Beam Delivery, MDI related updates Andrei Seryi for BDS Area GDE/LCWS meeting at Bangalore March 10, 2006.

Slides:



Advertisements
Similar presentations
Ideas and Speculations for the Headon Extraction Line L. Keller Oct. 19, Give up the 3.5 m Separation between the Charged Dump and the Incoming.
Advertisements

The ILC low power option Andrei Seryi SLAC ILC08 and LCWS08 November 17, 2008 Photo: Dan Chusid, 2003.
Question from the GDE : Could local “doughnut” type muon spoilers like those in SLC be substituted for the 5 meter magnetized wall? 5m magnetized wall.
Summary of the discussion for the commissioning session 2 nd ATF2 Project Meeting KEK, Tsukuba, Japan 6/ 1/ 2006 T.Okugi (KEK)
Zero Degree Extraction using an Electrostatic Separator Take another look at using an electrostatic separator and a weak dipole to allow a zero degree.
Global Design Effort Beam Delivery System & Machine Detector Interface Andrei Seryi, SLAC Annual DOE HEP Program Review June 11-14, 2007.
Summary of wg2a (BDS and IR) Deepa Angal-Kalinin, Shigeru Kuroda, Andrei Seryi October 21, 2005.
Beam Loss in the Extraction Line for 2 mrad Crossing Angle A.Drozhdin, N.Mokhov, X.Yang.
NLC - The Next Linear Collider Project NLC IR Layout and Background Estimates Jeff Gronberg/LLNL For the Beam Delivery Group LCWS - October 25, 2000.
PROBLEM: Radiation Dose Rate in IR2 When IR1 is Operating (and Vice Versa) Muon Dose Rate > 1 mRem/hr for 0.1% Collimated Halo.
K. Moffeit 6 Jan 2005 WORKSHOP Machine-Detector Interface at the International Linear Collider SLAC January 6-8, 2005 Polarimetry at the ILC Design issues.
CF Constraints to the Strawman BDIR Configuration Tom Markiewicz SLAC 07 January 2005 IR Hall Muon Wall Beam Dump Detector Photon Dump 4m tunnel with “Y”
NLC - The Next Linear Collider Project Backgrounds Update Tom Markiewicz SLAC LCWS Cornell 15 July 2003.
November 07, 2006 Global Design Effort 1 Beam Delivery System updates BDS Area leaders Deepa Angal-Kalinin, Hitoshi Yamamoto, Andrei Seryi Valencia GDE.
HPS Test Run Setup Takashi Maruyama SLAC Heavy Photon Search Collaboration Meeting Thomas Jefferson National Accelerator Facility, May 26-27,
Beam Delivery System Deepa Angal-Kalinin, Hitoshi Yamamoto, Andrei Seryi for BDS Area review video meeting March 28, 2006.
Global Design Effort Push-pull studies How to proceed LCWS07 June 1, 2007 at DESY Andrei Seryi for BDS Area leaders Deepa Angal-Kalinin, A.S., Hitoshi.
October 13, 2006 Global Design Effort 1 International Linear Collider Machine Detector Interface Materials for discussion at Engineering Forum: experiences.
ILC BCD Crossing Angle Issues G. A. Blair Royal Holloway Univ. London ECFA ILC Workshop, Vienna 14 th November 2005 Introduction BCD Crossing Angle Rankings.
October 31, BDS Group1 ILC Beam Delivery System “Hybrid” Layout 2006e Release Preliminary M. Woodley.
January 10, 2007M. Woodley (SLAC)1 ILC Beam Delivery System “Interim Working Assumption” 2006e Release European LC Workshop, January , Daresbury.
Proposed machine parameters Andrei Seryi July 23, 2010.
Global Design Effort Beam Delivery System => EDR LCWS07 June 2, 2007 at DESY Andrei Seryi for BDS Area leaders Deepa Angal-Kalinin, A.S., Hitoshi Yamamoto.
Backgrounds in the NLC BDS ISG9 December 10 – Takashi Maruyama SLAC.
Si D in 14mrad/14mrad/z=0 ILC T. Markiewicz/SLAC SiD Advisory Group 14 August 2006.
SB2009/ Low energy running for ILC International Workshop on Linear Colliders 2010 Andrei Seryi John Adams Institute 19 October 2010.
ILC Beam Delivery System / MDI Issues for LCC-phase (~
Global Design Effort ILC Crab Cavity Overview and requirements Andrei Seryi SLAC on behalf of ILC Beam Delivery and Crab-Cavity design teams Joint BNL/US-LARP/CARE-HHH.
GDE questions, including one or two IRs Grahame Blair, Tomo Sanuki, Andrei Seryi for WG4 Snowmass, CO, August 25, 2005 Grahame Blair, Tomo Sanuki, Andrei.
Philip Burrows Snowmass 2005: SiD Concept Plenary, 15/8/05 SiD and MDI issues Philip Burrows Queen Mary, University of London Thanks to: Toshiaki Tauchi,
Interaction Region & IR integration EDR Planning Tom Markiewicz/SLAC SLAC BDS Kick-Off-Meeting 13 October 2007.
October 20, 2006 Global Design Effort 1 ILC Interaction regions : The GDE perspective Talk based on several talks presented by BDS area leaders Andrei.
17 th November, 2008 LCWS08/ILC08 1 BDS optics and minimal machine study Deepa Angal-Kalinin ASTeC & The Cockcroft Institute Daresbury Laboratory.
November 07, 2006 Global Design Effort 1 Beam Delivery System / Machine Detector Interface BDS Area leaders Deepa Angal-Kalinin, Hitoshi Yamamoto, Andrei.
ILC MDI workshop January 6-8, 2004 PEP-II IR M. Sullivan 1 Interaction Region of PEP-II M. Sullivan for the ILC MDI workshop January 6-8, 2005.
BDS: 1 October 13, 2007 BDS KOM EDR planning discussion Andrei Seryi October 13, 2007.
1 O. Napoly ECFA-DESY Amsterdam, April 2003 Machine – Detector Interface : what is new since the TDR ? O. Napoly CEA/Saclay.
Global Design Effort CLIC-ILC BDS & MDI work Materials for discussion Daniel Schulte, Rogelio Tomas and Emmanuel Tsesmelis for CLIC team Andrei Seryi for.
Recent Studies on ILC BDS and MERIT S. Striganov APD meeting, January 24.
ILC-GDE Meeting Beijing Feb Effect of MDI Design on BDS Collimation Depth Frank Jackson ASTeC Daresbury Laboratory Cockcroft Institute.
11/15/20051 Radiation Protection Issues for ILC (not exhaustive) A. Fassò, N. Noriaki, H. Vincke Radiation Physics.
NLC - The Next Linear Collider Project Tor Raubenheimer Beam Delivery System Design Differences American Linear Collider Physics Meeting SLAC January 8.
L. Keller 3/18/02 Beam-Gas-Bremsstrahlung and Coulomb Scattering in the NLC Beam Delivery System Conditions for Calculation: 1. Program is DECAY TURTLE.
WG3a Sources Update Jim Clarke on behalf of WG3a GDE Meeting, Frascati, December 2005.
COMPENSATION OF DETECTOR SOLENOID FIELD WITH L*=4.1M Glen White, SLAC April 20, 2015 ALCW2015, KEK, Japan.
May 31, 2005Mike Hildreth – ATF 2005 Energy Spectrometry and ATF Components of the nano-BPM Test Program and Plans for Future Tests Mike Hildreth University.
Beam Delivery (wg4) update since Snowmass Andrei Seryi for WG4 GDE meeting December 8, 2005 Snowmass 2005 GDE Meeting at INFN-LNF.
Beam Delivery configuration materials to start discussion Andrei Seryi, Deepa Angal-Kalinin, Hitoshi Yamamoto BDS area GDE meeting at KEK, January 19-20,
IWLC10, 18 th -22 nd October10, CERN/CICG 1 Global Design Effort Updates to ILC RDR Beam Delivery System Deepa Angal-Kalinin & James Jones ASTeC, STFC.
BDS/MDI Deepa Angal-Kalinin Andrei Seryi AD&I Meeting, DESY, May 29, 2009.
1 O. Napoly ECFA-DESY Amsterdam, April 2003 Machine – Detector Interface : what is new since the TDR ? O. Napoly CEA/Saclay.
Dark Current in ILC Main Linac N.Solyak, A.Sukhanov, I.Tropin ALCW2015, Apr.23, 2015, KEK LCWS'15, Tsukuba, 04/2015Nikolay Solyak1.
ILC BDS Commissioning Glen White, SLAC AWLC 2014, Fermilab May 14 th 2014.
Positron Source for Linear Collider Wanming Liu 04/11/2013.
MAIN DUMP LINE: BEAM LOSS SIMULATIONS WITH THE TDR PARAMETERS Y. Nosochkov E. Marin, G. White (SLAC) LCWS14 Workshop, Belgrade, October 7, 2014.
Baseline BDS Design Updates Glen White, SLAC Sept. 4, 2014 Ichinoseki, MDI/CFS Meeting.
Design challenges for head-on scheme Deepa Angal-Kalinin Orsay, 19 th October 2006.
The design of the 2mrad extraction line Rob Appleby Daresbury Laboratory On behalf of the SLAC-BNL-UK-France task force ILC European Regional Meeting and.
1 Positron Source Configuration Masao KURIKI ILC AG meeting at KEK, 2006 Jan. Positron Source Configuration KURIKI Masao and John Sheppard  BCD Description.
Beam Delivery update Andrei Seryi December 12, 2005
Large Booster and Collider Ring
AD & I : BDS Lattice Design Changes
Radiation Physics requirements for the IR
Updates on IR and FF for super-B factory
Beam Delivery System Schedule at ILC2010
Extract from today’s talk given to DCB
BDS civil construction Single IR upgrade scenarios discussion
Interaction Region Design Options e+e- Factories Workshop
Fassò, N. Nakao, H. Vincke Aug. 2, 2005
HALLA APEL REPORT Yves Roblin Hall A colllaboration Meeting
Presentation transcript:

Beam Delivery, MDI related updates Andrei Seryi for BDS Area GDE/LCWS meeting at Bangalore March 10, 2006

10 Mar 06 2 Contents Will review several MDI related issues that were discussed after Frascati GDE meeting. Use slides from talks given at GDE meetings at KEK in January and Fermilab in February Muon walls and detector tolerance to muons Low E positron transport in BDS IR layout and radiation physics Concepts of upgrade to  and back to e+e- Extraction lines & linac orientation Updates on IR magnet designs Updates on crab cavity developments Missing bends and E upgrade

10 Mar 06 3 Muon walls BCD: two walls, 9m and 18m per branch, to reduce muon flux to less than 10muons/200bunches if collimate of the beam Predictions of halo ~1e-6 - 1e-5 Min one 5m wall needed for PPS Approach: consider installing single 5m wall, space in tunnel for full set The 5m wall allow to collimate 2e-5 before reaching 10  /200bunches Before the CCR can be considered => –ask Accel. Phys. Tech. System to evaluate predictions of halo population –ask Installation Tech. System to evaluate possibility to install additional wall if muon rate will exceed the limit –ask MDI panel to evaluate the 10  /200bunches detector tolerance No magnetic wall 5 m wall at S = -321m 18 m wall at S = -321m 250 GeV beam Lew Keller Muon Momenta from PC-3 Hitting 6.5 m Detector

10 Mar 06 4 Low energy e+ transport in BDS Layout (cost) & interference with detector and BDS are the main questions Options for e+ transport: –option 1: separate tunnel ~ km long going around larger crossing angle IR –option 2: going under the IR hall (the e+ beamline is 21 m under the IP beamlines). This is similar to TESLA (where dh was 17m) –option 3: going from tunnel of 1 st IR to tunnel of 2 nd IR and back Info on e+ beam (tbc) –Energy range considered: 250MeV-1GeV (5GeV also was discussed) –Power 20kW – 80kW –Energy spread 10% – 2.5%

10 Mar 06 5 e+ transport, option 1 (around IR) e+ tunnel Layouts by Fred Asiri et al.

10 Mar 06 6 e+ transport, option 2 (under IR hall)

10 Mar 06 7 e+ transport, option 3 (between tunnels)

10 Mar 06 8 A

9 e+ transport downstream diagn.

10 Mar Options of e+ transport Option 1 (around IR) –pro: minimal interference with considered options of IR layout (two or one IRs, different or same z) and IR operation –con: longer additional tunnel Option 2 (under IR hall) –pro: smaller length of additional tunnels –con: difficult construction; structural stability of IR hall; difficult to provide support for BDS magnets in region of tunnel separation; difficult maintenance; additional shielding of detector required, etc… Option 3 (between tunnels) –pro: minimize additional tunnel length –con: losses of e+ beam near IR => potential background; contradicts to the option of both IRs at the same z=0; if one of IRs is off, its detector could be accessed, but the downstream diagnostics cannot be accessed without switching off the linac; –require additional shielding of detector Option 1 suggested for baseline, 2&3 may be considered for AC

10 Mar Separate & single hall options, Rad. phys. and PPS Questions to study: wall thickness and location, packman thickness, tunnel to hall transition, etc Wall “Pacman” Fence optional

10 Mar IR design and Radiation safety design criteria IR design requires the radiation safety criteria to be defined Started the work on “ILC radiation guidance document” –beam containment policies and devices, conditions for occupancy For IR region, in particular, defines –Normal operation: dose less than 0.05 mrem/hr (integrated less than 0.1 rem in a year with 2000 hr/year) –Accidents: dose less than 25rem/hr and integrated less than 0.1 rem for 36MW of maximum credible incident (MCI) The team presently includes N.Mokhov, D.Cossairt, L.Keller, S.Rokni, A.Fasso and will be augmented with colleagues from all regions

10 Mar Hall with shielding wall For 36MW MCI, the concrete wall at 10m from beamline should be ~3.1m Wall 18MW loss on Cu target 9r.l \at s=-8m. No Pacman, no detector. Concrete wall at 10m. Dose rate in mrem/hr. 25 rem/hr 10m Alberto Fasso et al

10 Mar Self-shielding color scale is different in two cases 18MW on Cu target 9r.l at s=-8m Pacman 0.5m iron and 2m concrete 18MW on Cu target 9r.l at s=-8m Pacman 1.2m iron and 2.5m concrete 18MW at s=-8m: Packman dose at pacman external wall dose at r=7m Fe: 0.5m, Concrete:2m 120rem/hr (r=3.5m) 23rem/hr Fe: 1.2m, Concrete: 2.5m 0.65rem/hr (r=4.7m) 0.23rem/hr Adjusting pacman to reduce dose below 25rem/hr Desired thickness is in between of these two cases

10 Mar Self-shielding Improving tunnel-to- pacman transition, add iron in tunnel and model non-axial symmetrical case In next iteration will add iron in the marked corners and expect dose to reduce below 25rem/hr Proper “tunnel plug” can be designed 0.7m of Fe for last 5m of tunnel Iron color scale is different in two cases

10 Mar Muon gaps 18MW loss on a Cu target (9r.l) placed at s=-8m Pacman is 0.5m iron and 2m concrete With muon chambers (with gap ~5cm) Dose rate shown is in mrem/hr

10 Mar Preliminary conclusions from all cases Self-shielding detectors –issue of gaps (muon chambers) need to be solved –entrance of tunnel should be covered by iron as well –distance helps (fencing out the working detector) –if issue of gaps can be solved, ~3m pacman is needed to meet 25rem/hr MCI requirement –accurate model of detector is very important –studies will continue Non self shielding detector –concrete wall at 10m from beamline should be ~3.1m

10 Mar Upgrade from e+e- to  and back to e+e- Assume that 25mrad is needed for  to attain its max potential Reversibility of upgrade may be essential –e.g. e+e- run =>  run => E upgrade and next e+e- run Consider concept for 20mrad or 14mrad IR upgrade

10 Mar Baseline layout 20mrad IR and 2mrad IR Grid size: 100m * 5m (Beamline is not placed near external walls, as suggested above)

10 Mar mr IR

10 Mar See notes on next page 20mr => 25mr

10 Mar Upgrade of 20mr to  25mr and back Install bend after energy collimator of modify E-coll bend to create additional 2.5mrad –Will need to study if this affects collimation efficiency and whether this is an issue for  Pink area show tunnels that need to be built for  in the upgrade or from start Detector and IP moved by about 1.8m, FF elements moved Build new ~0.25km gas dump followed by water dump for  ( next slide ) in a new tunnel, do not dismantle either the water dump for e+e- or extraction line If the  beam dump and new tunnel need to be much longer, the positron transfer tunnel should go above the projected path of  dump In back conversion  to e+e-, move FF beamline and detector back, continue to use e+e- water dump.

10 Mar Assumed this dump for  (feasibility to be studied)

10 Mar mr => 25mr additional angle is 5.5mrad and detector need to move by about 4.2m

10 Mar Upgrade of 14mr to  25mr and back Additional comments Tunnel in FF area may need to be wider The gg dump is in separate tunnel – may ease radiation issues and upgrade back to e+e-

10 Mar Extraction line and linac angles Extraction line study –Detailed studies of extraction lines is ongoing. –Synchrotron radiation of disrupted beam in chicanes reach 0.76MW for 1TeV CM in 2mrad beamline. Protection collimators with up to 1TGy/yr peak dose which can severely limit the lifetime even for metals (N.Mokhov, A.Drozhdin et al) Linac angles are fixed to 20mrad after discussion at KEK GDE Areas meeting in January and following CCR (Configuration Change Request) by the Executive Committee

10 Mar QD0 SD0 QF1 SF1 Q,S,QEXF1 Disrupted beam & Sync radiations Beamstrahlung Incoming beam 60 m Shared Large Aperture Magnets Rutherford cable SC quad and sextupole pocket coil quad 2mrad IR: Fermi and possibly Saclay will look on feasibility and cost estimates

10 Mar Progress on 14mrad solution, BNL Brief summary from Brett Parker: Working on support structure, cryostat design, verified space for He-II cooling, will start modeling temperature distribution with E deposition calculations Close to winding a short sectupole (SD0 prototype) on top of the OC0 coil we have already wound. Integrated both DC and pulsed (1ms) heating elements into the coil to directly measure how much energy deposition (mJ/gm) is needed to cause a quench. Will measure the magnetic centers for the octupole and sextupole windings Final QT assembly with the active shield coil in place cancellation of the external field with a shield coil has been successfully demonstrated at BNL at the end of 2005

10 Mar (20)mrad, BNL

Model of 3.9GHz deflecting (crab) cavity designed by Fermilab Collaboration is being formed to work on ILC crab cavity systems: Fermilab, Daresbury, SLAC, … The 3.9GHz deflecting cavity designed at Fermilab. Several simplified models have been manufactured. Complete design with all couplers exist now. Design is being verified with various tools including parallel codes (see next page), and then a prototype will be built. The phase stabilization system is being designed.

Parallel Electromagnetic Codes - SLAC Parallel codes capable of simulating complex 3D cavities in time and frequency domains were applied to the optimization of HOM damping in ILC Low-Loss cavity. The plan is to apply the same capabilities to the design of the 3.9 GHz crab cavity. ILC Low-Loss Cavity HOM Damping (Omega3P) Wakefields (T3P)

10 Mar At 500GeV CM will install 50% or even less number of bends to cut the cost. These bends need to be installed after the energy upgrade. Bends will be split and arranged in strings so that decreasing the energy much below the nominal 500GeV CM will be done by switching off the strings. Example shows one of possible configuration in the FF part (Y.Nosochkov) Missing bend strategy at 500GeV CM

10 Mar Summary We discussed updates on several MDI related design issues Important issues to be focused on: –Taking into account real life constraints, –how to build a consensus toward two or one IRs? –… two or one detector? –… push-pull or normal? –… how to ensure that community support is not decreased if the number of IRs and detectors goes to minimum?