1 Sunrise Powerlink and Southwest Powerlink Reliability Performance Evaluation Double Line Outage Probability Analysis March 6, 2008.

Slides:



Advertisements
Similar presentations
West of McNary Generation Integration Project
Advertisements

Southwest Rhode Island Transmission Supply Study Long Term Needs and Solutions.
2004 NERC, NPCC & New England Compliance Programs John Norden Manager, Operations Training, Documentation & Compliance August 31, 2003 RC Meeting.
WECC Board of Directors April 21-23, 2004 Seattle, Washington WECC Procedure for Reporting of System Events Disturbance Reports Rod Maslowski OC Vice Chairperson.
Report of the Planning Coordination Committee WECC Board Meeting Albuquerque, NM December, 2007.
CPUC Vision for Transmission Planning in the West Dian M. Grueneich, Commissioner California Public Utilities Commission Western Electricity Coordinating.
Summary of Second Draft of the NERC Standard PRC Disturbance Monitoring and Reporting JSIS Meeting August 10, 2010 Salt Lake City, UT.
Central California Clean Energy Transmission Project
Central California Clean Energy Transmission Project PCC Meeting Vancouver, BC October 24, 2007.
PCC Update Presentation to TEPPC June 2010 Dana Cabbell PCC Chair.
TRDTF Transmission Reliability Database Task Force Update & Approval Vote Brian Keel SRP
Remedial Action Scheme Reliability Subcommittee, RASRS WECC Operating Committee June 18-19, Gene Henneberg.
Operating Reserves --- Again A Discussion Primer
WECC TRD/NERC TADS Webinar
1 Report of the Planning Coordination Committee WECC Board of Directors Meeting April 21, 2006 San Diego, CA.
Report of the Planning Coordination Committee December 2006 WECC BOD Meeting Cabo Del Sol, Los Cabos.
1 MSRATF Update to TSS (Modeling SPS and RAS Ad Hoc Task Force) Scope of Work Approval January 25, 2013 Joe Seabrook Puget Sound Energy.
WECC Standards Committee Joint Session
Report of the Planning Coordination Committee WECC Board Meeting San Diego, CA April, 2009.
WECC System Performance Criteria 1st Team Meeting Background
Operating Transfer Capability Policy Committee Report Board of Directors Meeting April 21 & 23, 2004 Thomas A. Delawder OTCPC Chair Western Electricity.
RPEWG REPORT June 2002 PCC Meeting James Leigh-Kendall.
Icfi.com 1 Framework for Determining Separation Distances Between Transmission lines in Wyoming icfi.com © 2008 ICF International. All rights reserved.
ACE Diversity Interchange (ADI)
WECC Operating Committee and Planning Coordinating Committee Brian K. Keel Chair – Reliability Subcommittee June 18 & 19, 2009 WECC Reliability Subcommittee.
Industry Brainstorm on increasing Export Capacity From Alberta to B.C. January, 2006.
FERC Order minute Scheduling.
Reliability Subcommittee Report Vishal C. Patel Chair – Reliability Subcommittee March 2014.
7. PV System Sizing Herb Wade Consultant
Jerry Rust Chair - Underfrequency Load Shedding Criterion Team
WECC Planning Coordinating Committee Brian K. Keel Chair – Reliability Subcommittee June, 2010 WECC Reliability Subcommittee Report.
Marv Landauer Report to TSS on RS Activities April 25-27, 2012 Salt Lake City.
Gene Henneberg RAS Criterion Drafting Team Chair WECC Reliability Subcommittee’s RAS Criterion Concerns 4/28/2011 San Diego, California.
RPEWG Present and Future Activities Boise, August 17, 2011 RPEWG Meeting 1.
MARKET INTERFACE COMMITTEE OC and PCC Approval Items March 6-7, 2008 Albuquerque, New Mexico.
TransWest Express and Gateway South WECC Planning Coordination Committee David Smith, National Grid October 25-26, 2007 Vancouver, B.C.
BAL-001-TRE-1 Primary Frequency Response Update for Texas RE RSC
North American Electric Reliability Council 1 Coordinate Operations Standard Jason Shaver Standard Drafting Team Chair September 29, 2005.
Underfrequency Load Shedding Assessment Report Kent Bolton January 30, 2014 JGC Meeting SLC, UT.
RAT R1 R2 R3 R4 R5 R6 R7 Fetch Q RS MOB ROB Execute Retire.
Goshen Area Bus Reconfiguration
April 15 and May 15, 2003 ERCOT System Disturbances ERCOT TAC Meeting June 4, 2003.
KURTEN SWITCH PROJECT (BRYAN/ COLLEGE STATION AREA UPGRADES) Technical Advisory Committee December 1, 2005 Transmission Services.
January 5, 2012 TAC Cross Valley 345 kV Project Jeff Billo Manager, Mid-Term Planning.
WECC and NERC Protection Criteria and Standards
2001 & 2002 Energy Preparedness Tucson Electric Power February 16, 2001 Michael Flores, Manager Control Area Operations David Hutchens, Manager Wholesale.
IMPERIAL VALLEY CONFERENCE July 21, SOLICITATION RENEWABLES PORTFOLIO STANDARD.
ISO Grid Planning Presentation to CREPC October 1, 2002
Charles Hosken, General Manager Imperial Irrigation District
Recommendations from 2011 Southwest Outage Heather Polzin, FERC Office of Enforcement Dave Nevius, Senior Vice President, NERC Member Representatives Committee.
December 7, 2012 ERCOT Planning Horizon SOL Methodology Update Jeff Billo RPG.
Lyndonville Electric Department Feasibility Analysis Review December 2,
LAREDO PLANT RMR EXIT STRATEGY Presentation to Board of Directors March 16, 2004 Transmission Services Operations.
March 11, 2011 RPG Meeting Lower Rio Grande Valley (LRGV) Import.
Current Export Initiatives Jerry Mossing Exports Workshop February, 16,2006, Metropolitan Center, Calgary.
JACKSBORO TO WEST DENTON and WEST LEVEE TO NORWOOD 345-kV PROJECTS April 20, 2004 Transmission Services Operations.
Operating Guide and Planning Guide Revision Requests Blake Williams, ROS Chair September 13, 2012.
© 2000 PACIFICORP kV LINE WALLA WALLA – WALLULA – Mc NARY 500 kV LINE HEMINGWAY – CAPTAIN JACK – REGIONAL PLANNING MEETING REGIONAL PLANNING PROJECT.
TRANSMISSION INFRASTRUCTURE IMPROVEMENTS — Current Projects — The Center for the New West “ The Sun Valley Energy Roundtables 2006” November 30 – December.
Cooperation on Regional Siting: How Is It Working - A California Perspective Dian M. Grueneich, Commissioner California Public Utilities Commission National.
June 26, 2008 Technical Advisory Committee American Electric Power Service Corporation Presidio Area Reliability Improvements Project James Teixeira Manager,
Barrilla Junction Area Transmission Improvements Project
Kenneth Silver Los Angeles Department of Water & Power
Proposal to Remove from Service the PV-COI RAS
HARRY ALLEN TRANSFORMER REMEDIAL ACTION SCHEME (RAS)
HARRY ALLEN TRANSFORMER REMEDIAL ACTION SCHEME (RAS)
Daniel J Marquis PNM Transmission Engineering
Palo Verde-COI RAS Retirement
Proposal to Remove from Service the PV-COI RAS
Palo Verde-COI RAS Retirement
Presentation transcript:

1 Sunrise Powerlink and Southwest Powerlink Reliability Performance Evaluation Double Line Outage Probability Analysis March 6, 2008

2 RPEWG and RS Recommendation After reviewing SDG&Es report, both the RS and RPEWG recommend that the proposed path (4 miles – 12 towers) for the Sunrise Powerlink and Southwest Powerlink double line outage analysis be approved for the category upgrade to Category D with cascading allowed.

3 Step 1: Project (Facility) Description SDG&E has proposed a new 500 kV transmission line called the Sunrise Powerlink (SRPL) that will connect the existing Imperial Valley substation, near El Centro, California to a new Central substation located in a central part of San Diego County. The proposed path for the Sunrise Powerlink would be in the same right of way as the Imperial Valley - Miguel line for approximately 4 miles. This route would contain approximately 12 towers. Step 1Step 2Step 3Step 4Step 5Step 6Step 7

4 Proposed and Alternative Paths Proposed Path – approximately 4 miles Alternative Path – approximately 36 miles

5 12 Tower Structures Step 1Step 2Step 3Step 4Step 5Step 6Step 7 Tower 50281Tower 50280Tower Tower 50273Tower 50276Tower 50274Tower Tower 50277Tower Tower 50272Tower 50271Tower 50270

6 Step 2: Outage Database – The Sample SWPL is SDG&Es only 500 kV transmission line, therefore outage data was collected on the Imperial Valley - Miguel portion of SWPL. With thirteen years of outage data ( ) available, SDG&E concluded that of the 44 forced outages on the Imperial Valley - Miguel line there was only one event that occurred on the proposed shared right of way during these years. SDG&E determined that using historical 500 kV data from the Palo Verde Hub to North Gila Performance Category Upgrade Request report by Arizona Public Service (APS) would be appropriate. Step 1Step 2Step 3Step 4Step 5Step 6Step 7

7 Step 3: Zero Events - Corrected MTBF MTBF is 928 years P T, P L, and P H are calculated using zero(0) events. SDG&E feels that after reviewing the data from the Robust Line Design, the MTBF will tend towards this value. Step 1Step 2Step 3Step 4Step 5Step 6Step 7

8 One Event - Corrected MTBF MTBF is 21 years P T, P L, and P H are calculated using one (1) event. The reason that there are two sets of values for the MTBF, is because there is not enough data to calculate definite values. Step 1Step 2Step 3Step 4Step 5Step 6Step 7

9 Step 4: Risk Factor Summary RiskRisk Factor R1Fire affecting both linesLow Risk R2One tower falling into another lineLow Risk R3Conductor from one line being dragged into another lineLow Risk R4Lightening strikes tripping both linesLow Risk R5Aircraft flying into both linesLow Risk R6Station related problems resulting in loss of two lines for a single eventLow Risk R7Natural disastersLow Risk R8Loss of two lines due to an overhead crossingLow Risk R9Loss of two lines due to vandalism/malicious actsLow Risk R10Flashover to vegetationLow Risk R11Single breaker failure causing loss of two linesLow Risk Step 1Step 2Step 3Step 4Step 5Step 6Step 7

10 The exposure to the system is estimated to be, at worst case, 675 hours per year or 7.71% per year, based on planning scenarios. However, the likelihood of this exposure due to operational conditions will be significantly less Step 5: Exposure Analysis Step 1Step 2Step 3Step 4Step 5Step 6Step 7

11 The results of the analysis indicated that to meet Category C criteria, a load drop scheme to reduce SDG&E import to approximately 3100 MW would be required for the N-2 loss of both 500 kV lines. Thus, from an SDG&E import level of 4100 MW, approximately 1000 MW would need to shed. The limiting factors are the thermal ratings of lines in CFE and SCE. Possible voltage collapse was seen when imports were above 3700 MW. Step 6: Consequence of an Outage Step 1Step 2Step 3Step 4Step 5Step 6Step 7

12 Step 7: Report Step 1Step 2Step 3Step 4Step 5Step 6Step 7

13 Performance Evaluation Conclusions The Proposed Path was recommended for Category D with cascading because: Probability of occurrence is extremely low as indicated by MTBF and Robust Line Design analysis. Cascading may occur under planning scenarios, but is not expected during normal operating conditions. SDG&E importing approximately 4100 MW in 2010, 5000 MW load, and only 900 MW of internal generation. SDG&E internal generation capability is expected to be almost 3000 MW in With an additional 400 MW of generation online the possibility of cascading was significantly reduced The proposed path is in the same right of way for 4 miles(12 towers). The lines terminate at separate substations on the west end. The lines will have diverse and redundant relaying schemes.

14 Project Timeline RPEWG Approval December 19, 2007 Reliability Subcommittee Approval January 10, 2008 Planning Coordination Committee March 6, 2008 WECC Board of Directors April 2008

15 Questions Deepika Sagi –