1 PSD - Case #1 Case #1: –A simple cycle natural gas power plant with PTE NOx of 300 tpy and GHGs of 150,000 tpy CO2e receives a PSD permit addressing.

Slides:



Advertisements
Similar presentations
New Source Review NSR Reforms Oklahoma Department of Environmental Quality Air Quality Council Presented by Matt Paque, Attorney, ODEQ - AQD April 20,
Advertisements

New Source Review (NSR) Program Basics
Richard (Rick) Goertz, P. E
Identification of BART-Eligible Sources in the WRAP Region A Summary of the April 4, 2005 Draft Report.
1 Year in Review: Climate Change Presented by: Tom Wood Stoel Rives LLP October 8, 2010 EPA Heats Things Up.
GHG Applicability Criteria. Introduction to PSD GHG Applicability As stated earlier, Tailoring Rule does not change basic applicability process Incorporation.
1 The US EPA GHG Tailoring Rule – The Actual Regulatory Language.
1 Katy R. Forney Energy Sector Technical Authority Air Permits Section EPA Region 4 PSD and Title V Greenhouse Gas Tailoring Rule 14 th Annual Power Generation.
What options do states have? What is Georgia planning to do? What are some of the other states doing? What are the possible implications to permit fees?
Response to Comments on HAR Amendments Clean Air Branch Greenhouse Gas Rules Stakeholders Meeting 10/18/2013.
NCMA Workshop March 24, 2015 Booker Pullen Supervisor, Permitting Section North Carolina Division of Air Quality, Raleigh, NC (919) Permitting.
NCMA Workshop March 19 and 24, 2015 Betty Gatano, P.E. Permitting Section North Carolina Division of Air Quality, Raleigh, NC (919)
Air Permitting Overview.
New Source Review (NSR) Program Basics and Highlights of the Proposed Tribal Major Nonattainment and Minor NSR Rules Laura McKelvey, Jessica Montañez,
Air Construction Permitting Services Sarah Piziali, Construction Permit Section Supervisor.
Overview of the Tribal New Source Review (NSR) Rule U.S. Environmental Protection Agency Office of Air Quality Planning and Standards (OAQPS) Research.
Clean Air Act and Permits
Transitional PSD Applicability Scenarios July 20, 2010 Jay Hofmann President trinityconsultants.com Troutman Sanders/Trinity Consultants PSD and Title.
AWMA – Georgia Chapter Air Permitting Update April 16, 2013 Eric Cornwell Stationary Source Permitting Program.
Indiana New Source Review Reform Plantwide Applicability Limitations (PALs) IDEM/Office of Air Quality September 7, 2004.
10/1/ Air Quality Permitting Air Quality Committee William D. Willets, P.E. Engineering Supervisor DAQ Permitting Section May 7, 2014.
CANDACE CARRAWAY OFFICE OF AIR QUALITY PLANNING AND STANDARDS US EPA JUNE 2013 General Permits and Permits by Rule 1.
Air Quality Policy Division D P A Q PM 2.5 Final NSR Implementation Rule Nat’l Tribal Air Assoc. July 16, 2008.
Greenhouse Gas (GHG) Permit Training Region 4 – Atlanta, GA Dec , 2010.
Bill Harnett March 30, 2010 WESTAR Spring Meeting.
John A. Paul RAPCA. Background  Supreme Court Decision  Endangerment Finding  Johnson Memorandum  Light Duty Vehicle GHG Emissions Rule  Tailoring.
Kimberton, PA | Kennesaw, GA | Strategic Air Planning: Is the Time for a PAL Here? Mark Wenclawiak, CCM|
Welcome Revisions of Chapter WAC Sections -035 and -036 Rule advisory committee workshop #5 Lacey, WA October 28, 2009.
Sound solutions delivered uncommonly well Understanding the Permitting Impacts of the Proposed Ozone NAAQS Pine Mountain, GA ♦ August 20, 2015 Courtney.
1. Carbon dioxide (CO 2 ) – Naturally occurring and man- made. 5,505.2 mmts emitted in 2009, GWP = 1 Methane (CH 4 ) - Naturally occurring and man-made.
ANPR: Transition to New or Revised PM NAAQS WESTAR Business Meeting March 2006.
Best Available Retrofit Technology Rule - Colorado David R. Ouimette Colorado Air Pollution Control Division.
Georgia’s 112(g) Experiences Eric Cornwell Acting Manager Permitting Program.
Greenhouse Gas (GHG) Permit Training Other Aspects of PSD Title V Permitting.
Overview of Air Permitting Fees In Illinois
Greenhouse Gas (GHG) Permit Training PSD Applicability Example Landfill Applicability Examples John Calcagni, EPA Region 4.
Jessica Montanez Environmental Protection Agency NEW SOURCE REVIEW (NSR) PROGRAM.
1 Non-Attainment NSR Program Donald Law EPA Region 8.
PSD/Nonattainment Review You can do this! Marc Sturdivant Air Permits Division Texas Commission on Environmental Quality Environmental Trade Fair 2015.
1 Permit Exemptions Rule Revisions North Carolina Division of Air Quality Permit Exemptions Rule Revisions North Carolina Division of Air Quality Air Quality.
New Source Review Rules Update Jessica Montanez U.S. Environmental Protection Agency Office of Air Quality Planning and Standards Air Quality Policy Division.
Title V, Preliminary Completeness Review. What do I need to do?  I need to find out if the application contains the required information.  Initial Title.
Emissions Banking and Trading (EBT) Overview/Update Melissa Ruano Air Quality Division Texas Commission on Environmental Quality Advanced Air Permitting.
A&WMA Southern Section Annual Meeting Biloxi, MS September 12, 2012 Carla Brown, P.E. MS Dept. of Environmental Quality
1 NSR Rule Review and Guidance 25 Pa. Code, Chapter 121. General Provisions Chapter 127 Subchapter E. New Source Review The Allegheny Mountain Section.
Permitting and National Ambient Air Quality Standards Changes Rick Goertz, P.E. Air Permits Division Texas Commission on Environmental Quality Advanced.
Greenhouse Gas Tailoring Rule aka GHG Permitting Rule.
MassDEP Response to EPA GHG Initiatives SIP Steering Committee January 13, 2011 Marc Wolman.
Update on EPA’s Greenhouse Gas Rulemakings Norman W. Fichthorn Hunton & Williams LLP 2010 American Public Power Association Energy and Air Quality Task.
2005 NSR Regulation Changes Dwight Wylie. Old Units vs. New Units  There is a broad disparity between air pollution control requirements and emissions.
IDEM Update March 9, 2011 Office of Pollution Prevention & Technical Assistance Rick Bossingham, Assistant Commissioner.
Tribal Permitting Conference 2013 Steve Dunn, P.E., Construction Permit Team Leader; Bureau of Air Management (608) ;
NSR—Minor New Source Review Darrel Harmon U.S. EPA Office of Air and Radiation.
1 Anna Marie Wood Acting Director, Air Quality Policy Division Office of Air and Radiation Office of Air Quality Planning and Standards May 2010 Prevention.
Nonattainment New Source Review (NA NSR) Program Raj Rao US Environmental Protection Agency Office of Air Quality Planning and Standards ,
Tailoring Rule - Title V Scenarios July 20, 2010 Katherine N. Blue Principal Consultant, Climate Change Services trinityconsultants.com Troutman Sanders/Trinity.
NAAQS Status in GA & PSD Inventory Update James W. Boylan Georgia EPD – Air Protection Branch Manager, Planning & Support Program AWMA Regulatory Update.
Regulatory background How these standards could impact the permitting process How is compliance with the standards assessed.
PSD/Nonattainment Applicability Arturo J. Garza Air Permits Division Texas Commission on Environmental Quality Environmental Trade Fair 2016.
Climate: ANPR, SIPs and Section 821 WESTAR October 2, 2008.
PSD Background Presentation
New Source Review (NSR) Program Basics
Clean Air Act Glossary.
EPA Regulation of Greenhouse Gases: The View from Washington Troutman Sanders LLP/Trinity Consultants July 20, 2010 PRESENTED BY Peter Glaser Troutman.
Final Rulemaking Nonattainment Source Review 25 Pa. Code, Chapter 121
Overview of New Source Review (NSR)
Major New Source Review (NSR) Part 2
Air Quality Permitting
Major New Source Review (NSR)—Part 1
Navajo Nation Minor Source Regulations
Presentation transcript:

1 PSD - Case #1 Case #1: –A simple cycle natural gas power plant with PTE NOx of 300 tpy and GHGs of 150,000 tpy CO2e receives a PSD permit addressing NOx, but NOT GHGs on December 31, The facility is not planning to begin actual construction until after July 1, –Will the permit need to be reopened to address BACT for GHGs? Answer: –No. The facility was permitted under the PSD regulations prior to Step 1 (January 2, 2011) and it is allowed to proceed.

2 PSD – Case #2 Case #2 –Same simple cycle natural gas power plant as Case #1 with PTE NOx of 249 tpy and GHGs of 125,000 tpy CO2e receives a state issued permit making the facility a minor source under the PSD regulations for all criteria pollutants on December 31, The facility is not planning to begin actual construction until after July 1, –Will the facility have to get a PSD permit for this project before it can begin construction? Answer: –Yes. Followup – When applying for the PSD permit to address BACT for GHGs, will it also have to address PSD for any criteria pollutants (i.e. NOx) whose PTE exceeds the significant increase levels? Answer: –Yes - 40 CFR 52.21(2)(iii) – “No major source…shall begin actual construction without a permit that the source meets [PSD] requirements”

3 PSD - Case #3 Case #3 –Site is an existing minor source for PSD –Owners currently planning a project that is minor and no permit limits at the source will be changed –After the project, site will be a major source –Will the Tailoring Rule directly impact the planned project for PSD purposes? Answer: –Tailoring rule transition will not impact this project. –After the project, site will be major and future modifications maybe impacted by PSD –However; if project has GHG > 100,000 tons CO2e and begins actual construction after July 1, 2011, PSD applies (anything above SER)

4 PSD – Case #4 Case #4 –Site an existing minor source for PSD. –As of July 1, 2011, facility has PTE for GHGs > 100,000 tpy CO2e –Will this facility need to evaluate future modifications for potential PSD applicability? When? Answer: –For GHGs, any modification for pending applications, or projects permitted but not yet begun actual construction, as of July 1, 2011, will need to be evaluated for PSD applicability at the 75,000 tpy CO2e significance level If a project has GHGs > 75,000 tpy CO2e, then must also evaluate whether or not projects has other NSR regulated pollutants greater than their respective significance levels. –For non-GHGs, facility is still a minor source for PSD. GHG only becomes “subject to regulation” when a modification is over 75,000 tons CO2e.

5 PSD – Case #5 Case #5 –Site is an existing major source for PSD –A PSD application has been submitted and construction authorization/permit modification is pending –Permit application did not address GHG –When must permit be issued in order to avoid PSD GHG applicability? Answer: –Permit must be finalized and issued prior to January 2, 2011, or else owner must address PSD GHG applicability (compare to 75,000 tpy CO2e). –Bonus: What if actual construction has not begun prior to January 2, 2011? –Answer: No consequences. Project went through PSD and may proceed.

6 PSD – Case #6 Case #6 –Site is an existing major source for PSD –Minor modification permit application submitted and the construction authorization is pending –Authorization will be finalized and permit issued prior to January 2, GHG not addressed in application –Site expects to begin actual construction prior to January 2, 2011 –Issues? Answer: –If project has GHG emissions less than 75,000 tpy CO2e, then there are no issues. –If existing source has GHG PTE > 100,000 tpy CO2e, then if project has GHG emissions > 75,000 tpy CO2e, then project would have to begin actual construction prior to July 1, –If project itself had GHG PTE > 100,000 tpy CO2e, then project is subject to PSD for GHGs unless it begins actual construction prior to July 1, 2011.

7 PSD – Case #7 Case #7 –Site is an existing major source for PSD –PSD applicable project construction authorization (without consideration of GHG) issued on December 28, 2010 –Project’s net emissions increase of GHG is more than 75,000 tpy CO2e –Actual construction not expected to begin until March 1, 2012 –Issues? Answer: –As long as project commences construction within 18 months (existing PSD requirement), project may proceed.

8 PSD – Case #8 Case #8 –Site is an existing minor source for PSD –As of July 1, 2011, site has GHG PTE > 100,000 tpy CO2e –Pending project expects construction authorization to be issued prior to July 1, 2011 –Issues? Answer: –If project GHG PTE is less than 75,000 tpy CO2e, then no issues. –If project GHG PTE exceeds 75,000 tpy CO2e, then project is subject to PSD unless it begins actual construction prior to July 1, –Similar to Case #4

9 PSD – Case #9 Case #9 –Existing facility with PTE for GHG of 160,000 tpy CO2e (actual above 100,000 tpy CO2e). The facility is not PSD major for any other pollutant (all below 250 tpy each). –Contemplated change would be post-July 2011 and increase NOx more than 40 tons/year but would NOT increase GHG more than 75,000 tpy CO2e. –PSD triggered for NOx increase or not? Answer –No. GHG is not “subject to regulation” unless project increases GHG by 75,000 tons or more.

10 Title V – Case #1 Case #1 –Existing minor source that will become subject to Title V in Step 2 (GHG PTE >100,000 tpy CO2e on and after July 1, 2011) –When do they have to submit their Title V application? Answer: –Submit permit application within 12 months after the source becomes subject to the program – July 1, 2012

11 Title V – Case #2 Case #2 –Existing Title V major, pending application for Title V renewal under review by EPD when GHGs become subject to regulation in Step 2 (July 1, 2011) –What does source need to do? Answer: –Nothing –If additional requirements become applicable to a source, after submittal of renewal (but prior to draft permit), source must supplement its application (and ensure compliance at time of permit issuance). –However, at this point, it doesn’t appear that there will be any applicable requirements for GHGs at that time. –At this point we plan to ask sources to report their GHG PTE in Title V applications received after July 1, Sources should have the ability to report this information before then if they choose. EPD (Data Management Unit) working on revision to application at this time.

12 Title V – Case #3 Case #3 –Existing Title V major, getting a PSD permit modification that includes new GHG applicable requirements (under either Step 1 or Step 2) –What does source need to do with Title V permit? Answer: –Nothing. –Georgia’s SIP permitting and Title V permitting programs are merged for existing sources. Therefore, the PSD permit modification will simultaneously be a modification to the Title V permit.

13 Title V – Case #4 Case #4 –Existing minor source that will become subject to Title V in Step 2 (but wants to take a limitation to remain minor) –What does facility need to do? Answer: –Submit application requesting synthetic minor permit limitations to limit PTE to less than 100,000 tpy CO2e –Would need to have limitations in place prior to July 1, 2012 to avoid requirement to obtain Title V permit –Recommend that facility submit application by October 1, 2011 to give us enough time to process the synthetic minor permit application.