The SLAC Phase II Collimator Program 15 June 2005 CERN Team Visit Tom Markiewicz SLAC BNL - FNAL- LBNL - SLAC US LHC Accelerator Research Program.

Slides:



Advertisements
Similar presentations
Coll Eng E Doyle 1/18 LARP Phase II Secondary Collimator RC1 Prototype Engineering Status 6/21/06 Jaw-hub-shaft concept - continued Permanent.
Advertisements

Status of the LARP Phase II Secondary Collimator Prototype 30 September 2013 LHC Collimation WG Meeting Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US.
Yury CHESNOKOV Crystal Collimation workshop, March 7, 2005 CALIBRATION of CMS CALORIMETERS with LHC PROTON BEAM DEFLECTED BY CRYSTAL CALIBRATION of CMS.
Status of the LARP Phase II Secondary Collimator Prototype 14 October 2013 LHC Collimation WG Meeting Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC.
SLAC rotating collimator for HiRadMat beam tests 14 March 2014 S. Redaelli, A. Bertarelli, CERN T. Markiewicz, SLAC US LHC Accelerator Research Program.
LARP Collimator Tasks Summary 28 April 2006 LARP Collaboration Meeting-LBL Tom Markiewicz SLAC BNL - FNAL- LBNL - SLAC US LHC Accelerator Research Program.
The LARP Collimation Program 13 June 2006 LARP DOE Review - Fermilab Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC Accelerator Research Program.
GRD - Collimation Simulation with SIXTRACK - MIB WG - October 2005 LHC COLLIMATION SYSTEM STUDIES USING SIXTRACK Ralph Assmann, Stefano Redaelli, Guillaume.
SLAC Phase II Secondary Collimators 6 October 2005 LARP Collaboration Meeting-St. Charles, IL Tom Markiewicz SLAC BNL - FNAL- LBNL - SLAC US LHC Accelerator.
Beam LARP Rotatable Collimator Mechanical Engineering Discussion 03 October 2008 Phase II CERN ME Video Mtg. Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC.
RFQ Thermal Analysis Scott Lawrie. Vacuum Pump Flange Vacuum Flange Coolant Manifold Cooling Pockets Milled Into Vanes Potentially Bolted Together Tuner.
Apex Target Marco Oriunno, April 23, Design and fabrication by: Marco Oriunno, Dieter Walz, Jim McDonald, Clive Field, Douglas Higginbotham, and.
LHC Phase II Collimator teleconference - 4 March 2008LHC Rotatable Phase II Collimators 1 beam LARP Phase II collimator Progress and Plans 4 March 2008.
LHC Phase II Collimator Compact jaw simulations New FLUKA => ANSYS mapping scheme New 136mm x 950mm jaw –60cm primary collimator –Helical cooling channel.
LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 06 June 2006 No 1 /17 LARP Phase II Secondary Collimator RC1 Collimator Test Program Plan Forward Revised.
Status of Phase II Energy Loss Studies 1. FLUKA with “simple” CERN-provided input file modeling ~40m around primary collimators used for all SLAC studies.
NML High Energy Beam Absorbers and Dump 29-August-2011 Beams-doc-3928.
LER Workshop, CERN, October 11-12, 2006Detector Safety with LER - Henryk Piekarz1 LHC Accelerator Research Program bnl-fnal-lbnl-slac Accelerator & Detector.
SLAC RC Status Report 30 August 2010 LHC Collimation Working Group Meeting Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC Accelerator Research Program.
Work required to have a proposal in June (for discussion) RA, CPM, 15/4/03.
RA CPM 21/2/03 1 Present Approach and Status R. Assmann for the LHC Collimation Team Problem: Al/Cu system would not resist irregular dumps (pre-trigger.
CERN-SLAC meeting June, The LHC Collimator Project LHC Collimators for Phase 1 CERN-SLAC meeting – June, Palo Alto, Ca Alessandro Bertarelli.
D. Still-FNAL/Tevatron HALO '03 Tevatron Collider II Halo Removal System Dean Still Fermilab Tevatron Department 5/21/2003 Motives for the Collider Run.
Collimator and beamline heating External Review of the LHC Collimation Project CERN Wed 30/6/2004.
Design Review of the 1 st Rotatable Collimator (RC1) Prototype Project Overview 15 December 2005 Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC Accelerator.
1 LARP Collimator Engineering E. Doyle 2/3/05. 2 Review: SS Thermal Simulation 150mm OD 25mm wall Simply supported Heat: 1hr beam life, FLUKA results,
Beam Rotatable Collimators as a Possible US Contribution to the LHC Luminosity Upgrade Project 20 June 2008 LARP DOE Review Tom Markiewicz/SLAC BNL - FNAL-
Task List for Phase II Rotatable Collimator Project at SLAC 30 January 2007 CERN/LARP Video Meeting Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC.
Heat Deposition Pre-Evaluation In the context of the new cryo-collimator and 11-T dipole projects we present a review of the power deposition studies on.
4/27/06 1 US LHC ACCELERATOR RESEARCH PROGRAM brookhaven - fermilab – berkeley - slac US LARP Inner Triplet Cryogenics and Heat Transfer LARP Collaboration.
LARP LHC PHASE II SECONDARY COLLIMATOR CD1 REVIEW. - E. Doyle 15 Dec /25 LARP Phase II Secondary Collimator RC1 Review SLAC 12/15/05 Prototype Engineering.
Case study: Energy deposition in superconducting magnets in IR7 AMT Workshop A.Ferrari, M.Magistris, M.Santana, V.Vlachoudis CERN Fri 4/3/2005.
LARP Coll. Video-conf. May 12, '05Phase II Collimator Engineering - E. Doyle1/20 Adapting the NLC Consumable Collimator to LHC Phase II Secondary Collimation.
R. Assmann, June 2009 Operational Experience with the LHC Collimation System R. Assmann, CERN 8/6/2009 for the Collimation Project Team Visit TU Munich.
Phase II Collimators for LHC Upgrade at SLAC - Material Issues E. Doyle 03 Sept /25 Workshop on Materials for Collimators CERN 2007/09/03 Phase.
A. Bertarelli – A. DallocchioWorkshop on Materials for Collimators and Beam absorbers, 4 th Sept 2007 LHC Collimators (Phase II): What is an ideal material.
LARP Rotatable Collimators 19 June 2006 ILC R&D Status Meeting Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC Accelerator Research Program.
LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 30 Jan 2007 No 1 /13 LARP Phase II Secondary Collimator RC1 Collimator Development and Test Program Status.
The LARP Collimation Program 1 June 2005 LARP DOE Review-Fermilab Tom Markiewicz SLAC BNL - FNAL- LBNL - SLAC US LHC Accelerator Research Program.
LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 10 Dec 2007 No 1 /12 LARP Phase II Secondary Collimator RC1 Collimator Development and Test Program Status.
accident deformation – doyle 1/12 Phase II Collimator - Accident Deformation Simulation December 11, 2006.
LARP Phase II Secondary Collimator Status Report SLAC ILC R&D Summary Meeting 24 April 2006 T. Markiewicz/SLAC.
LARP Collimation – Engineering & Analysis
LARP Phase II Secondary Collimator RC1
LARP Phase II Secondary Collimator RC1
LARP Phase II Secondary Collimator RC1
Problem: A kicker failure can deposit 9 x 1011 protons on any metallic
LARP Phase II Secondary Collimator RC1 Review SLAC 12/15/05 RC1 Construction and Test Plan LARP LHC PHASE II COLL REVIEW – RC1.
Joint Meeting SPS Upgrade Study Group and SPS Task Force
Status of energy deposition studies in IR3
Recommendations of 12/16/05 review committee & SLAC response
LARP Collimation – Engineering & Analysis
23 April 2012 Tom Markiewicz/SLAC
Discussion on the TDI impedance specifications
accident deformation – doyle (rev1) 1/8
Phase II Collimators : design status
LHC Collimation Requirements
Cooling aspects for Nb3Sn Inner Triplet quadrupoles and D1
LARP Phase II Secondary Collimator RC-0 and RC-1
LARP Rotatable Collimators for LHC Phase II Collimation
LARP Phase II Secondary Collimator RC-1
Discussion of High Energy Proton Losses in Arc 7
US LHC Accelerator Research Program
Micro Status Report of SLAC Phase II Plan Tom Markiewicz SLAC
RC1 Prototype Conceptual Design Review 15 December, 2005
LHC Collimator – RF Contact Concept (180o wrap)
Engineering Update E. Doyle 5/16/06
Collimator Efficiency Study
US LHC Accelerator Research Program
accident deformation – doyle 1/8
Presentation transcript:

The SLAC Phase II Collimator Program 15 June 2005 CERN Team Visit Tom Markiewicz SLAC BNL - FNAL- LBNL - SLAC US LHC Accelerator Research Program

CERN Team Visit - 15 June 2005 SLAC Phase II Collimator Program - T. MarkiewiczSlide n° 2 / 20 Must move towards detailed design & construction Sept if we are to meet schedule FY 2004:Introduction to project FY 2005:Phase II CDR and set up of a collimator lab at SLAC FY 2006:Design, construction & testing of RC1 FY 2007:Design, construction & no-beam testing of RC2 FY 2008:Ship, Install, Beam Tests of RC2 in LHC May-Oct 2008 run FY 2009: Final drawing package for CERN FY 2010:Await production & installation by CERN FY 2011:Commissioning support RC1=Mechanical Prototype; RC2: Beam Test Prototype Engineer#2 Postdoc#1 Active Manpower: Eric Doyle-Engineering Lew Keller-FLUKA Yunhai Cai-Tracking Tom Markiewicz- Integration Meeting/advice: Tor Raubenheimer Andrei Seryi Joe Frisch Planned hires: Mech. Engineer#2 Postdoc#1 Future Effort: Controls Engineer Designer

CERN Team Visit - 15 June 2005 SLAC Phase II Collimator Program - T. MarkiewiczSlide n° 3 / 20 LHC Collimator Mechanism Concept End and center aperture stops included in same model Helical coolant supply tubes flex, allow one rev of jaw Jaws supported a both ends for stability, allow tilt control Alternative: jaws supported in center thermal deflection away from beam no tilt control Not yet included: 1.Rotary jaw indexing mechanism 2.Loading springs which hold jaws against aperture stops 3.Open aperture power-off mechanism 4.Vacuum chamber, BPMs, movers, etc beam

CERN Team Visit - 15 June 2005 SLAC Phase II Collimator Program - T. MarkiewiczSlide n° 4 / 20 Stop Roller Details Ball screw (stationary) Ball nut (turned by actuator outside vacuum chamber). Thrust bearing Hole for beam passage As shown in current model: aperture range limited to ~ 10mm. This can be improved but this mechanism will not be able to produce the full 60mm aperture. Auxiliary jaw retracting mechanism needed. Also note possible vulnerability of mechanism to beam-induced heating.

CERN Team Visit - 15 June 2005 SLAC Phase II Collimator Program - T. MarkiewiczSlide n° 5 / 20 Geometrical limits due to 150mm rotor, 224 mm Beam Axis Spacing, 8.8cm beam pipe 30mm jaw travel (in red) causes jaw to intersect adjacent beam pipe. No space for vacuum chamber wall. Resolution: 1) smaller jaw diameter 2) vacuum envelope encloses adjacent beam pipe 3) less jaw motion 4) reduce diameter of adjacent beam pipe.

CERN Team Visit - 15 June 2005 SLAC Phase II Collimator Program - T. MarkiewiczSlide n° 6 / 20 ANSYS 3D Time Dependent Thermal Distortion Simulations of 15cm OD, 1.2m long cylindrical jaws Cu, 61C  x=221 um support beam

CERN Team Visit - 15 June 2005 SLAC Phase II Collimator Program - T. MarkiewiczSlide n° 7 / 20 Status of Phase II Collimator Conceptual Design Adequate software in place and MANY studies have been done We do NOT yet have a conceptual design we are ready to start to build Spatial constraints of LHC beam pipes & tunnel –Reduce cylinder diameter from 150mm to 138mm –60mm gap at injection incompatible with center mounted gap adjustor Look into adopting Phase I adjustment mechanism –Adjust length to ~75cm fit into exact Phase I vacuum box Overall heat load and peak temperature –If exclude low Z material because of efficiency there is no magic material or config –Still concentrate on Cu because of high thermal conductivity –Maximum permissible peak temperature still under discussion Deformation under 10sec 4E11 p/s loss >> 25 um –Non-azimuthal cooling scheme to minimize  T across cylinder –Break the first secondary into two unequal length pieces of perhaps different materials –Grooved “expansion slots” to limit deformation –Adjust gaps of the first carbon & metal secondary to reduce heat load while maintaining efficiency with remainder of secondary system –Deformation tolerance relaxed to ~> 100 um if jaws expand AWAY from beam Recent concept for adjustable “stops” proposed –28 of 30 Phase II collimators will not have a heating problem Keep C-C in hot position and design remainder for ~10% DC heat load

CERN Team Visit - 15 June 2005 SLAC Phase II Collimator Program - T. MarkiewiczSlide n° 8 / 20 Feb CERN Calculations show 130kW p/s) in first Cu Secondary Jaws at 10 sigma “Pencil” Beam with 80:5:5:10 loss model Only 1 TCSH in current (v6.5) collimation configuration Study E_dep vs. jaw Z alloys, coatings, etc.

CERN Team Visit - 15 June 2005 SLAC Phase II Collimator Program - T. MarkiewiczSlide n° 9 / 20 Lew Keller Uses CERN FLUKA input deck varying material, collimator gap and loss distribution for 25 x 80mm jaws

CERN Team Visit - 15 June 2005 SLAC Phase II Collimator Program - T. MarkiewiczSlide n° 10 / 20 Primary Collimator (source) TCSM.B6.L7 Jaws at 7 sigma TCSM.B6.L7 Jaws at 10 sigma Copper Al_2219 Copper Al_2219 TCP.D6.L7 (TCPV) TCP.C6.L7 (TCPH) TCP.B6.L7 (TCPS) Power Deposition on First Secondary Collimator in 12 Min. Lifetime (kW per jaw) Notes: 1. Collimator data, ray files, and loss maps from LHC Collimator web page, Feb Must add contribution from direct hits on secondary jaws. Sensitivity to aperture and to source of halo: H, V, or S

CERN Team Visit - 15 June 2005 SLAC Phase II Collimator Program - T. MarkiewiczSlide n° 11 / cm Missteered beam (9E11 protons) on secondary Jaw Copper Jaw Cross section at shower max. Copper Fracture temp. of copper is about 200 deg C What is the damage area in a missteering accident? Assumed Damage threshold seems inconsistent with FNAL experience

CERN Team Visit - 15 June 2005 SLAC Phase II Collimator Program - T. MarkiewiczSlide n° 12 / 20 Copper Similar result was obtained by Ralph A  mann Yunhai Cai Study of Material for Secondary Collimators High Z materials improve system efficiency Copper being considered because its high thermal conductivity Available length is about 1 meter Achievable efficiency is about 3.5x10 -4 at 10  As Sixtrack program adds absorbers/tertiary collimator we expect ~x10 improvement

CERN Team Visit - 15 June 2005 SLAC Phase II Collimator Program - T. MarkiewiczSlide n° 13 / 20 Quench Protection Sets Maximum Current Given Collimator System Inefficiency 7.6E6 7 TeV 12min 2E-5 Desired 2E-4 Phase II (assumes 1m Cu) 11E-4 Phase I Nom. I IntensityInefficiency 4E11 p/s x 2E-5 = 8E6 p/s corresponds to stated quench limit in Q3 given maximum dQ/dV

CERN Team Visit - 15 June 2005 SLAC Phase II Collimator Program - T. MarkiewiczSlide n° 14 / 20 IR7 Collimator Layout Beam Direction Primary Collimators Hard Hit Secondary Collimators

CERN Team Visit - 15 June 2005 SLAC Phase II Collimator Program - T. MarkiewiczSlide n° 15 / 20 Possible Path to Immediate RC1 Prototype: Leave TCS#1 Carbon-Carbon, Remainder Cu Inefficiency 1C-10CuAll Cu Horizontal2.84x x10 -4 Vertical3.63x x10 -4 Skew 4.57x x10 -4

CERN Team Visit - 15 June 2005 SLAC Phase II Collimator Program - T. MarkiewiczSlide n° 16 / 20 Consider concentrating E_dep in Front Part of Jaw by using Phase I Carbon SC as “preradiator” or going to W: hope to isolate heat in short enough jaw that deformation is minimized

CERN Team Visit - 15 June 2005 SLAC Phase II Collimator Program - T. MarkiewiczSlide n° 17 / 20 Material Comparison for SS 90kW & Transient 450kW Low Z good for heating; bad for efficiency Short bends less than longer LHC Thermal Deflection Spec. is 25um 90kW ~OK 450kW-10s Not OK Note: Green shading: meet our suggested alternative spec of 50um for SS and 200um (10s) for the transient.

CERN Team Visit - 15 June 2005 SLAC Phase II Collimator Program - T. MarkiewiczSlide n° 18 / o & limited arc coolant channel concepts Limited cooling arc: free wheeling distributor – orientation controlled by gravity – directs flow to beam-side axial channels regardless of jaw angular orientation. Far side not cooled, reducing  T and thermal distortion. 360 o cooling by means of a helical channel. Lowers peak temperatures but, by cooling back side of jaw, increases net  T through the jaw, and therefore thermal distortion. Could use axial channels.

CERN Team Visit - 15 June 2005 SLAC Phase II Collimator Program - T. MarkiewiczSlide n° 19 / 20 Grooved Cylindrical Jaw Reduces Deflection Parameters 150mm O.D., 25mm wall, 120cm long Grooves: 10mm deep, 50mm spacing 10kW heat, evenly distributed 45 deg cooling arc CaseTmax °CDeflection (um) CuJaw edge ref axis ref straight59.533~100 grooved59.515~74

CERN Team Visit - 15 June 2005 SLAC Phase II Collimator Program - T. MarkiewiczSlide n° 20 / 20 Goals of Meeting How to move from current status to point where we can begin a design we can build and that incorporates all LHC constraints and as much of Phase I infrastructure and hardware as possible Discuss what the testing program of first prototype should be and if/how we can use CERN testing hardware here at SLAC Better understanding of average and peak heat loads and damage potential for each of the 32 metals secondary collimators Better understanding of which collimators are most important to achieving 2E-5 inefficiency in context of beamline fully equipped with tertiary collimators (8.4 sigma) and absorbers (10 sigma)