Construction Delays & CPM Schedules
Advertisements

1 CLIENT CONSULTANT AGREEMENT. 2 Negotiations Types of Consulting Contracts Standard Form of Contract Form of Contract General Conditions Special Conditions.
CARLIN LAW GROUP, APC Grounds for Additional Time and/or Compensation A.Express Changes B.Constructive Changes C.Differing Site Conditions D.Express Suspension.
ABC Change Orders College of Environmental Design
CONTRACT A binding agreement between two or more parties for performing, or refraining from performing, some specified act(s) in exchange for lawful consideration.
Presented by: Fouad Al-Malazi ID No.: Managing Construction Contracts By Robert D. Gilbreath Chapter 1 CONSTRUCTION CONTRACTS: Roles and Relationships.
DISTRICT FIVE CONSTRUCTION CONTRACT ADMINISTRATION UPDATE TRAINING Submission of Working Schedule Specification SP A.
Presenter: Victor C. Tyler, P.E. Estimating and Bidding Strategies that Drive Best Practices.
CON 4003 CVE 4073/5073 The Estimating Process Prof. Ralph V. Locurcio, PE.
Delays and the consequences and time management
KING FAHD UNIVERSITY OF PETROLEUM & MINERALS DHAHRAN, SAUDI ARABIA Construction Engineering & Management CEM-520 CHANGE ORDERS IN CONSTRUCTION PROJECTS.
Project Cost Management Estimation Budget Cost Control
/1.401/ESD.018 Project Management Lecture 20 Project Reporting Project Close-out Samuel Labi and Fred Moavenzadeh Massachusetts Institute of Technology.
Determination of Construction Contract Duration for Public Projects in Saudi Arabia By: Ahmed Saleh Al-Sultan, June 1989 Presented by Sameh Elish January.
PREPARED BY: Mohammed Tanbora SUPERVISED BY: Dr. Kamalain K. Shaat CHAPTER8: Application Of Controls.
KFUPM, Department of Construction Engineering and Management CEM 520 LIABILITY ALLOCATION AMONG THE PARTIES TO FIXED-PRICE CONSTRUCTIN CONTRACTS IN SAUDI.
Introduction -Discussed preparation of the overall plan for the project - as well as its implementation. -The control system quantitatively measures actual.
Time and Cost Estimation
Review of Plans & Estimating Introduction Architect’s Responsibilities Types of Estimates Factors Affecting Cost Film Project:
Lecture(3) Instructor : Dr. Abed Al-Majed Nassar
APPLICATION OF CONTROLS CHAPTER 8 Presenting by : Mustafa Al tayeb Date 21/11/2005.
LOGO October The Employer FIDIC 1999 dasdas Supervisor: Dr.Kamalain shaath Done by: Mahmoud Abu Kmail Construction Contract Administration ENGC.
Construction Engineering 221 Contracts & Contractor Procurement.
Construction Engineering 221 Cost Estimating and Bidding.
EM15 – Contractors COST MANAGEMENT
Cost Management Week 6-7 Learning Objectives
AN INTRODUCTION TO: from the leading resource for education and information in the repair industry... TECHNICAL GUIDELINE S Guide for Methods of Measurement.
Construction: Legal Issues. Legal Issues In the Bidding Process Timing of various activities has legal implications. During the bidding process: –A bid.
Contract Pricing Methods Ch 2. Lump Sum –Contractor bids 1 price for entire project –Estimate needs to be detailed –Design needs to be finished before.
Surety Bonds 101 The Basics of Bonding. Surety Bonds Vs. Traditional Insurance Surety BondsInsurance 3-party2-party Risk transfer Duty to obligeeDuty.
An-Najah National University Graduating project II Delay in construction projects.
Compensation events and claims Presented by Prof. Khem Dallakoti.
Construction Engineering & Management Department CEM 510 Construction Planning & Scheduling Dr. S. Almohawis Presented By Abdulrahman Alghamdi Article:
Health Economics Unit Definition of Economics  Demand − relationship between quantities and prices that addresses how much bought at each price.
Software Engineering Saeed Akhtar The University of Lahore Lecture 8 Originally shared for: mashhoood.webs.com.
CONSTRUCTION ADMINISTRATION Construction Operations Dr. Alaattin Kanoğlu Spring, 2013 Professional Practice Management I.B.U. Architecture Undergraduate.
General Condition THE EMPLOYER Construction Law Supervised By : Dr. Kamalain Shaath Prepared By : Eng. Fawzy El.farra.
ARC 807: Professional Practice and Procedure Department of Architecture, Federal University of Technology, Akure, Nigeria ARC 807: Professional Practice.
CON 4003 CVE 4073/5073 Construction Cost Estimating Class #2: The Estimating Process Prof. Ralph V. Locurcio, PE.
Chapter 3 Financial Management Part 2 BCN 4772 Summer 2007.
Quantifying change order impact on productivity by using ANN approach ECE 539 Project Presentation (Order: 316) Min-Jae Lee Construction Management Program.
CONTRACT PRICING ALTERNATIVES Presented by: Fahad H. Al-Anazi CEM 520 February 27,1999.
CE 366 PROJECT MANAGEMENT AND ECONOMICS Robert G. Batson, Ph.D., P.E. Professor of Construction Engineering The University of Alabama
PREPAREDBY: PREPARED BY: Ahmed Al Tayeb Saed Al Qeshawe Tareq Amen Abdalla Syiam SUPERVISED BY: Dr. Kamalain K. Shaat CHAPTER8: Application Of Controls.
Construction Eng 221 Project Management and Administration.
Risk Management Phase Risk management Assessment, tracking and control – Tools: Risk Hierarchical modeling: Risk breakdown structures Risk matrixes Contingency.
1 CONTRACTING. 2 WHAT IS CONTRACTING ? CONTRACTING IS BASICALLY AN AGREEMENT BETWEEN TWO PARTIES, ONE CALLED THE CONTRACTING PARTY AND THE OTHER THE CONTRACTED.
Measurement and Payment
CLAIMS MANAGEMENT. PRESENTATION OUTLINE INTRODUCTION TYPICAL CLAIMS AGAINST OWNER TYPICAL CLAIMS AGAINST CONTRACTOR CRITICAL PATH METHODS UTILIZATION.
Scheduling CTC-370. Value Engineering Provides alternatives to the proposed design –Save Owner $$ –Must be as good or better than original design –Must.
University of Calgary Continuing Education Construction Contract Law and Documents Week 12 Changes Delays Claims Contract Documentation.
UNIVERSITY OF DAR ES SALAAM t Selection and Employment of Consultants Negotiations with Consultants; Monitoring Performance of Consultants; Resolving Disputes.
Fundamentals of Project Control Chapter 11 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project.
Collaboration of Entitlement and Cost Efforts in Claims Analysis Rubino & McGeehin Consulting Group June 27, 2005.
Not for Distribution Outside of MBP1 April 11, 2012.
Information Technology Project Management, Seventh Edition Note: See the text itself for full citations.
DR. Nabil Dmaidi F ACTORS THAT D ETERMINE V ARIATION IN E STIMATES.
Estimating and Scheduling CEE 492
Faculty of Postgraduate Studies and Scientific Research German University in Cairo Modeling to Reduce Variation Order in Construction Projects in Egypt.
Reconstruction site Investigation, Planning, Scheduling, Estimating and Design Eng. Fahmi Tarazi.
(Additional materials)
Request for Proposal & Proposal
Risk Management Practice (Case study: Sydney Opera House)
Project Cost Control.
Construction Contracts
Basic Principles of Estimating
‘ Causes of Delay During Construction Phase at Palestine ’
CEM 515 Done by: Abdulkarim Sulais
Directed Change Constructive Change
TOTAL COST CONTROL ON CONSTRUCTION PROJECTS
Presentation transcript:

King Fahd University of Petroleum & Minerals Construction Engineering &Management Department Construction Contracting Dr. Suliman Al mohawis

Causes & Effects of Change orders on Construction Projects Presented by: Mohammed Abu Neamah

Outline: Introduction. Objective. Reason for issuing Change Order. Effects of Change Order on Construction Projects. Parties benefits and losses through Change Order. Recommendations.

Introduction: Change : is any event lead to modification in the original scope of the work, in the completion time of project, and in the cost of project and become part of most construction project. Change Order: Is a formal document that deal with changes in project.

Objective: Determine causes & effects of changes on project. (Productivity, Time, and Cost) offer recommendations to reduce negative impacts on future projects.

Reason For issuing Change Order: Changes related to Owner. Changes related to Consultant. Changes related to Contractor. Other Changes..

Changes related to Owner: Budget problems. Objective of project. Change in specifications. Supply material and equipment. Nature of the owner

Changes related to Consultant: Errors in design. failure to delineate best alternative design. Change in specifications. Information about material and equipment is not available. Complexity of the design. Details in drawings are not sufficient

Changes related to Contractor: Change in quantities. Financial of contractor. Skilled labors and equipment required.. Profit desired. Involvement in design process Mature contractor.

Other changes: Weather conditions. Economical conditions Social conditions. Unexpected conditions.

Effect of Change Order on Projects: Productivity. Cost. Time.

Productivity: Productivity : is the amount of work produced refer to amount of resources consumed. Change order lead to negative impact on labor morale and efficiency. It is very difficult to quantify productivity loss due to changes.

Productivity Cont.: Factors associated with change order and effect on productivity: Number of change order. Time of change order. Type of work. Type of impact.

Productivity Cont.: Productivity can be measured using either: Micro level of productivity Macro level of productivity. The term delta can be used to measure productivity loss. Delta: is difference between actual labor hours to complete project and the estimated labor hours plus approved change order hours.

Productivity Cont.:

Productivity Cont.: Positive value for delta indicate that actual productivity is less than planned. Negative value for delta indicate that actual productivity is higher than estimated

Effect of change order on Cost: Contract price is adjustment: Cost associated with material procurement. Decreasing in labor efficiency. Losses in profit. Increases in indirect cost.

Effect of change order on Time: Negative outcomes of change order related to time: Delay in progress payment. Delay in Procurement of material and equipment Schedule compression. Logistic delay.

Parties benefit & losses: Each part of contract can benefit and loss at the same time Contractor: Contractor earned money due to increasing in work and variation of quantities. Contractor encounter damage in his reputation.

Parties benefit & losses Cont.: Owner: Owner obtain his requirements without defects after modification. Owner revenues will be delayed due to delay in project completion time. Consultant: Consultant earned money due to time extension and adjustment to design.

Recommendations: Owners should select qualified and experienced consultant and contractor. Owner need to determine his requirements within his budget . Consultants should demonstrate the effect of changes on project to the owner.

Recommendations: Reduce processing time of change order . Monitoring productivity during construction. Update project schedule regularly. Involve contractor in the design phase

Thank You For listening