Summary of Suspension Configurations Yuta Michimura Department of Physics, University of Tokyo March 18, 2015.

Slides:



Advertisements
Similar presentations
Vibration Isolation Group R. Takahashi (ICRR)Chief T. Uchiyama (ICRR)Payload design H. Ishizaki (NAOJ)Prototype test R. DeSalvo (Caltech)SAS design A.
Advertisements

Takanori Sekiguchi Italy-Japan Workshop (19 April, 2013) Inverted Pendulum Control for KAGRA Seismic Attenuation System 1 D2, Institute for Cosmic Ray.
SEO report _SAITO 1. Overall schedule of iKAGRA installation/commissioning change to Michelson Interferometer 2. Scheduling of daily works for installation.
Prototype Test of Vibration Isolation System Current Status & Schedule
Takanori Sekiguchi Anual Meeting of Physics Society of Japan Sep. 22nd, 2013) Prototype Test of Vibration Isolation System Current Status & Schedule 1.
Takanori Sekiguchi ALPS Report, Dec. 26th, 2013 Prototype Test of Type-B 1 Takanori Sekiguchi KAGRA F2F MEETING Feb
KAGRA Roadmap and Progress Evaluation Assessment S.Miyoki  M.Ando 2012/7/30.
Ryutaro Takahashi (National Astronomical Observatory of Japan) Vibrtion isolation system for KAGRA The 6th Korea-Japan workshop on KAGRA NAOJ, June,
Takanori Sekiguchi External Review Control and tuning of suspension 1 T. Sekiguchi KAGRA 4th External Review.
Optical Levers Layout and Cabling Yuta Michimura, Yuya Kuwahara Ando Group Department of Physics, University of Tokyo November 19, 2015.
Intensity Stabilization Servo Plan Yuta Michimura Department of Physics, University of Tokyo November 23, 2015.
New iKAGRA Configuration Yuta Michimura Department of Physics, University of Tokyo 11th KAGRA F2F (University of Tokyo) Feb 6, 2015.
KAGRA ISC Electrical Components Layout Yuta Michimura Ando Group Department of Physics, University of Tokyo December 8, 2015.
Aligning Advanced Detectors L. Barsotti, M. Evans, P. Fritschel LIGO/MIT Understanding Detector Performance and Ground-Based Detector Designs LIGO-G
1 PAY & OSD Piero Rapagnani 26/02/ Fatal interference with current geometry: deep redesign of the payload needed Positioning another payload close.
Low frequency anti-vibration system of LCGT Vibration Isolation Group R. Takahashi (ICRR), K. Yamamoto (ICRR), T. Uchiyama (ICRR), T. Sekiguchi (ICRR),
Vibration Isolation Subsystem KAGRA face to face meeting (31 July, 2012) R. Takahashi (ICRR), K. Yamamoto (ICRR), T. Uchiyama (ICRR), T. Sekiguchi (ICRR),
Summary of iKAGRA Test Run Mar 25-31, 2016 Yuta Michimura Department of Physics, University of Tokyo April 12, 2016JGW-T
IKAGRA 初期アラインメント手順 Initial Alignment Procedure for iKAGRA Yuta Michimura Department of Physics, University of Tokyo July 5, 2016JGW-T
Local control sensors for iKAGRA payloads and perspective (Optical lever) Kazuhiro Agatsuma 2013/Dec./5 ELiTES meeting at Tokyo1.
Summary of iKAGRA Test Run Apr 11-25, 2016 Yuta Michimura Department of Physics, University of Tokyo May 9, 2016JGW-T
Main Interferometer Subsystem
Type B Installation Plan
KAGRA+ Upgrade Plans Yuta Michimura1, Kentaro Komori1
Summary of iKAGRA Test Run Mar 25-31, 2016
Summary of iKAGRA Test Run Apr 11-25, 2016
Kazuhiro Yamamoto on behalf of KAGRA collaboration
KAGRA用防振装置の開発 VIII Configuration Sensors and Actuators
Yuta Michimura Department of Physics, University of Tokyo
KAGRA Control Room Appearance (tentative)
Yoichi Aso on behalf of the LCGT ISC Group
Vibration Isolation Systems
The Advanced LIGO Angular Control System (ASC) (Hanford edition)
KAGRA+ Upgrade Plans Yuta Michimura1, Kentaro Komori1
Summary of the iKAGRA Run
Interferometer Design for bKAGRA Phase 1 and Beyond
iKAGRA初期アラインメント手順 Initial Alignment Procedure for iKAGRA
Type B Installation Plan
KAGRA+ Upgrade Plans Yuta Michimura1, Kentaro Komori1
Cartoon of the optical layout around IMC, IFI and IMM
Mark Barton f2f Meeting 2/22/16
KAGRA+ Upgrade Plans Yuta Michimura1, Kentaro Komori1
Interferometer Design for bKAGRA Phase 1 and Beyond
Mark Barton f2f Meeting 2/22/16
Summary of iKAGRA Test Run Mar 25-31, 2016
Summary of iKAGRA Test Run Mar 25-31, 2016
Interferometer Design for bKAGRA Phase 1 and Beyond
Interferometer Design for bKAGRA Phase 1 and Beyond
Interferometer Design for bKAGRA Phase 1 and Beyond
Commissioning Procedure for bKAGRA Phase 1 ( )
iKAGRA初期アラインメント手順 Initial Alignment Procedure for iKAGRA
Commissioning Procedure for bKAGRA Phase 1 ( )
Summary of the iKAGRA Run
Commissioning Procedure for bKAGRA Phase 1
Commissioning Procedure for bKAGRA Phase 1
Commissioning Procedure for bKAGRA Phase 1 ( )
iKAGRA初期アラインメント手順 Initial Alignment Procedure for iKAGRA
Yuta Michimura Department of Physics, University of Tokyo
Status of KAGRA Yuta Michimura on behalf of the KAGRA Collaboration
Commissioning Procedure for bKAGRA Phase 1
Status of KAGRA Yuta Michimura on behalf of the KAGRA Collaboration
Commissioning Procedure for bKAGRA Phase 1
Interferometer Design for bKAGRA Phase 1 and Beyond
Beam Propagation for bKAGRA Phase 1 with flat ETMs
Development of vibration isolation systems for LCGT VII
iKAGRA初期アラインメント手順 Initial Alignment Procedure for iKAGRA
Summary of iKAGRA Test Run Mar 25-31, 2016
Interferometer Design for bKAGRA Phase 1
KAGRA ISC Electrical Components Layout
Yuta Michimura Department of Physics, University of Tokyo
Presentation transcript:

Summary of Suspension Configurations Yuta Michimura Department of Physics, University of Tokyo March 18, 2015

For bKAGRA ITM, ETM Type-A Suspension 2 Top Filer Inverted Pendulum Standard Filer Bottom Filer Intermediate Mass Test Mass Geophone (H) x3 LVDT + Act (H) x3 LVDT + Act (V) x1 OSEM x6 Platform LVDT + Act (V) x1 Coil-magnet (H) x4 Oplev x1

For BS, SRM, SR2, SR3 Type-B Suspension 3 Inverted Pendulum Top Filer Standard Filer Bottom Filer Intermediate Mass Test Mass LVDT + Act (V) x1 OSEM x6 LVDT + Act (V) x1 OSEM (H) x4 Oplev x1 Geophone (H) x3 LVDT + Act (H) x3 LVDT + Act (V) x1

Type-Bp Suspension 4 For PRM, PR2, PR3 Standard Filer Bottom Filer Intermediate Mass Test Mass LVDT + Act (V) x1 OSEM x6 LVDT + Act (V) x1 OSEM (H) x4 Oplev x1

Fixed Type-Bp Suspension 5 For iKAGRA ITM, ETM Bottom Filer Intermediate Mass Test Mass OSEM x6 LVDT + Act (V) x1 OSEM (H) x4 Oplev x1

Type-C Suspension 6 For MCi, MCo, MCe, and other input output optics Intermediate Mass Test Mass Stack Coil-magnet (H) x4 Oplev x1 Picomotor (V) x2

References 7 See wiki page AssemblyStatus for the assembly status of suspensionsAssemblyStatus See JGW-T for sensors and actuators arrangement of Type-A suspensionJGW-T Suspension performance below