Economic Transmission Case Study: Champlain Wind Link Vermont System Planning Committee March 10, 2010.

Slides:



Advertisements
Similar presentations
Central Vermont Public Service SOUTHERN LOOP COOLIDGE CONNECTOR Coolidge Connector Community Working Group April 30, 2007.
Advertisements

Evaluation Independent Monitoring Presented at: LPSC Staffs Technical Conference and ESIs Bidders Conference for the Fall 2006 Limited-Term RFP September.
Electricity Industry The Potential Effect of Locational Marginal Pricing on Renewable Resources for Environmental Issues in Energy NECPUC Annual Symposium.
FLORIDA PUBLIC SERVICE COMMISSON WORKSHOP ON RENEWABLE PORTFOLIO STANDARDS JULY 26, 2007 BY E. LEON JACOBS, JR. WILLIAMS & JACOBS.
Order 2000 and PJM: A Natural Match Craig Glazer Manager of Regulatory Affairs PJM Interconnection, LLC.
Project Delivery Approaches for Wastewater Utilities in Minnesota June 24, 2008 Metropolitan Council Environment Committee.
Winter 2013/2014 Reliability Solution Including LNG MWHs N. Jonathan Peress Conservation Law Foundation Greg Lander Skipping Stone NEPOOL Markets & Reliability.
Demand Response in Connecticut Presented by: Bob Laurita ISO New England December 2, 2004.
Infrastructure Planning: Non-Transmission Alternatives 2010 NASUCA Mid-Year Meeting San Francisco, June 15, 2010 Drew Murphy NRG Executive Vice President.
The European Union’s CARDS programme for the Balkan region – Contract No This project is funded by the European Union Regional Electricity Balkan.
Coordinated Competitive Regional Renewable Power Procurement New England States Committee on Electricity May 16, 2013 Massachusetts Wind Working Group.
Responding to the Electricity Challenges: Five Point Plan Overview 19 December 2014 Confidential 1.
Kansas Renewable Energy and Energy Efficiency Conference Wind 2007 RFP Update John Grimwade - Sr. Director Strategic Planning and Development September.
1.  Purpose  To present Staff’s Preliminary Findings on the 2012 Integrated Resource Plans of:  APS – Arizona Public Service Company  TEP – Tucson.
1 Dale Osborn Midwest ISO February 27, Wisconsin Renewable Energy Summit Transmission Expansion Opportunities with Wind Energy.
Energy Planning and Recent Regulatory Developments Northwest Energy Systems Symposium (NWESS) University of Washington February 22, 2008 Nicolas Garcia.
Prospero LLC December 2, 2004 Connecticut’s Energy Future Financing Sustainable Energy.
Preliminary Analysis of the SEE Future Infrastructure Development Plan and REM Benefits.
BOSTON CHICAGO DALLAS DENVER LOS ANGELES MENLO PARK MONTREAL NEW YORK SAN FRANCISCO WASHINGTON Governors’ Wind Energy Coalition November, 2011 Competitive.
Demand Response in MISO Markets NASUCA Panel on DR November 12, 2012.
Long Term Study Task Force Update to ETWG ERCOT Long-Term Study: Scenarios, New Software, and Emerging Technology Assumptions January 27, 2012.
Results of Geothermal Power Survey of Electric G&T Cooperatives Robert Putnam, CH2M HILL Bob Gibson, NRECA Steve Lindenberg, Lindenberg Consulting.
North Eastham Wind Feasibility Study Results Brian Eastman Eastham Energy Committee Kristen Burke Massachusetts Technology Collaborative Ric O’Connell.
Increasing Access to the Grid NIPPC September 8, 2005 Brian Silverstein VP, Operations and Planning Bonneville Power Administration.
BUG Workshop People and Processes 23 February 2010 Scott Harvey
NREL is a national laboratory of the U.S. Department of Energy Office of Energy Efficiency and Renewable Energy operated by the Alliance for Sustainable.
EDP Renewables North America Massachusetts Wind Working Group March 15, 2013.
Energy Price Hedging Using Non-Fossil Fuel Generation Tuesday – June 7, 2005 Russ Sylva General Manager.
NREL is a national laboratory of the U.S. Department of Energy Office of Energy Efficiency and Renewable Energy operated by the Alliance for Sustainable.
1  The IPM model projects increases in electricity prices as a result of the RGGI policy scenarios which, by themselves, would increase the household.
The Regulatory Assistance Project 177 Water St. Gardiner, Maine USA Tel: Fax: State Street, Suite 3 Montpelier, Vermont.
IRP in Vermont Docket 7081 Workshop Sept. 13, 2005.
Demand Response: Keeping the Power Flowing in Southwest Connecticut Presented by: Henry Yoshimura Manager, Demand Response ISO New England September 30,
Preliminary Results with the Regional Portfolio Model Michael Schilmoeller for the Northwest Power and Conservation Council Generation Resource Advisory.
Bulk Power Transmission System
Linking the Wholesale and Retail Markets through Dynamic Retail Pricing Presented by: Henry Yoshimura Manager, Demand Response ISO New England September.
1 Clean Line Energy National Association of State Utility Consumer Advocates Charleston SC Annual Meeting June 2012.
Combined Heat and Power Workshop Report and Next Steps Power Committee Briefing 7/15/03.
1 Market Evolution Program Long-Term Resource Adequacy Regulatory Affairs Standing Committee Meeting May 14, 2003.
Competing For Advantage Chapter 4 – The Internal Organization: Resources, Capabilities, and Core Competencies.
American Public Power Association Pre-Rally Workshop February 28, 2006 Washington, D.C. Climate Change: Making Community-Based Decisions in a Carbon Constrained.
Forming a Cost Assignment/ Cost Recovery Team RMATS Steering Committee January 13, 2004.
Department of Marketing & Decision Sciences Part 5 – Distribution Wholesaling and Physical Distribution.
Proposed Analytical Approach - Modeling Phase 3 - Formation of new team December 9, 2003 Steering Committee Presentation.
Outage Planning Subcommittee Mark Wilson. Outage Planning Subcommittee Created to address Market Participant concerns with existing rules and procedures.
ERCOT TAC11/2/ CREZ Study Update ERCOT TAC 11/2/2006.
Economic Assessment of Implementing the 10/20 Goals and Energy Efficiency Recommendations – Preliminary Results Prepared for : WRAP, AP2 Forum Prepared.
G 200 L 200 ISO NEW ENGLAND T H E P E O P L E B E H I N D N E W E N G L A N D ’ S P O W E R. Southwest Connecticut RFP Markets Committee November 14, 2003.
RPG: September 24, Long-Term System Assessment Introduction Jeff Billo, Manager, Transmission Planning September 2013 Regional Planning Group.
Resource Analysis. Objectives of Resource Assessment Discussion The subject of the second part of the analysis is to dig more deeply into some of the.
California Energy Action Plan December 7, 2004 Energy Report: 2004 and 2005 Overview December 7, 2004.
UM 1751 Energy Storage Workshop #3 May 9, UM 1751 Workshop #3 Topics Most viable and beneficial applications (HB 2193 time frame: ) Emerging.
A Generation and Transmission Solution for the Clean Energy RFP
Overcoming Challenges to Green Power Markets Renewable Energy Certificates 2004 World Resources Institute Sustainable Enterprise Summit March 18, 2004.
ENERGY SERVICES RFP: COMMENT OVERVIEW Peninsula Clean Energy Authority March 31, 2016.
©2003 PJM 1 Presentation to: Maryland Public Service Commission May 16, 2003.
Integrated Resource Plan 2016
Toronto Waterfront Scan and Environmental Improvement Strategy Project - Economic Opportunity in a Sustainable Waterfront Presentation to the Federation.
Affordable Energy Production from Renewable Fuel
Procurement: Use of Metrics
Flexible Forward Contracts for Renewable Energy Generators
Electricity Procurement Options
December 9, 2005 Allison DiGrande, External Affairs Department, ISO/NE
Marginal Cost Pricing: Why Is It Important? Have We Achieved It?
Market Design in New England
New England Electricity Restructuring Roundtable September 18, 2009
Geographic Eligibility Under GIS and RPS
A Business Simulation for Corporate Finance Courses
Comments on New England Regional State Committee*
Portfolio Standards and the Supply of Renewable Energy in New England
Presentation transcript:

Economic Transmission Case Study: Champlain Wind Link Vermont System Planning Committee March 10, 2010

Champlain Wind Link (“CWL”) Potential project expanding PV-20 path  230kV into Vermont  Capital intensive, across control areas  Scoped/developed by VELCO and Anbaric Transmission, LLC Value proposition: several potential components Power supply working group  Initial thoughts on benefits/risks  Research & findings

Potential Value Components Power supply value to project owners/subscribers  Cost-effective power source, vs. New England alternatives Regional reliability benefits  NY Central-East interface  New England single-import limit Local (?) reliability benefits  Address needs that Vermont reliability projects would otherwise need to address Multiple facets  Each one complex  Multiple beneficiaries  Some winners & losers

Power Supply Working Group DU power supply staff, VELCO, Anbaric December 2009 to February 2010 Review the CWL from the perspective of a potential power supply resource  Not other considerations like system reliability, return on invested capital  Confidential Gather information about potential sources of power over the CWL Identify principal elements of the power supply value proposition, and associated risks

Working Group Goals Inventory benefits / risks unique to imported power over the proposed CWL Solicit indicative proposals from potential NY suppliers  Gauge types of available resources, approximate pricing & terms Conduct preliminary research on primary risks related to imports Screening-level assessment of potential viability & cost-effectiveness of purchasing new power supply resources over the CWL

Initial Thoughts: Potential Power Supply Benefits New York renewable resources  Perceived cost advantage of NY wind vs. equivalent New England wind  Access to additional renewable resources Access to lower-cost market power (energy & capacity) from northern NY  Price “spread” between the NY and NE markets Negotiating leverage vs. other potential suppliers

Initial Thoughts: Potential Power Supply Risks Uncertainty regarding permitting / timing of CWL versus capacity market and supplier contract timelines Complexity of the potential transactions (i.e., intermittent wind “firmed” by other resources) Issues related to imports & intermittent wind  Capacity market penalties applicable only to imports  Requirements for external resources to sell Renewable Energy Credits in New England  Potential scheduling penalties related to imports Future changes in market rules / rule differences between New York & New England

Request for Proposals Distributed to potential suppliers December 2009  Mix of generation owners and other market participants On behalf of the Vermont DUs, up to 150 MW Seeking long-term resources  Wind and “firming” power  Individually or together  Indicative proposals

Concept of Wind & “Firming” Power via the CWL

RFP Findings & Observations on Power Supply via CWL Didn’t find compelling power supply benefits  Not enough “spread” vs. New England options Other basis for expecting CWL power supply value?  Historical data & consultant projections indicate a wholesale price “spread” from northern NY to Vermont  But probably not enough to cover full CWL transmission costs The transaction concept (wind + firming from NY) is quite complex to evaluate and implement  Combination of intermittent resource & imports  A unique combination of transactions; outside the experience of Vermont DUs (and most market participants)

A Few Observations on Economic Transmission Importing power entails incremental risks (compared to resources internal to New England)  Capacity market, scheduling, REC eligibility  Many of these would not apply for an economic transmission project within New England If power supply value derives from proposed projects, timelines can present extra challenges  Proposed power plant, output to be transmitted via proposed CWL Substantial time & cost to evaluate  Project scoping & initial design  Transmission reliability/planning impacts  Power supply impacts for participants, non-participants  LMP effects  Multiple areas of expertise