Mod 116B Steve Rose - on behalf of RWE Trading. 2 Background Mod 116 B was raised after discussion with a number of shippers about aspects Mod 116 which.

Slides:



Advertisements
Similar presentations
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Advertisements

Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Review Group 0166 Review of Necessary Reform of NTS Offtake Arrangements 20 th September 2007 Beverley Grubb SGN.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
UNC Mod 485: CMP-LTUIOLI Progress Update 3 April 2014.
Exit Reform Review Transmission Workstream 07 January 2010.
UNC Modification Proposal 0116 Reform of the NTS Offtake Arrangements Transmission Workstream 5 th October 2006.
Operating Margins. 2 Competitive Provision of Operating Margins Change to National Grid Gas’s Transporter Licence which:  Introduced Special Condition.
Enduring Offtake Arrangements including an Off-Peak Interruptible Service Peter Bolitho.
Mod 0445 – Amendment to the Arrangements for Daily Metered Supply Point Capacity Ofgem Direction to Provide Further Evidence National Grid Distribution.
1 Review Group 166 Review of necessary reform of NTS Offtake Arrangements Exit reform from an interconnector perspective Avian Egan 20 th September 2007.
Capacity trade and transfer mechanism and the next AMSEC auction Nienke Hendriks Head of Gas Transmission Policy, Enforcement and Compliance 9 May 2007.
1 CODE MODIFICATION PROPOSAL No 0243 Amendments to the process for initialisation of Enduring NTS Exit (Flat) Capacity at the Moffat NTS Exit Point Presentation.
“Introduction of a New Shipper Obligation in Relation to the Procurement of Gas Below the Gas Safety Monitors” Transmission Workstream 4 th Jan 2007 Chris.
Capacity Release Processes and Investment Planning Transmission Planning Code Workshop 2 1 st May 2008.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Mod 214 – Reservation of firm NTS Exit Capacity at new NTS Exit Points in the transitional period Steve Rose.
Transfers and Trades Transmission Workstream
Mod 0333: Update of default System Marginal Prices Review Group August 2010 Transmission Workstream 07/10/2010.
Discretionary Release of Non Obligated NTS System Entry Capacity Transmission Workstream 1st May 2008.
Modification Proposal 0246: Quarterly NTS Entry Capacity User Commitment Chris Shanley.
UNC (Urgent) Modification Proposal 0044: “Revised Emergency Cash-out & Curtailment Arrangements” UNC Transmission Workstream 11 th August 2005.
UNC Proposal 329 – Review of Industry Charging & Contractual Arrangements - DM SHQs and DM SOQs Joel Martin – 21/09/10.
Classification: Statoil Internal Status: Draft Mod 156/156a Questions regarding the proposals…
Delivering Connections and Capacity RIIO-T1 and associated commercial changes - Summary June 7th 2012.
Enduring NTS Offtake Arrangements Transmission Workstream 5th September 2006.
DNPC06 LDZ NEC Charges Denis Aitchison 25 th January 2010.
Review Group Modification Proposal Introduction of Enduring NTS Exit Capacity Arrangements.
Review Group 221 Session 3: 13 October Introduction  During this presentation we will seek views on the following questions.  What should the.
DNPD04 LDZ Exit Capacity Charges- Discussion Report Denis Aitchison 27 th July 2009.
Force Majeure - Capacity Transmission Workstream 2 July 2009.
Mod 166 Review Group Incremental Exit Capacity at New and Existing Exit Points.
Mod Clarifications Transmission Workstream 6 August 2009.
11 User Pays User Committee 11th January Agenda  Minutes & Actions from previous meeting  Agency Charging Statement Update  Change Management.
Entry Capacity Trading Transmission Work Stream, 5 April 2007.
Enduring Exit Regime & NTS Risk Management Processes Offtake Arrangement Workstream – OAD Section I Review Group 316.
Transmission workstream 6 April Overview of TPCR Third Consultation UNC transmission workstream – 6 April Mark Feather.
Exit Capacity Release Methodology Statement - ExCR Transmission Workstream – 5 th March 2009.
Review Group -140 Thoughts on additional information requirements.
MOD0164 Bi-Directional Connection Point Overrun Charge Calculation Stuart Waudby (Centrica Storage Ltd.)
Exit Capacity Release Methodology Statement - ExCR Transmission Workstream – 5 th Feb 2009.
UNC0376A - Increased Choice when applying for NTS Exit Capacity – User Pays initial thoughts Review Group August 2010 Transmission Workstream 01.
Transfers and Trades Special Transmission Workstream
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Review of the UNC Post-emergency Claims Arrangements Strawman February 2009.
Mod 376: Increased Choice when Applying for Enduring NTS Exit Capacity Jeff Chandler - 5 th May 2011 Transmission Workgroup - Elexon 1.
DN Interruption Reform Transmission Workstream Mark Freeman 5 th April 2007.
Exit Capacity User Commitment – Transmission Workstream update
Transmission Workstream 4th July 2007
Transmission Workstream, 6 August
0350 – Combining the NTS entry capacity and exit capacity credit checks Chris Shanley.
DNPC06 From 1 October 2012 the DNs will pay the NTS Exit Capacity charges to the NTS and recover the cost from shippers DNPC06 put forward for consultation.
7th July 2011 Transmission Workgroup - Elexon
Publication of Zonal Flex Data
COR1360 NTS Exit Reform (Mod 0195AV) UK-Link Committee 11th June 2009
0350 – Combining the NTS entry capacity and exit capacity credit checks Chris Shanley.
EU/GB Charging Project – Delivery Timescales
MOD National Grid NTS Initiated Flow Swaps
Simon Trivella –5th May 2011 Transmission Workgroup - Elexon
Modification Proposal 0101 – “Amendment to demand forecasting timings in relation to the Gas Balancing Alert”
Transmission Workstream – Partial Assignment
UNC Transmission Workstream 7th December 2006
Proposed Transitional Gas Exit Arrangements
Transmission Workstream 2nd December 2010
Entry Overrun Calculation
Workgroup meeting October 2014
Stefan Leedham Transmission Workstream 2nd November 2006
Exit Overruns in the Enduring Regime
Transmission Workstream 05 November 2009
Presentation transcript:

Mod 116B Steve Rose - on behalf of RWE Trading

2 Background Mod 116 B was raised after discussion with a number of shippers about aspects Mod 116 which were unduly complex and which increased shipper risk. If Ofgem decide Mod 116 does better facilitate the achievement of the relevant objectives they can then consider if Mod 116B does so more strongly. If Ofgem decided that Mod 116 does not better facilitate the achievement of the relevant objectives then neither should Mod 116B. Support or qualified support of Mod 116B does not stop Users from supporting Mods 116 and/or Mod 116C.

3 Section 1 A User may not offtake gas at a rate of offtake which exceeds or is less than the OPN Prevailing Offtake Rate by more than the relevant tolerance specified in Network Exit Provisions NExA tolerance = 3%. DN tolerance = 10% at an individual offtake and 3% at all offtakes in an LDZ 1.5% overall tolerance not sufficient to take account of a Users NExA flow entitlement and Users could incur an overrun by complying with their NExA as shown in this example.

4 Section 2 New Firm Supply Points commissioned prior to the Enduring Arrangements to have an Initial Prevailing NTS Exit (Flat) Capacity holding based on their first registered capacity. Calrification on latest date for reducing Initial Prevailing NTS Exit (Flat) Capacity. Distinction made between release/reduction of Prevailing NTS Exit (Flat) Capacity at new and existing exit points. –Developers (Users and non UNC parties) shall use reasonable endeavours to make a user commitment in the July window. –NG shall use reasonable endeavours to make new capacity available within the desired timescales if user commitment given outside July window. – NG shall use reasonable endeavours to make new capacity available from a date other than the start of the Gas Year provided user commitment is given.

5 Section If a User does not rely on the annual auctions to secure NTS Exit (Flexibility) Capacity and re-submission of its OPN reduces the amount of capacity required (based on its original OPN) the allocated capacity should be reduced accordingly. Latest time for NTS Exit (Flexibility) Capacity between Exit Zones to be aligned with initial OPN submission time. Transfer and assignment of NTS Exit Capacity (Flat and Flex) to be a matched process prior to acceptance to avoid erros being automatically accepted (as per Entry and NBP). No changes to sections 5 & 6

6 Section 7 Reference to NTS Exit (Flexibility) Commodity Charge deleted 1.5% tolerance increased to 3% in overrun calculation NTS Exit (Flexibility) Overruns only to be incurred if there is an aggregate overrun and the day has been declared a “flexible constraint day” Relief from overrun charges arising from intertrips or forced outages in the same way as for NTS Exit Capacity constraints management actions taken by NG. NTS Exit Capacity neutrality arrangements to be split into separate pots for flat and flex costs/revenues. Flat neutrality to be smeared based on proportion of national flat capacity. Flex neutrality to be smeared based on proportion of area flex capacity.

7 Sections No changes to Section 8 NG to be required to publish the following information once the enduring arrangements take effect: –Actual utilisation of NTS Exit (Flexibility) Capacity in each zone for each gas day (by 11:00 hrs D+1) –NTS Exit (Flexibility) Overrun quantity and charges for each gas day in e NTS Exit Zone NG to be required to publish the following information w.e.f. 1/7/07: –The sum of the NTS Exit (Flexibility) Capacity expected to be utilised in each zone based on the initial OPN submissions D-1 and subsequently fore each hour within the gas day

8 Advantages Potential to lessen the extent of User system build by lessening Users exposure to overrun charges and flex commodity charges. Avoids the rigidity of developers having to signal new capacity requirements within an annual July window and for an October start. Soft landing approach to such fundamental reform Avoids overrun exposure caused by intertrips/forced outages Targets flex neutrality cost/revenue only to User’s who utilise flex (as opposed to flat capacity) and only at zones where they offtake gas. Provides information on flex utilisation in advance of the first opportunity Users have to acquire it to better inform their bidding strategy.