Transitional PSD Applicability Scenarios July 20, 2010 Jay Hofmann President trinityconsultants.com Troutman Sanders/Trinity Consultants PSD and Title.

Slides:



Advertisements
Similar presentations
New Source Review NSR Reforms Oklahoma Department of Environmental Quality Air Quality Council Presented by Matt Paque, Attorney, ODEQ - AQD April 20,
Advertisements

Copyright Holland & Hart LLP All Rights Reserved. The Deseret Power Case and Implications for CO2 Regulation Under the Clean Air Act Presented by.
GHG Applicability Criteria. Introduction to PSD GHG Applicability As stated earlier, Tailoring Rule does not change basic applicability process Incorporation.
Alabama Dept of Public Health New Onsite Regulations Overview of Permitting Requirements.
New Federal Regulations for Internal Combustion Engines Doug Parce.
Child Status Protection Act (CSPA) References: –PL , effective 08/06/2002 –INA 101(b)(1), 203(d) & 203(h) –AFM 21.2(e) –April 30, 2008 memo from.
1 The US EPA GHG Tailoring Rule – The Actual Regulatory Language.
1 Katy R. Forney Energy Sector Technical Authority Air Permits Section EPA Region 4 PSD and Title V Greenhouse Gas Tailoring Rule 14 th Annual Power Generation.
What options do states have? What is Georgia planning to do? What are some of the other states doing? What are the possible implications to permit fees?
Response to Comments on HAR Amendments Clean Air Branch Greenhouse Gas Rules Stakeholders Meeting 10/18/2013.
NCMA Workshop March 24, 2015 Booker Pullen Supervisor, Permitting Section North Carolina Division of Air Quality, Raleigh, NC (919) Permitting.
Florida Department of Environmental Protection Nonattainment Area New Source Review Updates Rule Development Workshop Chapters and October.
Overview of the Tribal New Source Review (NSR) Rule U.S. Environmental Protection Agency Office of Air Quality Planning and Standards (OAQPS) Research.
The world’s leading sustainability consultancy Generic Front Cover What’s this layout for? This is the generic slide front cover, but you can also make.
1 PSD - Case #1 Case #1: –A simple cycle natural gas power plant with PTE NOx of 300 tpy and GHGs of 150,000 tpy CO2e receives a PSD permit addressing.
GHG Regulations Update AWMA Southern Section September 12, 2012 Biloxi, MS Katy R. Forney Energy Sector Technical Authority EPA – Region 4 Atlanta, Georgia.
AWMA – Georgia Chapter Air Permitting Update April 16, 2013 Eric Cornwell Stationary Source Permitting Program.
Indiana New Source Review Reform Plantwide Applicability Limitations (PALs) IDEM/Office of Air Quality September 7, 2004.
Georgia Environmental Protection Division Stage II Gasoline Vapor Recovery Decommissioning Workshop June 11, 2014 EPD Tradeport Training Room.
10/1/ Air Quality Permitting Air Quality Committee William D. Willets, P.E. Engineering Supervisor DAQ Permitting Section May 7, 2014.
August 4, 2011 Heather Ceron US EPA Region 4 1. Greenhouse Gases 2.
Proposed Rulemaking 25 Pa. Code Chapter 121. General Provisions Chapter 127 Subchapter E. New Source Review John Slade, Chief Division of Permits Bureau.
Greenhouse Gas (GHG) Permit Training Region 4 – Atlanta, GA Dec , 2010.
Greenhouse Gases (GHGs) and You 1. The Regulated GHGs CO 2 (Carbon Dioxide) CH 4 (Methane) N 2 O (Nitrous Oxide) SF 6 (Sulfur Hexafluoride) HFCs (Hydrofluorocarbons)
Kimberton, PA | Kennesaw, GA | Strategic Air Planning: Is the Time for a PAL Here? Mark Wenclawiak, CCM|
Welcome Revisions of Chapter WAC Sections -035 and -036 Rule advisory committee workshop #5 Lacey, WA October 28, 2009.
2008 SPCC Rule Amendments 2008 SPCC Rule Amendments Donald P Smith US Environmental Protection Agency Region VI May, 2009 Current Status.
Sound solutions delivered uncommonly well Understanding the Permitting Impacts of the Proposed Ozone NAAQS Pine Mountain, GA ♦ August 20, 2015 Courtney.
1. Carbon dioxide (CO 2 ) – Naturally occurring and man- made. 5,505.2 mmts emitted in 2009, GWP = 1 Methane (CH 4 ) - Naturally occurring and man-made.
Change picture on Slide Master The Climate Change Scene in Washington Georgia Traditional Manufacturers Association LaGrange, GA November 5, 2009 PRESENTED.
1 Public Involvement, Access, and Petitions DJ Law EPA Region 8.
Best Available Retrofit Technology Rule - Colorado David R. Ouimette Colorado Air Pollution Control Division.
Georgia’s 112(g) Experiences Eric Cornwell Acting Manager Permitting Program.
Greenhouse Gas (GHG) Permit Training Other Aspects of PSD Title V Permitting.
Greenhouse Gas (GHG) Permit Training PSD Applicability Example Landfill Applicability Examples John Calcagni, EPA Region 4.
Jessica Montanez Environmental Protection Agency NEW SOURCE REVIEW (NSR) PROGRAM.
1 Non-Attainment NSR Program Donald Law EPA Region 8.
REGULATIONS & LEGISLATION BIG TEN ENVIRONMENTAL STEWARDSHIP GROUP STEVE MARUSZEWSKI – PENN STATE Greenhouse Gases.
Fred P. Osman, P.E. Osman Environmental Solutions Harrisburg, PA April 21, 2011.
1 Permit Exemptions Rule Revisions North Carolina Division of Air Quality Permit Exemptions Rule Revisions North Carolina Division of Air Quality Air Quality.
New Source Review Rules Update Jessica Montanez U.S. Environmental Protection Agency Office of Air Quality Planning and Standards Air Quality Policy Division.
Emissions Banking and Trading (EBT) Overview/Update Melissa Ruano Air Quality Division Texas Commission on Environmental Quality Advanced Air Permitting.
1 NSR Rule Review and Guidance 25 Pa. Code, Chapter 121. General Provisions Chapter 127 Subchapter E. New Source Review The Allegheny Mountain Section.
Permitting and National Ambient Air Quality Standards Changes Rick Goertz, P.E. Air Permits Division Texas Commission on Environmental Quality Advanced.
Greenhouse Gas Tailoring Rule aka GHG Permitting Rule.
MassDEP Response to EPA GHG Initiatives SIP Steering Committee January 13, 2011 Marc Wolman.
Update on EPA’s Greenhouse Gas Rulemakings Norman W. Fichthorn Hunton & Williams LLP 2010 American Public Power Association Energy and Air Quality Task.
Update on Methane Regulations Affecting Landfills Pat Sullivan Senior Vice President SCS Engineers Nov. 10, 2015.
2005 NSR Regulation Changes Dwight Wylie. Old Units vs. New Units  There is a broad disparity between air pollution control requirements and emissions.
Aggregation Issues Jesse Lovegren, Ph.D. Air Permits Division Texas Commission on Environmental Quality Advanced Air Permitting Seminar 2015.
New Source Review Reform & the PAL Tom Wood September 18,2003.
CEQA and Climate Change Evaluating & Addressing GHG Emissions from Projects Barbara Lee, CAPCOA.
1 Anna Marie Wood Acting Director, Air Quality Policy Division Office of Air and Radiation Office of Air Quality Planning and Standards May 2010 Prevention.
Nonattainment New Source Review (NA NSR) Program Raj Rao US Environmental Protection Agency Office of Air Quality Planning and Standards ,
HIPAA Privacy Rule Positive Changes Affecting Hospitals’ Implementation of the Rule.
Senate Bill 288- Limits Changes to Air Districts’ New Source Review Rules Beverly Werner, Manager Stationary Source Division California Air Resources Board.
Perspective on Contingency Mitigation Options Presented by John Annicchiarico, Senior Engineer August 17, 2015.
Tailoring Rule - Title V Scenarios July 20, 2010 Katherine N. Blue Principal Consultant, Climate Change Services trinityconsultants.com Troutman Sanders/Trinity.
Climate: ANPR, SIPs and Section 821 WESTAR October 2, 2008.
HIPAA Privacy Rule Positive Changes Affecting Hospitals’ Implementation of the Rule Melinda Hatton -- Oct. 31, 2002.
PSD Background Presentation
Clean Air Act Glossary.
EPA Regulation of Greenhouse Gases: The View from Washington Troutman Sanders LLP/Trinity Consultants July 20, 2010 PRESENTED BY Peter Glaser Troutman.
Final Rulemaking Nonattainment Source Review 25 Pa. Code, Chapter 121
Major New Source Review (NSR) Part 2
Julie Woosley, Division of Waste Management
TRTR Briefing September 2013
Status of RMRR or learning the definition of “routine”…
SIA in US Legislative Update Shanghai, China
Navajo Nation Minor Source Regulations
Presentation transcript:

Transitional PSD Applicability Scenarios July 20, 2010 Jay Hofmann President trinityconsultants.com Troutman Sanders/Trinity Consultants PSD and Title V Tailoring Rule Seminar

Overview  Six PSD Applicability Transition Scenarios  Scenario A – Existing Minor Source (will become major due to a plant expansion project sometime in the future)  Scenario B – Existing Minor Source (will become major on July 1, 2011 due to GHG emissions and the Tailoring Rule) – Minor modification permit applications pending  Scenario C – Existing Major Source – Pending PSD application  Scenario D – Existing Major Source – Minor modification permit issued and actual construction will begin prior to January 2, 2011  Scenario E – Existing Major Source – PSD permit issued just prior to January 2, 2011 – Actual Construction will not begin until March, 1, 2012  Scenario F – Existing Minor Source (will become major on July 1, 2011 due to GHG emissions) – Pending project to be issued authorization to construct prior to July 1, 2011

Scenario A  Site is an existing minor source for PSD  Owners currently planning a project that is minor and no permit limits at the source will be changed  After the project, site will be a major source  Will the Tailoring Rule directly impact the planned project for PSD purposes?

Scenario A (Cont.)  Minor sources can not trigger PSD unless the project results in the relaxation of an existing synthetic minor limit (a PSD “(r)(4)” limit) or the project is major “in and of” itself  Tailoring rule transition will not impact this project.  After the project, site will be major and future modifications maybe impacted by PSD

Scenario B  Site an existing minor source for PSD.  Site will become major due to Tailoring Rule (GHG emissions above thresholds on a mass and GWP basis) as of July 1,  Any permit applications pending as of July 1, 2011 for plant modifications, will need to be evaluated for PSD applicability  A similar situation is addressed in Scenario F

Scenario C  Site is an existing major source for PSD  A PSD application has been submitted and construction authorization/permit modification is pending  Permit application did not address GHG  Permit must be finalized and issued prior to January 2, 2011, else owner must address PSD GHG applicability  What if actual construction has not begun prior to January 2, 2011? Scenario E

Scenario D  Site is an existing major source for PSD  Minor modification permit application submitted and the construction authorization is pending – Authorization will be finalized and permit issued prior to January 2, GHG not addressed in application  Site expects to begin actual construction prior to January 2, 2011  Issues?

Scenario E  Site is an existing major source for PSD  PSD applicable project construction authorization (without consideration of GHG) issued on December 28, 2010  Project’s net emissions increase of GHG is more than 75,000 tpy (GWP basis) and more than 0 tpy (mass basis)  Actual construction not expected to begin until March 1, 2012

Scenario E (cont.)  Construction authorization contains the following language: “Approval of construction shall become invalid if construction is not commenced within 18 months after receipt of such approval, if construction is discontinued for a period of 18 months or more, or if construction is not completed within a reasonable time.”

Tailoring Rule Preamble – Step 1  EPA’s Step 1 Transitional Guidance – No “Grandfathering”  “We are not promulgating an exemption for PSD permit applications that are pending when Step 1 of the permitting phase-in begins for those sources that would otherwise need to obtain a PSD permit based on emissions of pollutants other than GHGs. Any PSD permits issued to such Step 1 sources on or after January 2, 2011 will need to address GHGs.”  “Final PSD permits issued before January 2, 2011 need not be reopened or amended to incorporate requirements for GHGs that take effect after the permit is issued.”  “A source that is authorized to construct under a PSD permit but has not yet begun actual construction on January 2, 2011 may begin actual construction after that date without having to amend the previously-issued PSD permit to incorporate GHG requirements, provided the permit has not expired.”

Scenario E Probably “OK” with respect to GHG

Scenario F  Site is an existing minor source for PSD  Site will become a major source for PSD after July 1, 2011, due to existing GHG emissions and the Tailoring Rule (Step 2)  Pending project expects construction authorization to be issued prior to July 1, 2011  Issues?

Tailoring Rule Preamble – Step 2  EPA’s Step 2 Transitional Guidance – No “Mercy”  “Sources that are not subject to PSD permitting requirements until Step 2 need not obtain a PSD permit addressing GHGs in order to continue any actual construction that begins before July 1, 2011, when such a source was not a major stationary source required to obtain a PSD permit.”  “However, Step 2 sources that begin actual construction in Step 2 may do so only after obtaining a PSD permit.”

Tailoring Rule Preamble – Step 2 (cont)  A picture is sometimes worth a thousand words…….

“Begin Actual Construction”  Begin actual construction - means, in general, initiation of physical on-site construction activities on an emissions unit which are of a permanent nature. Such activities include, but are not limited to, installation of building supports and foundations, laying underground pipework and construction of permanent storage structures. With respect to a change in method of operations, this term refers to those on-site activities other than preparatory activities which mark the initiation of the change.

Scenario F Site will need to begin actual construction prior to July 1 to be certain to avoid GHG requirements