PRR835 – Reactive Power Capability Requirement

Slides:



Advertisements
Similar presentations
Wind Turbine Session 4.
Advertisements

Testing Workshop: Reactive Capability Testing
ERCOT VRT Study, Phase I ERCOT ROS Meeting December 10, 2009.
Connection of Wind Farms to Weak AC networks – ERCOT Experience and Challenges Shun-Hsien (Fred) Huang ERCOT System Planning CIGRE WG B4.62 Meeting June.
Wind farms with HVDC delivery in Load Frequency Control Lingling Fan April 22, 2010.
Raine Cotton  Registered DG settlement is in accordance with Protocol Section as Real-Time Energy Imbalance at a Load.
1. 11/26/2012: NERC Board of Trustees adopted CIP v5 CIP thru CIP CIP and CIP Version 5 Filing FERC requested filing by 3/31/2013.
System Voltage Planning Brian Moss PD / Transmission Planning Transmission Planning Overview October 30, 2007.
System Strength Discussion
Technical Advisory Committee December 6, 2010 Summary of the CREZ Reactive Study Warren Lasher Manager, Long-Term Planning and Policy.
1 New Resource Qualification Testing Sandip Sharma Supervisor, Operations Analysis New Generation Information Forum ERCOT Public November 4, 2014.
Presentation to WECC TSS May 8, 2015
A Partial Interim Report To WMS Guidance on Implementing Protocol Implementation Plan (PIP) 102 Reactive Power Task Force.
2001 South First Street Champaign, Illinois (217) Davis Power Consultants Strategic Location of Renewable Generation Based on Grid Reliability.
1 Voltage Stability and Reactive Power Planning Entergy Transmission Planning Summit New Orleans, LA July 8, 2004 Entergy Transmission Planning Summit.
RenewElec October 21, 2010 Robert Nordhaus, David Yaffe Van Ness Feldman 1050 Thomas Jefferson Street, NW Washington, DC (202) FERC’s.
PLWG Report to ROS July 9, PGRRs needing vote PGRR043 – FIS Scoping Amendment – PGRR043 moves the Subsynchronous Resonance (SSR) Study out of the.
Review of BPA Voltage Control Conference
Review of progress and future work SQSS Sub Group 2 August 2006 DTI / OFGEM OFFSHORE TRANSMISSION EXPERTS GROUP.
Determine Facility Ratings, SOLs and Transfer Capabilities Paul Johnson Chair of the Determine Facility Ratings Standard Drafting Team An Overview of the.
Costs of Ancillary Services & Congestion Management Fedor Opadchiy Deputy Chairman of the Board.
Houston Area Dynamic Reactive Project March 11,
Warren Lasher Director, System Planning October 4, 2014 Our Energy Future.
Long Term Study Task Force Update Transmission Study Practices and Methodologies April 5th,2011 LTS.
RELIABILITY and RENEWABLES: Two Case Studies Using the SuperOPF Tim Mount Department of Applied Economics and Management Cornell University
Overview of the North American and Canadian Markets 2008 APEX Conference in Sydney, Australia October 13, 2008 Hung-po Chao Director, Market Strategy and.
RTWG Report to TAC August 5, 2010 Howard Daniels.
Workshop: Reactive Power Testing:
Generator Test Data, Generator Capability Curve, and NPRR 366 Terms March 14, 2012 Mike Noth & Bracy Nesbit 1.
1 TRANSMISSION SYSTEM OVERVIEW NETWORK OPERATING COMMITTEE April 17, 2007 New Mexico Transmission System Overview.
1 Mid-Continent Area Power Pool Wind Integration Studies Edward P. Weber August 16, 2007.
August 17, 2012 Solar PV Inverters Anuj Dixit Planning Engineer Resource Integration RPG Meeting.
ERCOT PUBLIC 5/20/ RTP Inputs and Assumptions May 20, 2014.
VRT Study Update José Conto ERCOT System Planning.
Vestas.com Wind Power Plant Dynamic Reactive Power “Hybrid” Solutions to meet ERCOT Reactive Power Capability Requirements Presented at ERCOT ROS Meeting,
NPRR425 - Creation of a WGR Group for GREDP and Base Point Deviation Evaluation and Mixing Turbine Types Within a WGR Art Deller, P.E. RARF Workshop 8/29/13.
Emerging Technologies Integration in ERCOT 2012 ERCOT Operations Seminar Mark Bruce Principal Stratus Energy Group.
Regulation Energy Management Overview CPUC Energy Storage Workshop March 9, 2011.
ERCOT Wind Survey Leo Villanueva. Abilene Mc Camey Big Spring.
Electric Reliability Council of Texas (ERCOT) A Success Story… In Progress Ingmar Sterzing United States Association of Energy Economics (USAEE) Pittsburgh.
Operational Issues & Risks ERCOT Operations Planning August 22, 2008.
May 11, 2012 RPG meeting YTP Scope and Process – RPG Comments.
Integrating Wind Energy Capabilities of Wind Power Plants Mark Ahlstrom Wind Energy: A Good Citizen of the Electric Grid Four Corners Wind Resource Center.
Grid Reliability Metrics by Jim Dyer Electric Power Group, LLC January 29, 2004 Washington, DC Transmission Reliability Research Review.
Operating Guide and Planning Guide Revision Requests Blake Williams, ROS Chair September 13, 2012.
Transmission Voltage Management Ross Owen Oncor Electric Delivery.
ROS July 10, 2008 Meeting WOTF Update on ROS Action Plan Summary: EECP Step #2 (Feb.26 th, 2008) Mark Garrott WOTF Chair.
ERCOT Public 1 Project Panel 1 Dan Woodfin Director, System Operations August 15, 2014.
ERCOT Wind Survey Leo Villanueva. Abilene McCamey Big Spring.
What’s happening in Spain? Access to the grid request of STE projects by Oct MW.
Panhandle Renewable Energy Zone (PREZ) Study
1 PRR #409 Voltage Support Service from Generating Resources Timeline Date Received 4/25/2003 Date Posted 4/28/2003 Comments Due 5/19/2003 PRS Review Date.
ERCOT Transmission Planning Process Overview and Recommendations November 6, 2002.
1/14/10ERCOT ROS / CREZ OGRR1 Why is CREZ Unique? 15 GW of intermittent generation when ERCOT load is less than 30 GW 5000 miles of 345 kV circuits with.
Voltage Control Brad Calhoun Consultant, Sr. Trainer Spring 2016.
03/06/2008 TAC CREZ Transmission Optimization (CTO) Study Update Dan Woodfin Director, System Planning.
Overview OF MULTI Mega Watt WIND TURBINES and wind parks
2016 LTSA Update Doug Murray 6/21/2016. Agenda Introduction Scenario Retirement Process Scenario Summary Results Appendix.
Impact of not including proposed generators lacking RARF data in the planning models Planning Guide Section 6.9 Issues February 17, 2016.
October 15, 2012 PV & Storage Workshop ERCOT’s Interconnection Process John Adams Principal Engineer.
Abilene Mc Camey Big Spring. Far West Abilene Area All the values are based on returned ERCOT survey results Total number of Wind Powered Generation.
Renewable Technology Working Group (RTWG) Report to TAC February 4, 2010 Henry Durrwachter.
Barrilla Junction Area Transmission Improvements Project
IG BASED WINDFARMS USING STATCOM
Columbia Grid Wind Integration Study Team Dynamic Transfer Capability Studies Update 9/10/09.
Reactive Power Task Force
Oncor Electric Delivery Company LLC
ECEN 460 Power System Operation and Control
DEC System Voltage Planning - June 2018
Mid-Continent Area Power Pool
Presentation transcript:

PRR835 – Reactive Power Capability Requirement Peter Wybierala Regional Director of Transmission & Interconnects Presentation to the ERCOT Reliability and Operations Subcommittee (ROS) October 15, 2009

Ancillary Services Section 6.5.7 needs to be revised The current ERCOT Protocol on reactive power capability requirements is obsolete Ancillary Services Section 6.5.7 needs to be revised All generators are not the same Synchronous generators have their own inherent reactive power characteristics The reactive capability of wind generators is evolving Early machines were Type 1and 2 induction generators with no reactive capabilty Type 3 machines consist of a Doubly Fed Induction Generator (DFIG) Type 4 machines employ a full bridge converter design coupled to either an induction or synchronous machine Other technologies such as solar and energy storage will have their own unique characteristics The imposition of a “one size fits all” approach to reactive power capability requirements will result in economic inefficiency and create barriers to entry for the adoption of new technologies

Ancillary Services Section 6.5.7 needs to be revised Not only is the current ERCOT Protocol obsolete...it’s also ambiguous Ancillary Services Section 6.5.7 needs to be revised Protocol 6.5.7.1 (2) states that... “Generation Resources required to provide VSS....shall have and maintain a URL which has an over-excited (lagging) power factor capabilty of ninety-five hundredths (0.95) or less and an under-excited (leading) power factor capabilty of ninety five hundredths (0.95) or less, both determined at the generating unit’s maximum net power to be supplied to the transmission grid and at the transmission system Voltage Profile established by ERCOT, and both measured at the point of interconnection to the TDSP.” Does “shall have and maintain” mean going forward in time or does it mean over the output range of the unit? PRR830, if adopted, would require a wind generator interconnected after February 17, 2004 to maintain a URL over the output range of the unit.

Wind turbine generator technology continues to evolve Type 1 and 2 induction generators – no inherent reactive production capability Lagging MVar MW Leading Type 3 doubly fed induction generators - +/- 0.95 pf (typical of GE 1.5 MW machines) Lagging +.95pf MVar MW Leading -.95pf Type 4 machines – reactive capability comparable to synchronous generators (typical of Siemens 2.3 MW machines and comparable to conventional synchronous units) Lagging MVar MW Leading

PRR835 does several things... It carves out a separate section for the reactive power requirements of Wind Generating Resources and requires a +/- 0.95 power factor range as the minimum requirement It provides for the imposition of additional reactive requirements consistent with PRR830 where it can be demonstrated through a system impact study that such capability is required to ensure safety and reliability PRR835 avoids requiring generators already interconnected to make costly investment in additional reactive capability where it is not justified PRR 835 exceeds FERC Order 661-A requirements

Comparision of PRR835 to PRR830 and FERC Order 661-A MVar Lagging Leading MW +.95pf -.95pf URL Minimum Maximum FERC Order 661-A Adopts +/- 0.95PF range as the maximum requirement Requires wind plants to maintain the required power factor range only if the Transmission Provider shows, through the System Impact Study, that such capability is required of the plant to ensure safety and reliability PRR830 Adopts the URL measured at +/-0.95 PF and maximum net MW output Requires URL over the full operating range of the plant PRR835 Adopts +/-0.95PF as the minimum reactive capability May require URL over the full operating range of the plant only if the Transmission Provider demonstrates it is needed to ensure safety and reliability through a System Impact Study

Transmission Line Example PRR830 will result in redundant and excessive reactive capability where it is not needed Transmission Line Example POI 3 2 1 Equivalent Transmission Line Representation Transmission Owner must provide shunt reactors to offset line charging when wind is calm and generator is not generating PRR830 would have the Generator install an additional shunt reactor to meet its URL requirement for leading reactive capability over its range of output Inherent Generator reactive capability MVar Lagging Leading MW +.95pf -.95pf URL Minimum PRR830 will result in the wasteful installation of redundant reactive resources.

Transmission Line Example PRR835 ensures system safety and reliability without mandating investment in reactive capability for providing VSS where it is not needed Transmission Line Example Generator shunt reactor (or capacitor) would not be required to meet its URL requirement for leading (or lagging) reactive capability over its range of output unless shown to be required by the System Impact Study

NextEra has engaged the services of Siemens-PTI to assess the current need for additional reactive resources in Western ERCOT Study Assumptions Reference case from ERCOT 2010/2011 Winter off-Peak (09/17/2009 update) 39,569 MW total generation; 3,719 MW wind generation (9.4%) Wind farms represented per ERCOT’s modeling Reactive power capability expressed by Qmin and Qmax as given in the reference case (rectangular reactive power capability) Wind farms represented by equivalent (aggregated) models Sensitivity cases Different reactive power capability (triangular capability) Different levels of wind generation Scenarios based on ERCOT case, from no wind to high wind penetration. Limited reactive power capability in the wind farms (conservative).

Sensitivity Scenarios Wind Farm Generation Re-Dispatch was performed to model the following sensitivity scenarios Sensitivity Scenarios No-Wind scenarios Constant load (conventional generation increased by 3,719 MW) Constant conventional generation (system load scaled down by 3,719 MW) Increased wind generation scenarios Scenario 3 (5,849 MW of wind generation, 14.7% of total) Maximum wind generation in the Gulf Coast and Horse Hollow gen-tie West Texas wind generation increased by 1,040 MW Scenario 4 (6,369 MW of wind generation, 16% of total) Scenario 3 with an additional 520 MW of wind in West Texas Scenario 5 (same as scenario 4 but with additional wind in west Texas dispatched against local generation)

Preliminary results indicate that voltage violations are not the issue for the current Western ERCOT system Results AC contingency analysis ERCOT contingency file (9,000+ cat. B and cat. C contingencies) Few post-contingency voltage violations Generally unrelated to the wind generation dispatch Also unrelated to reactive power capability at the wind farms Thermal violations Existing system configuration → restrictions to dispatch of West Texas wind generation Significant overloads already identified before reaching full power output of wind generation in West Texas Thermal overloads are the limiting factors. No condition has been identified that shows the need for additional reactive power capability from wind farms

Generator reactive capability requirements are driven by system topology and the imbalance between generation and load in Western ERCOT. This trend will become further exaggerated with CREZ implementation Current ERCOT System West Zone load – approximately 4,000 MW West Zone Generation – approximately 8,000 MW ERCOT System post CREZ West Zone load – approximate 4,400 MW West Zone Generation – 18,000 MW WGR lagging reactive capability will need to increase with MW output to compensate for transmission line reactive losses. WGR leading reactive capability will have little value since shunt reactors will be required to offset transmission line charging anyway when the wind is calm. CREZ doesn’t make things worse but amplifies the consequences of adopting PRR830!

Highlights of PRR835 Sets minimum requirement of +/-0.95 Power Factor at the Point of Interconnection May require additional reactive requirements when supported by a System Impact Study Addresses the “Cone” versus “Rectangle” debate Wind generator reactive requirements and VSS are distinguished from non-wind generators Requires wind generators to provide real-time reactive capability through SCADA Does not unnecessarily limit aggregation of wind turbine generators based on size and type as does PRR830 Grandfathers WGRs interconnected after May 17, 2005 and before the adoption of PRR835 in meeting the +/- 0.95 PF requirement What differentiates PRR835 from PRR830 is that it provides superior economies while ensuring system safety and reliability where justified and needed!