelerate to TAC and Board in February NPRR285: Generation Resource Base Point Deviation Charge Corrections –Move from Phase 2 to Phase 1 NPRR282: Dynamic Ramp Rates Use in SCED –Move from Phase 3 to Phase 2 NPRR241: Aggregate Incremental Liability (AIL) Calculation and Credit Reports Publish Corrections –Move from Phase 2 to Phase 3 NPRR257: Sync with Nodal Operating Guide Section 9, Monitoring Programs –Move from TBD to Phase 2 NPRR256: Sync Nodal Protocols with PRR787, Add Non-Compliance Language to QSE Performance Standards –Move from TBD to Phase 3 NPRR258: Sync with PRR824 and PRR833 and Additional Clarifications All PRS Recommendations were incorporated into the impact assessment schedule (see appendix for details)

Implementation Recommended –NPRR208 – Registration & Settlement of Distributed Generation (DG) Less Than 1 MW Est. Cost = $5k-$10kTarget Delivery = September 2011(150 market notice required) –NPRR282 – Dynamic Ramp Rates Use in SCED Est. Cost = $30k-$35kTarget Delivery = June 2011 –NPRR285 – Generation Resource Base Point Deviation Charge Corrections Est. Cost = $30k-$40kTarget Delivery = June 2011 Attempting to expedite the curtailment flag portion –NPRR290 – ERCOT Publication of DAM PSS/E Files Est. Cost = $15k-$25kTarget Delivery = August 2011 –NPRR293 – Requirement to Post PTP Obligation Quantities Awarded in DAM Est. Cost = $12k-$15kTarget Delivery = May 2011 –NPRR302 – Correct Fuel Type Language for Mitigated Offer Cap Est. Cost = <$5kTarget Delivery = March 2011 –NPRR303 – Requirement to Post PTP Options Quantities Cleared in DAM or Taken to Real Time Est. Cost = $10k-$15kTarget Delivery = July 2011 –NPRR251 – Sync PRR845, Definition for IDR Meters and Optional Removal of IDR Meters at a Premise Where an Advanced Meter Can be Provisioned Est. Cost = $30k-$50kTarget Delivery = June 2011 –NPRR221 – Automated Default Uplift Invoice Est. Cost = $45k-$65kTarget Delivery = September 2011 Information only item – this is the automation of existing Protocol requirements Impact Analysis Results – Phase 1 Items

7 Implementation Not Recommended at This Time –NPRR219 – Resolution of Alignment Items A33,A92,A106,A150 - TSPs Must Submit Outages for Resource Owned Equipment & Clarification of Changes in Status of Transmission Element Postings Cost to implement greatly exceeds the offsetting labor savings achieved with this project ($565k-$750k) Need to consider alternate approaches or combining with one or more related efforts –NOGRR050 – Resolution of Reporting Issues Related to NPRR219 Not recommended at this time due to its connection to NPRR219 Impact Analysis Results – Phase 1 Items

8 Recommendation TBD –SCR759 – acLineSegment Name Length Increase in Information Model Manager Now combined with SCR760 –SCR760 – Recommended Changes Needed for Information Model Manager and Topology Processor for Planning Models Tabled at TAC These items will be considered in the stakeholder process as language is approved and IA/CBA documents are completed Impact Analysis Results – Phase 1 Items

9 –Suggested subcommittee endorsement language: endorses the Impact Analysis and Cost Benefit Analysis documents for Phase 1 of the Parking Deck impact assessment: –NPRR208 – NPRR219 –NPRR251 – NOGRR050 –NPRR282 –NPRR290 –NPRR293 –NPRR303 In addition, endorses the delivery targets for the revision requests listed above. Items not targeted for delivery in 2011 will be considered in a future year as part of the release planning process. Parking Deck and New NPRR/SCR Prioritization – Endorsement

10 Appendix

11 –PRR799 (approved 2/2009) allowed ERCOT to defer the impact assessment of revision requests requiring system changes that were deemed not needed for Nodal go-live by the ERCOT CEO –The stakeholder approval process proceeded on these items with the understanding that impact assessment would be done at a later time –These deferred items were housed in the Parking Deck and included a Board-approved Priority 29 items were on the Parking Deck at Nodal go-live –All are now Board-approved except SCR760 and NPRR290 –All have Priority assigned except NPRR290 A number of other items were tracked from various sources to provide a place to house other ideas that might result in NPRRs, SCRs, etc. Parking Deck and New NPRR/SCR Prioritization – Origin

12 –In November 2010, ERCOT began planning for the impact assessment of the Parking Deck items –A limited number of items were selected in the first phase of the Parking Deck impact assessment to avoid impacts to Nodal Stabilization resources The first phase of impact assessments is nearing completion Market subcommittee review will take place in February –Further analysis by ERCOT suggests the need for 3 more impact assessment phases –A special PRS meeting was held on January 27 to review ERCOT’s recommendation and the rationale behind it. Market input was provided and incorporated into the recommendation. Parking Deck and New NPRR/SCR Prioritization – Recent Events

13 –Guidelines for Determining Placement of a Parking Deck Item in the Impact Assessment Phases Priority Perceived impact on reliability and the market based on our experience since Nodal go-live Availability of Resources to Conduct Impact Assessments Complexity –Likely Placement in Release 2.0 »Planning begins Q »Implementation expected in 2012 –Dependencies with Other Changes Elimination of Manual Workarounds Parking Deck and New NPRR/SCR Prioritization – Guidelines

14 Parking Deck and New NPRR/SCR Prioritization Phase 2 – Proposed Next Phase of IAs and CBAs –NPRR210: Wind Forecasting Change to P50, Sync with PRR841 –NPRR240: Proxy Energy Offer Curve –NPRR241: Aggregate Incremental Liability (AIL) Calculation and Credit Reports Publish Corrections –NPRR244: Clarification of Other Binding Documents –NPRR256: Sync Nodal Protocols with PRR787, Add Non-Compliance Language to QSE Performance Standards –SCR755: ERCOT.com Website Enhancements Proposed Schedule –February/March- IA/CBA development –March- Market subcommittee review –April- Market subcommittee endorsement –May- TAC and Board consideration

15 Parking Deck and New NPRR/SCR Prioritization Phase 3 – Proposed Next Phase of IAs and CBAs –NPRR131: Ancillary Service Trades with ERCOT May move from Phase 3 to TBD based on outcome of a revision that is being drafted –NPRR181: FIP Definition Revision –NPRR207: Unit Deselection –NPRR222: Half-Hour Start Unit RUC Clawback –NPRR257: Synchronization with Nodal Operating Guide Section 9, Monitoring Programs Due to complexity, IA/CBA development might not finish until Phase 4 –NPRR258: Sync with PRR824 and PRR833 and Additional Clarifications –NPRR260: Providing Access to MIS Secure Area to MIS Registered Users –NPRR272: Definition and Participation of Quick Start Generation Resources –NOGRR034: Rescind Telemetry Performance Calculation Exclusions Proposed Schedule –April/May- IA/CBA development –May- Market subcommittee review –June- Market subcommittee endorsement –July- TAC and Board consideration

16 Parking Deck and New NPRR/SCR Prioritization Phase 4 – Proposed Final Phase of IAs and CBAs –NPRR146: ICCP Telemetry Information Submittals –NPRR153: Generation Resource Fixed Quantity Block Offer Proposed Schedule –June/July- IA/CBA development –July- Market subcommittee review –August- Market subcommittee endorsement –September- TAC and Board consideration TBD –NPRR164: Resubmitting Ancillary Service Offers in SASM Pending resolution of NPRR307 This would conclude the Impact Analysis and CBA development of the Board-approved Parking Deck items

17 Parking Deck and New NPRR/SCR Prioritization – Reconciliation Why are we only being asked to approve 8 IAs/CBAs? There are 13 items in Phase 1 (see slide 4) –Phase 1 contained both Parking Deck NPRRs as well has NPRRs submitted after go-live –Also, some items were expedited and others are still undergoing language review or impact assessment –Reconciliation Items seeking subcommittee approval in February8 Still TBD * (SCR759, SCR760) 2 Already Board-approved or being expedited (NPRR285, NPRR302) 2 Internal item that doesn’t eliminate grey-box language (NPRR221) 1 Total13 * Some of the TBD items will be ready for IA/CBA consideration by PRS in February