ATF2 commissioning in Autumn 2009 for discussion Philip Bambade LAL & KEK LCWS09 BDS session Albuquerque, New Mexico October 1, 2009 on behalf of the commissioning.

Slides:



Advertisements
Similar presentations
Summary of the discussion for the commissioning session 2 nd ATF2 Project Meeting KEK, Tsukuba, Japan 6/ 1/ 2006 T.Okugi (KEK)
Advertisements

Coupling Correction in ATF2 EXT 7 th ATF2 Project Meeting, december 2008 C.Rimbault, LAL Orsay.
Beam position monitors LCABD Plenary meeting Bristol, 24th March 2009 A. Aryshev, S. T. Boogert, G. Boorman, S. Molloy, N. Joshi JAI at Royal Holloway.
IPBPM piezo-mover system and plans for in situ monitoring of calibration and stability Current status and plan for ATF2 Philip Bambade Laboratoire de l’Accélérateur.
Status of IPBSM Improvement N. Terunuma, KEK 2012/July/13 ATF2 Weekly Meeting.
-brief report of October runs and some inputs for the Nov/Dec planning – Nobuhiro Terunuma, KEK, ATF ATF session on LCWS13, Tokyo Univ., Nov. 13, 2013.
Analysis of ATF EXT/FF Orbit Jitter and extrapolation to IP (Data of ) ATF2 Project Meeting K. Kubo.
ATF2 Status and Plan K. Kubo ATF2, Final Focus Test for LC Achievement of 37 nm beam size (Goal 1) – Demonstration of a compact final focus.
1.Beam Tuning Simulation 2.IP Beam Position Stability 2-1 ) Magnet Vibration 2-2 ) IP position jitter subtraction for 2 nd bunch with FONT feedback 2-3.
High Resolution Cavity BPM for ILC final focal system (IP-BPM) ILC2007/LCWS 2007 BDS, 2007/6/1 The University of Tokyo, KEK, Tohoku Gakuin University,
Discussion on Milestone and schedule Toshiyuki Okugi ATF2 commissioning meeting 1 / 7 / 2009.
Status of very high priority beam tuning software Special ATF2 project meeting, Korea, 1 st October 2008 Cécile Rimbault, on behalf of High Priority task.
ATF2: the linear collider final focus prototype at KEK - an international telescope for nanometre size beams - Philip Bambade Laboratoire de l’Accélérateur.
Personal strategy for ATF2 beam operation in 2009 Toshiyuki OKUGI 2009 / 7 /22 ATF2 weekly meeting.
ATF2 optics … 1 3 rd Mini-Workshop on Nano Project at ATF ATF2 optics, tuning method and tolerances of initial alignment, magnets, power supplies etc.
UK/EU Plans for ATF2 G.A. Blair ATF2-IN2P3-KEK kick-0ff meeting, Annecy, 8 th October 2006 Overview EUROTeV UK.
March 7, 2007 LET Issues (Cai/Kubo/Zisman) Global Design Effort 1 Low-Emittance Tuning Issues and Plans Yunhai Cai, Kiyoshi Kubo and Michael S. Zisman.
FFS Issues in the 2011 autumn continuous operation Toshiyuki OKUGI (KEK) 1/13/2011 The 11 th ATF2 project meeting SLAC, USA.
New IP chamber for ATF2 goal 2 Philip Bambade Laboratoire de l’Accélérateur Linéaire Université Paris 11, Orsay, France ATF2 Technical Review KEK, 3-4.
Fifth ATF2 Project Meeting, dec. 2007, KEK, Japan Emittance measurements with multiple wire-scanners and quadrupole scans in ATF EXT C. Rimbault,
June 30, th ATF2 Project Meeting Andrei Seryi for the ATF2 team May 2010 Continuous Run Operation.
Continuous Run in May K.Kubo. Final Focus Test Line IP; ~40 nm beam ATF Linac (1.3 GeV) ATF Damping Ring (140 m) Extraction Line Photo-cathode.
Summary of Commissioning and Tuning session Philip Bambade LAL-Orsay 5 th ATF2 project meeting KEK, 21 December 2007.
ATF2 beam commissioning status and beam time request Toshiyuki Okugi 2008 / 11 / 12 ATF2 Commissioning Meeting.
Feedback On Nanosecond Timescales (FONT): Robert Apsimon, Philip Burrows, Neven Blaskovic, Douglas Bett, Glenn Christian, Michael Davis, Davide Gamba,
Commissioning Status of Shintake Monitor (IP-BSM) T. Yamanaka, M. Oroku, Y. Yamaguchi, Y. Kamiya, S. Komamiya (Univ. of Tokyo), T. Okugi, N. Terunuma,
Mark Woodley, SLACATF2 Project March 20-21, Summary of Tuning, Corrections, and Commissioning.
Highlights and discussion at LAL FKPPL & FJPPL “Toshiko Yuasa” workshop Philip Bambade Laboratoire de l’Accélérateur Linéaire Université Paris 11, Orsay,
Technical Board “issues” Philip Bambade Laboratoire de l’Accélérateur Linéaire Université Paris 11, Orsay, France ATF2 Technical Review KEK, 3-4 April.
8 th Meeting of the ATF TB/SGC 11 June Hardware Status Fast Kicker – FID pulsers have had a reliability problem: this appears to have been solved.
ATF2 Software tasks: - EXT Bunch-Bunch FB/FF - IP Bunch-Bunch FB - FB Integration Status Javier Resta-Lopez JAI, Oxford University FONT meeting 1th August.
ATF2 Commissioning Toshiyuki Okugi 2008 / 7 /9 ATF2 beam commissioning meeting, KEK.
Low emittance tuning in ATF Damping Ring - Experience and plan Sendai GDE Meeting Kiyoshi Kubo.
Operational Experience with ATF2 Beam Diagnostics Glen White, SLAC On Behalf of ATF2 Collaboration TIPP, Chicago, June
EXT: Summary of activities, software development, and tuning performance 11th ATF2 Project Meeting, January M. Woodley1/29.
Greeting for 10 th ATF2 project and TB/SGC joint meeting 1.
1 H. Hayano for the ATF collaboration Low Emittance Beam Generation in ATF H. Hayano for the ATF collaboration BPM electronics improvement emittance tuning.
Status of ATF Collaboration The unique test facility for ILC with a low emittance beam. Junji Urakawa, KEK LCPAC at KEK
1 H. Hayano ATF Status June/2004 H. Hayano ATF: emittance status beam study status plan nm-project collaboration & plan ATF review 6/17/2004.
July 2, th ATF2 Project Meeting Philip Bambade, Andrei Seryi, Toshiaki Tauchi Summary for TB.
Initial beam size commissioning for ATF2 T.Okugi 3rd ATF2 Project Meeting, KEK 12/ 19/ 2006.
IP instrumentation configuration for Autumn 2010 ATF2 runs Toshiyuki OKUGI, KEK 2010 / 7/ 1 10 th ATF2 project meeting.
ATF2 Tuning Summary Nov & Dec 2010 Glen White, SLAC 11 th ATF2 Project Meeting, SLAC Jan
ATF2 Software Review LAL June SHORT SUMMARY - Philip Bambade ATF2 weekly meeting July
Task Lists of ATF2 commissioning Toshiyuki Okugi ATF2 Project Meeting 12 / 17 / 2008.
Plans for Laser-wire System Grahame Blair 21 st June 2005 Brief overview of UK LW programme ATF Extraction line LW Plans for this year ATF2.
ATF2: Summary of Scheduling Strategy Session Grahame Blair Feedback and Feedforward systems Fast Kicker for ILC bunch train structure Laser-wire Shintake.
ATF2 beam operation status Toshiyuki OKUGI, KEK The 9 th TB&SGC meeting KEK, 3-gokan Seminar Hall 2009/ 12/ 16.
ATF status M. Ross October 15, 2004 The ATF is the largest test facility built exclusively for linear collider RD –Utility not reduced by the selection.
Emittance measurements with multiple wire-scanners and quadrupole scans in ATF EXT C. Rimbault, Brossard, P. Bambade (LAL) Main goal : - Try to improve.
Summary of Tuning, Corrections, and Commissioning ( Short summary of ATF2 meeting at SLAC in March 2007 ) and Hardware Issues for beam Tuning Toshiyuki.
ATF2 Software Review LAL June 2008 Philip Bambade & Glen White ATF2 weekly meeting June
CERN, BE-ABP (Accelerators and Beam Physics group) Garcia, Pfingstner, Renier ATF operations training Report about the ATF operations training Hector Garcia.
IP diagnostics Toshiyuki Okugi 2008 / 6 /19 ATF2 Software mini-workshop LAL, Orsay.
IoP HEPP/APP annual meeting 2010 Feedback on Nanosecond Timescales: maintaining luminosity at future linear colliders Ben Constance John Adams Institute,
1 1 H. Hayano and ATF group ATF Status August/2004 H. Hayano and ATF group Multibunch emittance Instrumentation developments Plans for run Multibunch.
2nd ATF2 Project Meeting (May 30, 2006)M. Woodley [SLAC]1 ATF2 Layout/Optics (v3.3) nBPM (SLAC) nBPM (KEK) FONT Compton / laserwire ODR Existing ATF Extraction.
Technical Board Summary Preliminary Philip Bambade Laboratoire de l’Accélérateur Linéaire Université Paris 11, Orsay, France ATF2 project meeting, Technical.
ATF2 Software tasks: - EXT Bunch-Bunch FB - IP Bunch-Bunch FB - FB Integration Status and plans Javier Resta-Lopez JAI, Oxford University ATF2 commissioning.
Status of ATF2 linear collider focus prototype emphasizing France-China joint contributions Philip Bambade Laboratoire de l’Accélérateur Linéaire Université.
Hardwares for commissioning 2 nd ATF2 Project Meeting KEK, Tsukuba, Japan 5/ 31/ 2006 T.Okugi (KEK)
Simulation for Lower emittance in ATF Damping Ring Kiyoshi Kubo Similar talk in DR WS in Frascati, May 2007 Most simulations were done several.
Measurements and analysis of beam parameters at post-IP wire-scanner
Expected hardware status and Priority of the commissioning task
Emittance Diagnostics
Philip Bambade, Andrei Seryi, Toshiaki Tauchi
13th ATF2 Project Meeting Summary
For Discussion Possible Beam Dynamics Issues in ILC downstream of Damping Ring LCWS2015 K. Kubo.
ATF2 IP Tuning Task Simulation Updates
ATF ICB meeting, LCWS08, UIC, Chicago, 11/18/2008
Presentation transcript:

ATF2 commissioning in Autumn 2009 for discussion Philip Bambade LAL & KEK LCWS09 BDS session Albuquerque, New Mexico October 1, 2009 on behalf of the commissioning team

Background material used : 1. Personal strategy for ATF2 beam operation in 2009 T. Okugi, July 22, 2009 ATF2 weekly meeting 2. Schedule plan of machine studies in October to December P. Bambade, Y. Kamiya et al., P. Burrows, August 12, 2009 ATF2 weekly meeting 3. Presentations at June 2009 ATF2 project meeting

Commissioning periods December 2008  3 weeks January – June 2009  14 weeks (= ) October – December 2009  7 weeks (=2+2+3) planned 2010… ~ idem Beam time scheduling 50% fraction for ATF2 & 4 days per week operation Individual R&D tasks  common goal Groups: KEK, Tokyo, Sendai, SLAC, IHEP, UK, France, Spain, CERN,… ATF2 educational function Several PhD & young post-doc researchers in accelerator science + few add. days 70% + Now…

New hardware systems for ATF2

Priorities for December 2008 – June 2009 Radiation KEK  get authorization Fast extraction kicker R&D in Damping Ring ATF2 hardware commissioning (magnets & instruments) Shintake monitor (BSM) commissioning & study Initial 1 st order optics measurements (methods, software)

Commissioning  gradual  x,y * ( demagnification ) reduction paced by instrumentation (BSM / other)‏background studybeam tuning

Variable  IP at ATF2  y [m] April - December 2009 March 2009 nominal value (  y = m) plans  y =  m  x = 0.08  m presently  y = 0.01 m  x = 0.08 m

December 2008

Vertical transfer matrix (ZV1X  QD2A) On-going : separate beam / instrumental variations & noise

Horizontal transfer matrix (ZH1X  QD2A) non trivial check !Final Doublet  not yet“Flight Simulator”

Test of beam based alignment automated software tool in “Flight Simulator” cavity BPM fixed on F.F. quad mounted on mover BPMs on sextupoles and quads not on movers  in progress

Phase space in extraction line systematic “manual” BBA on selected quads careful dispersion + coupling measurement & correction   y ~ pm reproducibly ! April & May DR measures ~ 6 pm ATF2 nominal = 12 pm BmagX BmagY  x ~ 1.7 nm  y ~ 11 pm (at minimum) Emittance and  mismatch during coupling reduction “Flight Simulator” and V-system tools

Phase space at post-IP wire-scanner Tungsten, 10  m diameter, 40 cm behind IP  x = 1.13  0.06 nm (design = 1.2 nm)  x = 13  1 cm (design = 10 cm) 28 May 2009 Minimum beam size ~ 10  m is resolved Must subtract measured dispersion (nominal + anomalous) cannot resolve  y ~ 0.35  m subtract (anomalous) dispersion use  y measured in extraction line   y ~ 1.4 cm (design = 1.8 cm)  Basic check of optical transfer from DR  IP

IP  y minimization at post-IP wire-scanner

IP  x with BSM “laser wire” mode established  y in interference mode  not yet a convincing signal but good progress made

Goals for October - December 2009 Continue fast extraction kicker R&D in Damping Ring Confirm large  * optics (  x,y =8,1cm)  towards sub-  m  y First signal evidence in interference mode  BSM  y measurement Sub-goals New BSM hardware Carbon wire scanner at IP with 5  m diameter Cavity BPM stability and reproducible calibrations Strip-line BPM improved calibration & reproducibility Efficient optical tuning strategy in extraction line  IP spot Additional goals preparing for New strip-line BPM electronics Multi-OTR fast extraction line 4D phase space diagnostics Tilt monitor & IP-BPM R&D FONT Background study at and near IP as function of  * and FD alignment

Priority tasks & responsibilities for Autumn commissioning 1) Team up by interest to conduct shifts, prepare software, do simulations & data analyses 2) Open and flexible Cavity BPM : calibration, stability, incl. S-band Boogert, Aryshev, Lyapin, Okugi, Naito, Molloy… Stripline BPM : better calib., add ADCs, high pass filter Renier, Naito, Okugi,… BSM : new diagnostics & other hardware, LW & interference modes, beam setup Kamiya + Tokyo group + local KEK team,… Post IP C-wire : commissioning, IP waist & knob scans incl.  * determination Bolzon, Bai, Zhou, McCormick, Kuroda, Terunuma, Tokyo group… Orbit reconstruction, on-line BPM & lattice diagnostics Renier, Boogert, Okamoto, White… Dispersion correction : EXT & IP, different knobs & methods incl. sextupoles Jones, Kubo, Kuroda, Marin-Lacoma, Okugi, White, Woodley,… Coupling correction : EXT & IP, different knobs & methods incl. sextupoles Bolzon, Kubo, Kuroda, Okugi, Rimbault, White, Woodley,… Background study : BSM + near IP, dependence with FD alignment &  * Guler + Verderi, Okugi + Tokyo group,…  not listed here : Fast Kicker, DR, FONT, LW, new EXT-BPM electronics + multi-OTR + tilt monitor

Collect important questions for each priority task 1) Below are only a few examples… 2) The whole group should add & improve ! Max. flux of bremstrahlung gammas in BSM detector for Compton signal detection ? Flux prediction from FD region GEANT4 simulation for given input halo distribution ? Background How can we automate EXT coupling corrector + wire scanning ? Matching of FF horizontal dispersion for sextupole mover knobs to be orthogonal ? Coupling Can IP D y be corrected to < 1 mm with EXT line “sum-knob” in  y = 1 cm optics ? Can vertical bumps help to fully correct D y (i.e. both phases) in EXT ? Dispersion Stability of BPM scale coefficients ? Precision of strip line and cavity BPMs ? Magnitude of reconstructed injected beam fluctuations ? Traj.rec.&latt. diag. What is expected signal strength from C wire and visibility in BSM reference layer ? Would automatic waist scans incorporating dispersion measurement be feasible ? How Twiss par. measured at IP compare with propagated ones from EXT meas. ? C wire &  match Can scanning be automated in ATF control system (V-system, Flight Simulator) ? BSM High-pass filters and separate ADCs sufficient for calibrations  precision < 5  m ? Strip line BPM Can the stability of calibrations for a given BPM be monitored daily / weekly ? Cavity BPM STATUSQUESTIONSTASK  not listed here : Fast Kicker, DR, FONT, LW, new EXT-BPM electronics + multi-OTR + tilt monitor

Propose successive realistic goals for each task 1) Start with end goals for 2009… are listed ones OK ? 2) Each group asked to formulate appropriate sequence DecemberOctoberNovember Background Coupling Dispersion Traj.rec.&latt. diag. C wire &  match BSM Strip line BPM Cavity BPM TASK First indication of “background-aperture” in Final Doublet region  y IP /  y EXTLINE < 3 D y < 1  y waist Consistency of IP and EXT propagated results Sub-  m resolution in cavity BPMs Running traj.rec.& latt.diag. spy program Reach ~ 1  m C wire resolution limit Waist + disp. autoscan Signal evidence in 4.5 degree mode with ~ 1  m vertical spot Offset stability & acceptable intensity dependence Calibration stability on day & week timescales S-band BPM Non-mover calibrations End 2009  not listed here : Fast Kicker, DR, FONT, LW, new EXT-BPM electronics + multi-OTR + tilt monitor

External presence at KEK for ATF2 during Fall 2009 known as of 1 October KEK : Aryshev, Bambade, Kubo, Kuroda, Naito, Okugi, Oroku, 0 0 Tauchi, Terunuma, Yamanaka,… ? ?

Tentative overall beam time scheduling during Fall 2009 confirmation of participant KEK feedback / suggestions on tasks & goals ?

Concluding remarks  discussion The progress made may be slow but is solid and can be built upon: - very successful installation, and performing hardware - BSM LW mode established and has carefully evaluated and implemented many improvements for this run - other instrumentation is working though needs improving - check of large  optics basic soundness - first optics correction experience - invaluable experience for small international team learning to work together Clear & agreed end-of-2009 goals + group mostly same from start But many different ATF2 and ATF activities: richness, though a focus and scheduling of main tasks is important given commissioning interdependencies A few software improvements in V-system & Flight Simulator are critical to automate and speed up tuning tasks Weekly Friday scheduling can consider overall scheduling, goals, progress made Mechanism needed to prepare, discuss + communicate weekly task schedules Such task schedules are in the hands of each group, but should ideally be presented & reviewed each at Friday meeting, and at least posted on the ATF web at the beginning of each week (through a button directly on the main schedule)