NERC Lessons Learned Summary April 2015. NERC lessons learned published in April 2015 Two NERC lessons learned (LL) were published in April 2015 LL20150401.

Slides:



Advertisements
Similar presentations
Facilities Management and Design Chapter 4 Safety and Security systems.
Advertisements

Preventing Equipment Failures
Developed by Western Iowa Tech Community College This material was produced under a grant (SH F-19) from the Occupational Safety and Health.
1. Four LLs were published in February Transmission Relaying – Undesired Blocking 2.Lack of Separation for Critical Control Power Supply Leads.
Key Reliability Standard Spot Check Frank Vick Compliance Team Lead.
Visit Us At Booth #306 J2 Engineering, Inc. J2 provides Construction and Environmental Services and is a verified Service-Disabled Veteran-Owned Small.
Utility Management Providence Health System - Oregon Environment of Care.
10 The Service Entrance. 10 The Service Entrance.
1 Component Design Basis Inspection (CDBI) Graydon Strong 6/17/14.
NERC Lessons Learned Summary December NERC lessons learned published in December 2014 Three NERC lessons learned (LL) were published in December.
 Description of PressurePro System  Identify system components  Display and Operational Modes  Sensor alerts  Checking of tire pressures  Manual.
EAS Lessons Learned Summary Lessons Learned Published in May 2014.
Diesel Generator Reliability: Lessons Learned from Storms
Take 5 for Safety E. Lessard May 5, LANL Electrical Accident May 3, 2015  LOS ALAMOS, N.M. —Los Alamos National Laboratory workers were injured.
September 2014 Lesson Learned Summary. September 2014 LLs 2 Three NERC lessons learned (LL) were published in September 2014 LL Redundant Network.
 Wireless, Web-Based Monitoring System  Alarm/Event Notifications by Text Message and or  VPN Connection for Fast Response to Alarms and Events.
Chapter 8 Output Modules.
NERC Lessons Learned Summary March NERC lessons learned published in March 2015 Two NERC lessons learned (LL) were published in March2015 LL
1 Lesson 3 Computer Protection Computer Literacy BASICS: A Comprehensive Guide to IC 3, 3 rd Edition Morrison / Wells.
NERC Lessons Learned Summary
E8 / PPA Solar PV Design Implementation O&M Marshall Islands March 31-April 11, 8・5 - Field Inspection Items Visual inspection and verification.
1 CREZ COMMUNICATIONS Presented by American Electric Power Telecommunications Engineering Matt WilliamsDon Demand Columbus, OHTulsa, OK.
EC4019PA Intrusion & Access Control Technology (IACT) Chapter 4- CAMS Prepared by Sandy Tay.
2013 NATEF Task Area A-7 Heating, Ventilation, and A/C A. A/C System Diagnosis & Repair B. Refrigeration System Component D & R C. Heating, Ventilation.
Generator Data Submittals 5/8/ Transmission Customer Forum Bob Jones Transmission Planning Southern Company Transmission 5/8/ Transmission.
Scheduled Versus Event Driven Testing of Distribution Protection IEDs Dr. Alexander Apostolov, Benton Vandiver, Will Knapek, OMICRON electronics.
Release Reporting. Lesson #17 - Release Reporting How Do I Know If I Have a Leak in My UST System?
Applying the Distribution System in Grid Restoration/NERC CIP-014 Risk Assessment Srijib Mukherjee, Ph.D., P.E. UC Synergetic.
1 Lesson 3 Computer Protection Computer Literacy BASICS: A Comprehensive Guide to IC 3, 3 rd Edition Morrison / Wells.
LHC ARC Commissioning report during LS1 Agenda: VRGPE documentation (former VRJGE) Active Penning modification By-Pass Valves modification LHC ARC commissioning.
EAS Lessons Learned Summary Lessons Learned Published in August 2014.
February 26, 2013 Board of Directors Meeting 2012 ERCOT Region Reliability Update.
Curtis Crews, Reliability Services Texas Reliability Entity, Inc. Changes in Relay Misoperations Reporting.
Summary Rich Bauer, Senior Reliability Engineer Event Analysis Subcommittee – LL Update March 04, 2014.
NERC Lessons Learned Summary February NERC lessons learned published in February 2015 Two NERC lessons learned (LL) were published in February 2015.
EAS Lessons Learned Summary Lessons Learned Published in June 2014.
Chiller control system Specification meeting Lukasz Zwalinski – PH/DT.
Utility Engineers, PC.  Generation  Transmission  Distribution.
What is POWERGRID??? The Power Grid Corporation of India Limited (POWERGRID), is an Indian state-owned electric utilities company headquartered in Gurgaon,
NERC Lessons Learned Summary LLs Published in September 2015.
2011 PLANT OPERATIONS MODULE 8 Maintain Bulk Plant Systems and Equipment.
Experiences in Managing Settings Bryan J Gwyn National Grid USA.
Staying in Compliance Dispensing Equipment Spill/Overfill Presented by Travis Benton United Pump and Controls, Inc.
NERC Lessons Learned Summary LLs Published in December 2015.
WELCOME!. Who is T&T Power Group? WELCOME! Who is T&T Power Group? What can we do for you?
Ruben Carcagno, Sandor Feher, George Velev (team leader) MQXFS1 status meeting Summary of the MQXFS1 Investigation.
AIR CONDITIONING (COOLING)
PROPRIETARY INFORMATION - © 2015 WOODWARD, INC. PAGE 1 HighPROTEC-2 MRI4-2 Feeder Relay Sales presentation 2015/08/10.
Summary Event Analysis Subcommittee – LL Update NERC OC Meeting - June 2014.
S A Griffiths CM42 June 2015 Electrical & Control.
NERC Published Lessons Learned Summary
NERC Published Lessons Learned
NERC Published Lessons Learned Summary
NERC Published Lessons Learned
NERC Lessons Learned Summary
NERC Published Lessons Learned
NERC Published Lessons Learned
EAS Lessons Learned Summary
NERC Published Lessons Learned Summary
NERC Published Lessons Learned Summary
PRC Implementation Plan and Summary of Devices
Presented by: LADWP November 14, 2017
GlueX Electronics Review Jefferson Lab July 23-24, 2003
Emergency Electrical Power Supply for Buildings
Lesson Seven: Flood Works Monitoring
WECC August 2017 Reliability Workshop James Merlo, PhD
Analyzing CM-Related Condition Reports
WECC August 2017 Reliability Workshop James Merlo, PhD
Electrical components and systems
Presentation transcript:

NERC Lessons Learned Summary April 2015

NERC lessons learned published in April 2015 Two NERC lessons learned (LL) were published in April 2015 LL Detailed Installation and Commissioning Testing to Identify Wiring or Design Errors LL Severe Flooding Damages Transformer Substations

Detailed Installation and Commissioning Testing to Identify Wiring or Design Errors Two redundant RAS input/output (I/O) devices failed due to a firmware RAM/ROM processor error Failure alarms undetectable due to an error on the wiring diagram Positive DC did not get connected properly which disabled the signaling of the I/O device’s alarm status Wiring diagram did not match schematic Commissioning records show alarms were tested No indication of the test used Entity assumes the alarms were simulated using remote confirmation

Detailed Installation and Commissioning Testing to Identify Wiring or Design Errors Corrective Actions: Wiring diagram was corrected and DC rewired Alarms operationally checked and proven Webinar for field relay techs Covered print review, alarm verification, and checkout process

Detailed Installation and Commissioning Testing to Identify Wiring or Design Errors Lessons: Detailed checkout and commissioning process Regular review and training Comprehensive alarm simulation Peer review during design process Strong emphasis on Human Performance Standardized RAS checkout procedures are needed

Severe Flooding Damages Transformer Substations A storm in the Northeast resulted in record rainfall (~5 inches) 3.5 inches fell within a span of two hours Severe localized flooding of two transformer stations Stations and all terminating circuits rendered unavailable Monitoring, protection, and control equipment is located below grade in basements Damaged equipment and caused misoperation of relay systems that removed kV and kV connected circuits from operation Interrupted 3,800 MWs of Load for several days

Severe Flooding Damages Transformer Substations Corrective Actions Sandbags were applied to window wells as a temporary repair Properly sealed cable conduit Some equipment was relocated above-grade Floor drain check valves verified Both transformer stations are now equipped with gas-fired pumps, hoses and fittings, and fuel to control storm water ingress in all control and relay rooms

Severe Flooding Damages Transformer Substations Lessons: Identify stations with critical power system equipment located below grade and verify: Floor drain check valves; sump pits or pumps; and diesel generator capability to power sump pumps Flood protection equipment should be verified during station inspections Consider relocating all replacement or new critical power system equipment in above-grade locations New and replacement cable conduit supplying critical power system equipment should enter the building via above-grade entrances Below grade cable penetrations need routine inspection

Link to Lessons Learned Directions to Lessons Learned: Go to > “Program Areas & Departments” tab > “Reliability Risk Management” (left side menu) > “Event Analysis” (left side menu) > “Lessons Learned” (left side menu) NERC’s goal with publishing lessons learned is to provide industry with technical and understandable information that assists them with maintaining the reliability of the bulk power system. NERC requests that industry provide input on lessons learned by taking the short survey. The survey link is provided on each Lesson Learned.

Questions?